Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JAN 2025 #bangaloremetro #bmrcl
Blue line updates from Airport to Hebbal. Recorded Date : 11-JAN-2025
Phase 2B - Airport to Hebbal
***********************************************
JANUARY 2025 Updates
Civil Contractor : PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
Piling Works Happening and Pier casting Picking up pace.
Package 2 :
Kodigehalli Station :- Pier casting in Progress.
Jakkur Cross Station :- PF and CC Beam casting in Progress.
Jakkur Plantation Station : Possible Future Station
Yelahanka / Kogilu Cross Station :- U Girder and I-Girder Erection in Progress
Bagalur Cross Station : PF and CC Slab casting in Progress
Package 3 :
Bettahalasuru Station : Unsure
Chikkajala...
Просмотров: 7 545

Видео

Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JAN 2025 #bmrcl #bangaloremetro
Просмотров 4 тыс.День назад
Blue line updates from Hebbal to K R Pura. Recorded Date : 05-JAN-2025 Phase 2B - Hebbal to K R pura January 2025 Updates Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Stations in the stretch : Package 1 : Kasturinagar St...
Blue line | ORR METRO | K R Puram to Silkboard JAN 2025 Updates #bmrcl #BengaluruMetro
Просмотров 8 тыс.День назад
Blue line | ORR METRO | K R Puram to Silkboard junction JAN 2025 Updates Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ JANUARY 2025 Updates Recorded Date : 05-JAN-2025 Civil Contractor : PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement PKG2 - Shankaranar...
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: DEC 2024 #bmrcl #bangaloremetro
Просмотров 3,7 тыс.Месяц назад
Blue line updates from Hebbal to K R Pura. Recorded Date : 08-DEC-2024 Phase 2B - Hebbal to K R pura DECEMBER 2024 Updates Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Stations in the stretch : Package 1 : Kasturinagar S...
Blue line | ORR METRO | K R Puram to Silkboard DEC 2024 Updates #bmrcl #bangaloremetro
Просмотров 12 тыс.Месяц назад
Blue line | ORR METRO | K R Puram to Silkboard junction DEC 2024 Updates Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ DECEMBER 2024 Updates Recorded Date : 08-DEC-2024 Civil Contractor : PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement PKG2 - Shankarana...
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || DEC 2024 #bangaloremetro #bmrcl
Просмотров 9 тыс.Месяц назад
Blue line updates from Airport to Hebbal. Recorded Date : 07-DEC-2024 Phase 2B - Airport to Hebbal DECEMBER 2024 Updates Civil Contractor : PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Package 2 : Kodigehalli Station :- Pier casting in Progress. Jakkur Cross Station :- PF and CC Beam cas...
Blue line | ORR METRO | K R Puram to Silkboard NOV 2024 Updates #bmrcl #bangaloremetro
Просмотров 9 тыс.2 месяца назад
Blue line | ORR METRO | K R Puram to Silkboard junction NOV 2024 Updates Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ NOVEMBER 2024 Updates Recorded Date : 10-NOV-2024 Civil Contractor : PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement PKG2 - Shankarana...
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: Nov 2024 #bmrcl #bangaloremetro
Просмотров 3,9 тыс.2 месяца назад
Blue line updates from Hebbal to K R Pura. Recorded Date : 10-NOV-2024 Phase 2B - Hebbal to K R pura NOVEMBER 2024 Updates Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Stations in the stretch : Package 1 : Kasturinagar S...
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || NOV 2024 #bangaloremetro #bmrcl
Просмотров 9 тыс.2 месяца назад
Blue line updates from Airport to Hebbal. Recorded Date : 08-NOV-2024 Phase 2B - Airport to Hebbal NOVEMBER 2024 Updates Civil Contractor : PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Package 2 : Kodigehalli Station :- Pier casting in Progress. Jakkur Cross Station :- PF and CC Beam cas...
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || OCT 2024 #bangaloremetro #bmrcl
Просмотров 8 тыс.3 месяца назад
Blue line updates from Airport to Hebbal. Recorded Date : 13-OCT-2024 Phase 2B - Airport to Hebbal OCTOBER 2024 Updates Civil Contractor : PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Package 2 : Kodigehalli Station :- Pier casting in Progress. Jakkur Cross Station :- CC Beam casting in ...
Blue line | ORR METRO | K R Puram to Silkboard OCT 2024 Updates #bmrcl #bangaloremetro
Просмотров 13 тыс.3 месяца назад
Blue line | ORR METRO | K R Puram to Silkboard junction OCT 2024 Updates Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ OCTOBER 2024 Updates Recorded Date : 12-OCT-2024 Civil Contractor : PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement PKG2 - Shankaranar...
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: OCT 2024 #bmrcl #bangaloremetro
