Blue line | ORR METRO | K R Puram to Silkboard OCT 2024 Updates
HTML-код
- Опубликовано: 31 дек 2024
- Blue line | ORR METRO | K R Puram to Silkboard junction OCT 2024 Updates
Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM
ಬಿಎಂಆರ್ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್ ಜಂಕ್ಷನ್ನಿಂದ ಕೆ.ಆರ್.ಪುರ | ಒಆರ್ಆರ್ ಮೆಟ್ರೊ
***********************************************
OCTOBER 2024 Updates
Recorded Date : 12-OCT-2024
Civil Contractor :
PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement
PKG2 - Shankaranarayana Constructions PVT ltd - 9.744 KM
ಸಿಲ್ಕ್ ಬೋರ್ಡ್ನಿಂದ ಕಾಡುಬೀಸನಹಳ್ಳಿಯವರೆಗಿನ ಪ್ಯಾಕೇಜ್ -1 ನಿರ್ಮಾಣ ಗುತ್ತಿಗೆಯನ್ನು ಆಫ್ಕಾನ್ಸ್ ಸಂಸ್ಥೆ ಪಡೆದಿದ್ದರೆ,
ಕಾಡುಬೀಸನಹಳ್ಳಿಯಿಂದ ಬೈಯಪ್ಪನಹಳ್ಳಿಯವರೆಗಿನ ಎರಡನೇ ಪ್ಯಾಕೇಜ್ನ ಗುತ್ತಿಗೆಯನ್ನು ಶಂಕರನಾರಾಯಣ ಕನ್ಸ್ಟ್ರಕ್ಷನ್ ಪಡೆದಿದೆ.
Stations in the stretch :
Central Silk Board Station ( Interchange with Yellow line ) : CC Connector erection and Arm casting in progress
HSR layout Station : All pier cast up to concourse level. CC Connector erection in progress
Agara Station : CC and PF arms being erected. U Girder erection has begun.
Ibbalur Station : All pier cast up to concourse level.
Bellandur Station : Core Works on Median Done. Secondary piers on sides being done.
Kadubeesanahalli Station : Core Works on Median Done. Secondary piers on sides being done.
Kodibeesanahalli Station : Core Works on Median Done. Secondary piers on sides being done.
Marathahalli Station : Concourse and platform beam casting in progress.
ISRO Station : CC and PF Connector erection in progress
Doddanekundi Station : CC and PF Connector erection in progress
DRDO sports complex Station : Core Works on Median Done. Secondary piers on sides being done.
SaraswathiNagar Station ( Mahadevpura ): Core Works on Median Done. Secondary piers on sides being done.
K R Pura Station ( Interchange with Purple line ) : Concourse and platform beam being cast
#bmrcl #bangaloremetro #ORRMetro
------------------------------
Track: Dance With Me - Next Route [Audio Library Release]
Music provided by Audio Library Plus
Watch: • Dance With Me - Next R...
Free Download / Stream: alplus.io/danc...
------------------------------
Man loved your summary, i appreciate your effort in making videos and improving the videos. Especially the summary you started adding is genius. Keep it up, one day u will have more enthu subscribers.
This month green line nagsandra to madavra will open then entire purple line and green is open to public.Next 3 months yellow line will open then pink,blue,orange,grey and red line will open.Total 250kms of metro track and 150kms of suburban train line and 280kms of circular railway is planned all will be ready bro 2030. Definetly BLR will come out of this traffic issue it is already improved from 2 to 6th position also AI traffic signal is in use. Let us help the city to bring back its glory by contributing 1% change in our driving habits like following lane discipline and help the city which gave life to many people.BLR is 😊❤
Keep dreaming for yellow line
@@ayushgarg7033 yellow line is opening in Jan 2025 with 3 trains like partial opening after that every month 2 trains will come slowly the line will become steady 👍
Yeah. Correct. In 2 yrs when the yellow and pink line opens only we can see a lot of improvement. Atleast in all these blockers and challenges, BMRCL has come this much right 👏🏿. That too being in southern most side of India, rather Delhi being Northern most and for DMRCL getting funds and approvals are easy, we can't compare our BMRCL with DMRCL. Also challenges BMRCL faced are unique and not in their hands, still they are trying their best to overcome those 👏🏿🙏🏿. Namma BMRCL, namma Bengaluru ❤️. Namma swarga 🙏🏿
@@shreyass5664 I think for the first few months, it will be unpopular as the headway is going to be more like 30 min. It's not really helpful for office goers. Only after the late next year, we might see some real practical usage of the yellow line. Hopefully then can speed up the trainsets delivery.
@@rajivkrishnatr yes first bmrcl will start with 3 trains layer every month 2 trains will be added. Let us hope that all trains get manufacture asap and start operations
This line(silk board to kr puram) will open first, airport to kr puram will take time
Yes. both are independent of each other and ORR line if completed should open without waiting for airport line. Will address a lot of traffic issues on ORR between KRP and SB and also vital link between Purple line , Yellow line. Many people from South who have to go to Majestic for interchange on green line can now do so at RV Road -> Silkboard -> KR Pura
@@SunilHPBut why no progress in depot section. Can the line open from bellandur to krpuram without it?
@@Ash-jh3gh All piers are up on depot line, many portal beams cast and pier cap cast. Since this is tucked behind the tech park with difficulty in transporting U girders, they will use all i-giders and they are being cast there itself.
We are looking at a minimum of 5 years more looking at the AFCONS part itself. Atlast seeing some progress from that LG in HSR layout but the silkboard, sarjapur signal and marathahalli parts of this phase will be a big pain
In this phase i think KR ORR will open only in late 2026.😢
2027. Or 2028
will there be benniganahalli station on blue line along with purple line?
No
@@dheerajp2285 so blue line passengers can only interchange at kr pura station
Yes.
Afcons struggling to cope on delivery (iblur to silk board). Hope they speed up as they have IPO funds.Will they complete by 2026 dec?
Bro when will blue line get completed?
Wow, really nice job. What are ur thoughts on the progress by Afcon, are they on the right track to finish the work soon?
They are. station works have picked up pace. Except for Iblur station all are going fine.
@sunilhp do you know why did maddyvoldy leave twitter?
Can you provide station wise work update chart?
please refer to the updates by Maddy. he has station info in great detail. Probably next time will try to add here
@@SunilHPWhere to see his updates ? Seems like his X account is deleted?
@@milindsrikantamurthy you can see the data here on the sheets.
docs.google.com/spreadsheets/d/1RLAjKG9OfwtPkf0LkqyBbg6RUcnaLCHSMDo6UvBpJJ8/edit?usp=sharing
Is the space on the curve between blue and pink line enough ? When seeing directly I always feel how will the train manage in that small gap 🫣
@@dhanushna1707 it is sufficient. If you mean near mahadevpura where blue and purple line cross. Already slab is cast here too
Thanks for covering a detailed video. This proves that BMRCL and Karnataka