Просмотров 10 тыс.3 месяца назад
Blue line updates from Hebbal to K R Pura. Recorded Date : 12-OCT-2024 Phase 2B - Hebbal to K R pura OCTOBER 2024 Updates Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Stations in the stretch : Package 1 : Kasturinagar St...
Blue line | ORR METRO | K R Puram to Silkboard SEP 2024 Updates #bmrcl #bangaloremetro
Просмотров 8 тыс.4 месяца назад
Blue line | ORR METRO | K R Puram to Silkboard junction SEP 2024 Updates Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ SEPTEMBER 2024 Updates Recorded Date : 08-SEP-2024 Civil Contractor : PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement PKG2 - Shankaran...
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: SEP 2024 #bmrcl #bangaloremetro
Просмотров 3,2 тыс.4 месяца назад
Blue line updates from Hebbal to K R Pura. Recorded Date : 08-SEP-2024 Phase 2B - Hebbal to K R pura SEPTEMBER 2024 Updates Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Stations in the stretch : Package 1 : Kasturinagar ...
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || SEP 2024 #bangaloremetro #bmrcl
Просмотров 11 тыс.4 месяца назад
Blue line updates from Airport to Hebbal. Recorded Date : 06-SEP-2024 Phase 2B - Airport to Hebbal SEPTEMBER 2024 Updates Civil Contractor : PKG2 - NCC LTD - 11.678 KM PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion. Piling Works Happening and Pier casting Picking up pace. Package 2 : Kodigehalli Station :- Pier casting in Progress. Jakkur Cross Station :- CC Beam casting i...
Blue line | ORR METRO | K R Puram to Silkboard AUG 2024 Updates #bmrcl #bangaloremetro
Просмотров 22 тыс.5 месяцев назад
Blue line | ORR METRO | K R Puram to Silkboard AUG 2024 Updates #bmrcl #bangaloremetro
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: AUG 2024 #bmrcl #bangaloremetro
Просмотров 4,6 тыс.5 месяцев назад
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: AUG 2024 #bmrcl #bangaloremetro
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || AUG 2024 #bangaloremetro #bmrcl
Просмотров 21 тыс.5 месяцев назад
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || AUG 2024 #bangaloremetro #bmrcl
Silk board Junction loops and ramps - AUGUST 2024 Updates #bmrcl #bangaloremetro #silkboard
Просмотров 6 тыс.5 месяцев назад
Silk board Junction loops and ramps - AUGUST 2024 Updates #bmrcl #bangaloremetro #silkboard
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUL 2024 #bmrcl #bangaloremetro
Просмотров 3,6 тыс.6 месяцев назад
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUL 2024 #bmrcl #bangaloremetro
Blue line | ORR METRO | K R Puram to Silkboard JUL 2024 Updates #bmrcl #bangaloremetro
Просмотров 9 тыс.6 месяцев назад
Blue line | ORR METRO | K R Puram to Silkboard JUL 2024 Updates #bmrcl #bangaloremetro
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JUL 2024 #bangaloremetro #bmrcl
Просмотров 10 тыс.6 месяцев назад
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JUL 2024 #bangaloremetro #bmrcl
Blue line | ORR METRO | K R Puram to Silkboard JUN 2024 Updates #bmrcl #bangaloremetro
Просмотров 15 тыс.7 месяцев назад
Blue line | ORR METRO | K R Puram to Silkboard JUN 2024 Updates #bmrcl #bangaloremetro
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUN 2024 #bmrcl #bangaloremetro
Просмотров 2,8 тыс.7 месяцев назад
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUN 2024 #bmrcl #bangaloremetro
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JUN 2024 #bangaloremetro #bmrcl
Просмотров 17 тыс.7 месяцев назад
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || JUN 2024 #bangaloremetro #bmrcl
Reach 3C | Green Line Extension | Nagasandra Station to BIEC MAY 2024 Updates #bangaloremetro #bmrcl
Просмотров 2,5 тыс.7 месяцев назад
Reach 3C | Green Line Extension | Nagasandra Station to BIEC MAY 2024 Updates #bangaloremetro #bmrcl
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || MAY 2024 #bangaloremetro #bmrcl
Просмотров 10 тыс.8 месяцев назад
Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || MAY 2024 #bangaloremetro #bmrcl
Blue line | ORR METRO | K R Puram to Silkboard MAY 2024 Updates #bmrcl #bangaloremetro
Просмотров 9 тыс.8 месяцев назад
Blue line | ORR METRO | K R Puram to Silkboard MAY 2024 Updates #bmrcl #bangaloremetro
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: MAY 2024 #bmrcl #bangaloremetro
Просмотров 4,5 тыс.8 месяцев назад
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: MAY 2024 #bmrcl #bangaloremetro
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: APR 2024 #bmrcl #bangaloremetro
Просмотров 4,2 тыс.9 месяцев назад
Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: APR 2024 #bmrcl #bangaloremetro

Комментарии

  • @AbzFusion
    @AbzFusion День назад

    Will the heavy truck vehicle not hit when passing below metro some sections? What is limit??

  • @shreyass5664
    @shreyass5664 2 дня назад

    Godrej company has got the order for station finishing work on the entire blue line stations 👍

  • @madhusudhanv4684
    @madhusudhanv4684 2 дня назад

    On Yelahanka station there are 2 u girders at the same side, is it for pocket track 23:01?

    • @SunilHP
      @SunilHP 2 дня назад

      @@madhusudhanv4684 yes. Rhs + pocket track

    • @madhusudhanv4684
      @madhusudhanv4684 2 дня назад

      @SunilHP ok thanks for information

  • @xdfdf_
    @xdfdf_ 2 дня назад

    When will phase 3 orange and grey lines construction start

    • @SunilHP
      @SunilHP 2 дня назад

      There is a lot of time for that. Now DDC Tenders are called and while the designs are being readied, supporting Geotechnical investigation are being done by multiple companies all along ORR. all these will form the tender document for Construction tenders.

  • @StonusIndia
    @StonusIndia 3 дня назад

    Should be operational by 2029. That is realistic

  • @shreyass5664
    @shreyass5664 3 дня назад

    @sunil one idea can u try once to make a single video of the entire blue line from silk board to airport it would be a different experience to see how the progress is made in the entire stretch 😊.

    • @SunilHP
      @SunilHP 3 дня назад

      @@shreyass5664 not possible since end to end takes 1.5 hours and by the time I reach hebbal itself traffic would have started and no progress can be seen meaningfully. My general thing is to shoot between 7 to 8 with the exception of fogs. Also it becomes tiresome with journey to airport, airport to hebbal to kr pura to silk board and finally silk board to home

    • @shreyass5664
      @shreyass5664 3 дня назад

      @SunilHP sure then can u join the three videos and make it as one just to get a different experience 🙂

  • @poms97
    @poms97 3 дня назад

    Not much progress near IAF, near Yelahanka station and after Jakkur but otherwise good progress

    • @SunilHP
      @SunilHP 3 дня назад

      @@poms97 right

    • @tejaswinisrinivasa5100
      @tejaswinisrinivasa5100 3 дня назад

      Isn’t this where it goes underground?

    • @poms97
      @poms97 3 дня назад

      @@tejaswinisrinivasa5100 Near IAF it goes underground due to IAF restrictions for overhead metro

    • @SunilHP
      @SunilHP 3 дня назад

      @@tejaswinisrinivasa5100 Right, along the AF boundary the line goes below ground and currently secant pile work going on for the UG part since it is cut and cover method

  • @natarajreddy5505
    @natarajreddy5505 4 дня назад

    We have good companies here In Our bangalore city but bmrcl is very slow in work,chennai,hyderabad kochi compared we are too slow

  • @natarajreddy5505
    @natarajreddy5505 4 дня назад

    Due to some unknown issues Bmrcl is very slow in completing Work,debris not cleared since one Year near many spots in outer ring road

  • @shreyass5664
    @shreyass5664 4 дня назад

    In 2024 tom tom traffic survey BLR no more the first congested city in india.👍😊

  • @Dhroolsyou
    @Dhroolsyou 4 дня назад

    What is the use of pocket track near kodibeesanahalli?

    • @SunilHP
      @SunilHP 4 дня назад

      train reversal, emergency use when a train breaksdown to push it in to clear the main line for ops and so on.

  • @Dhroolsyou
    @Dhroolsyou 4 дня назад

    Hi bro you can try giving monthly updates of the entire section of pink line 1) Kalena Agrahara to Tavarekere 2)Taverekere to MG Road 3) MG Road to Nagawara, and also why is the construction of kodigehalli stn getting delayed

  • @rakshithkumarms9450
    @rakshithkumarms9450 4 дня назад

    Now the thing is do they really open this route by the end of 2026?😊

    • @SunilHP
      @SunilHP 4 дня назад

      Only time will tell.

  • @arunshekhar3915
    @arunshekhar3915 4 дня назад

    are you able to view workers working day and night to complete metro construction

  • @Naman_2309
    @Naman_2309 4 дня назад

    no sufficient workers.... #delayed

  • @gamerartificial7208
    @gamerartificial7208 4 дня назад

    How 24:03 and 24:00 is so different because how suddenly foggy became unfoggy is it a scam

    • @SunilHP
      @SunilHP 4 дня назад

      What Scam can it be. ? they are shot at different times. One part in the morning since as we approach city , we cannot shoot without getting in traffic and the Airport to Kogilu cross is shot in the afternoon.

    • @gamerartificial7208
      @gamerartificial7208 4 дня назад

      @@SunilHP ok ok sorry bro 😔

  • @shreyass5664
    @shreyass5664 4 дня назад

    The next three years 2025,2026,2027 will see a big game changer in public transportation in BLR ❤.Yellow line,pink line,blue line will open around 175kms will become operational😊.BLR will definetly come out of this traffic issue in few months and we can see that BLR name will not be in the tom tom traffic index list😊👍

    • @arunshekhar3915
      @arunshekhar3915 4 дня назад

      Are you sure within 2027 all these lines will be totally operational 😂

    • @shreyass5664
      @shreyass5664 4 дня назад

      ​@@arunshekhar3915 yellow line ,pink line and blue line will open.Around 170kms of metro line will be ready 😊👍

    • @madhur3737
      @madhur3737 4 дня назад

      Yellow line 19km-2025, Pink line 21km -2026,Blue line 58 km -2027 mostly operate but lack of coaches availability leads to postponed to 2028...

    • @shreyass5664
      @shreyass5664 3 дня назад

      @@madhur3737 BEML has already manufactured prototype train.I think there will not be much delay like the yellow line.In 2026 atleast 1 section of the blue line will open for sure.Let us hope as soon as possible all lines opens to public.👍🙂

    • @shining7287
      @shining7287 3 дня назад

      Orange Line survey is also in under progresss

  • @gamerartificial7208
    @gamerartificial7208 4 дня назад

    And what is cross field run taxiway

    • @SunilHP
      @SunilHP 4 дня назад

      KIA Airport is planning a Taxiway on the West Side connecting both runways

  • @sudhisubbu5852
    @sudhisubbu5852 4 дня назад

    @SunilHP can tell me why is the metro line splitting as they approach the stations and stations in this section are being built differently too can you tell me why is that thank you

    • @SunilHP
      @SunilHP 4 дня назад

      The stations from Kodigehalli to Doddajala are with Island platform unlike the regular stations which have platform on both sides. This was done with the low footfall in mind in these stations and cost savings since lifts , escalators and other infra can be half the original. So the line splits as it approaches the stations and then merges back as it moves away from the station.

    • @sudhisubbu5852
      @sudhisubbu5852 3 дня назад

      @@SunilHP ohhh cool thanks

  • @xdfdf_
    @xdfdf_ 4 дня назад

    Is chikkajala metro station being built or have they modified the pillars to make it just for track???

    • @SunilHP
      @SunilHP 4 дня назад

      For now only the tracks

    • @xdfdf_
      @xdfdf_ 3 дня назад

      ​@@SunilHPdoes that mean that chikkajala station will be built??

  • @sathyamanikanta2784
    @sathyamanikanta2784 4 дня назад

    Nice to see this video's.....but Yellow line operation when???

    • @SunilHP
      @SunilHP 4 дня назад

      Probably April 2025

    • @sathyamanikanta2784
      @sathyamanikanta2784 4 дня назад

      @SunilHP Wat...it was supposed to come in 2023 First quarter.... Now postponed to April ... someone tweeted it 7 jan 2025 Now April In this...way...Hebbal Airport route will complete by 2030

    • @SunilHP
      @SunilHP 4 дня назад

      @@sathyamanikanta2784 2023 I dont know who told , it was never that after the CRRC Factory in Sricity went into limbo due to Geo Political crisis and the fallout. Having said that Now second trains is getting shipped , once speed and collision avoidance trials are done and RSDO Certifies rolling stock, BMRCL will have to apply for CMRS Certification and line opening. So this time frame is strictly for certification activities . On the blue line we cannot extrapolate based on what has happened in Yellow line. Hopefully by then BEML starts delivering trains.

  • @ayushgarg7033
    @ayushgarg7033 5 дней назад

    NCC progress is literally stopped in package 2 also, any reason why? It seems they are already 1 yr behind

    • @SunilHP
      @SunilHP 5 дней назад

      No Ayush, they are doing just fine. Jakkur Cross station they have covered fine, almost all down line rebar are up between hebbal and kempapura . Yelahanka station U girders are started. So basically they have some tall piers requiring 3 stage cast between Jakkur cross and kodigehalli and hence takes time.

    • @ayushgarg7033
      @ayushgarg7033 4 дня назад

      @SunilHP I am saying based on the tracker sir, I believe they have to finish civil work by 2025 end

    • @SunilHP
      @SunilHP 4 дня назад

      @@ayushgarg7033 ok

  • @AbhinavPathak17
    @AbhinavPathak17 5 дней назад

    someone was saying this will be ready by 2025 end, seems like 2026 end and operational by 2027 end

    • @SunilHP
      @SunilHP 5 дней назад

      ok

    • @rishk1
      @rishk1 5 дней назад

      operational by the end of 2026

  • @shreyass5664
    @shreyass5664 5 дней назад

    Thanks for the airport line video 👍

  • @balarajuc5048
    @balarajuc5048 5 дней назад

    Thanks lot for sharing , I lived at Doddnekundi for so long and now outside bangalore and great to see that junction , thanks million . great work .

  • @vijethkumar6549
    @vijethkumar6549 5 дней назад

    I guess there won't be much progress in Airforce region due to Airshow. Also what is the update on OWG. Has SWR given the permission to go ahead?

    • @SunilHP
      @SunilHP 5 дней назад

      Yes, In that work I am sure they wll ask to shut down work, like they did last time . Didnt even allow piling near Hebbal for some weird reasons. OWG i think is a go ahead since NCC has completed piling on both sides now.

    • @gamerartificial7208
      @gamerartificial7208 4 дня назад

      What is owg​@@SunilHP

    • @SunilHP
      @SunilHP 4 дня назад

      @gamerartificial7208 Open Web Girder , which Railway mandates over railway lines.

  • @gamerartificial7208
    @gamerartificial7208 6 дней назад

    No update about airport

    • @SunilHP
      @SunilHP 6 дней назад

      @gamerartificial7208 mostly this weekend. Unable to make time and plus early morning fogs are another challenge

    • @SunilHP
      @SunilHP 5 дней назад

      pls watch. ruclips.net/video/_1lPHd87_mM/видео.html

  • @chethank1181
    @chethank1181 6 дней назад

    Since Kempapura is a interchange station will it going to be side by side platform interchange or above and below platforms like in Majestic and Jayadeva?

    • @SunilHP
      @SunilHP 6 дней назад

      This is going to be a little unique station with the structure on three legged portal piers . the outer lines will be blue line and the middle lines will be future Orange line.

  • @shreyass5664
    @shreyass5664 7 дней назад

    Once this entire Metro and suburban rail opens to public, 25lakhs people will use metro and 25l sub urban train ,definitely BLR will come out of this traffic issue in the next 5 yrs by 2030.😊👍

  • @KarthikR-i3s
    @KarthikR-i3s 7 дней назад

    @sunil hp pls upload hebbal to kia route upload

    • @SunilHP
      @SunilHP 7 дней назад

      Hi Karthik. Yes by this weekend. Held up and unable to make time so.

    • @SunilHP
      @SunilHP 5 дней назад

      ruclips.net/video/_1lPHd87_mM/видео.html

  • @shreyass5664
    @shreyass5664 7 дней назад

    @sunil when will u be posting the airport to hebbal video eagerly waiting 😊

    • @SunilHP
      @SunilHP 7 дней назад

      Hopefully this weekend. Held up due to work.

    • @SunilHP
      @SunilHP 5 дней назад

      ruclips.net/video/_1lPHd87_mM/видео.html

  • @KarthikR-i3s
    @KarthikR-i3s 8 дней назад

    Waiting for hebbal to KIA route video

  • @rprahalad396
    @rprahalad396 8 дней назад

    Why still airport to hebbal jan 2025 update has not come?

    • @SunilHP
      @SunilHP 8 дней назад

      Not yet shot . Held up due to work. Mostly this week

  • @ಗೌತಮ್ಗೌಡ
    @ಗೌತಮ್ಗೌಡ 8 дней назад

    Waiting for Airpot to Hebbal

  • @sampathnaidu2461
    @sampathnaidu2461 8 дней назад

    BY 2035 WE WILL GET AIRPORT METRO 😮

  • @haneesh__1
    @haneesh__1 9 дней назад

    Practically in this current rate, when could it possibly start operations?

    • @SunilHP
      @SunilHP 8 дней назад

      This section between Hebbal to KR Pura will be the last since it is complex with 3 split flyovers at Kalyan nagar, Nagawara , Veerannapalya and 1 Split underpass at Hennur. So in all probabilities 2027 end.

  • @gamerartificial7208
    @gamerartificial7208 9 дней назад

    Where is airport wala video

    • @SunilHP
      @SunilHP 8 дней назад

      Yet to Shoot

  • @mallikarjunb2006
    @mallikarjunb2006 9 дней назад

    12:38 Any idea when the high tension line will be removed ?

    • @SunilHP
      @SunilHP 8 дней назад

      Hopefully sooner. KPTCL is doing the same on BMRCL Behalf

  • @KarthikR-i3s
    @KarthikR-i3s 9 дней назад

    When u are posting hebbal to KIA route pls let me know

    • @SunilHP
      @SunilHP 9 дней назад

      @@KarthikR-i3s sure.

  • @ayushgarg7033
    @ayushgarg7033 9 дней назад

    Ncc is the contractor for this stretch, I thinkthey have enough experience to speed it up

    • @SunilHP
      @SunilHP 9 дней назад

      Right. But for that lapse and the slowdown it caused, they would have been in Good shape too. Anyways its their doing trying to cut corners on safety. Touch wood now they seem to be getting back to normalcy. Hopefully this time they do it properly

  • @Vishwajeet0723
    @Vishwajeet0723 9 дней назад

    Great video, really wish this becomes operational by 2027 December.

  • @Iamprasannar
    @Iamprasannar 9 дней назад

    there are no pillars also for possible bettahalasuru future station, so its almost 100% scapped

  • @shreyass5664
    @shreyass5664 9 дней назад

    Finally today titagarh company manufactured yellow line 1st metro train it will reach blr by 10th 😊👍.By march end or April yellow line will open to public then metro length in the city will extend to 97kms 👍👍

  • @rajds328
    @rajds328 10 дней назад

    BRING BJP, SAVE KARNATAKA

    • @NomanSabit000
      @NomanSabit000 9 дней назад

      40%

    • @rajds328
      @rajds328 9 дней назад

      @NomanSabit000 this ur IQ level. Right? Only 40% 😀😀

    • @NomanSabit000
      @NomanSabit000 9 дней назад

      @@rajds328 it’s shameful that you don’t have any idea how IQ is calculated

  • @msrmaddymech
    @msrmaddymech 10 дней назад

    Thanks for the post. Captures the reality that we should stop dreaming of a ride to the airport on metro by 27.

  • @ssatishkumar1981
    @ssatishkumar1981 10 дней назад

    Awesome coverage

  • @rakshithkumarms9450
    @rakshithkumarms9450 10 дней назад

    This stretch works are as slow as nor still slower than tortoise 😂

  • @sarvodaydutta1905
    @sarvodaydutta1905 10 дней назад

    *Work is painfully slow where work should go on a full throttle....* *Phase - 3 and 3A will also be as slow and painful as Phase - 2, 2A and 2B are....*

  • @baijalashok
    @baijalashok 10 дней назад

    Why have the up and down lines been split on two sides of the road near Hebbal station

    • @SunilHP
      @SunilHP 10 дней назад

      the median is kept for future ORR West line, so that Kempapura station can accomodate both Blue and Orange line and allows for interchange too.

  • @sathyamanikanta2784
    @sathyamanikanta2784 10 дней назад

    2030 December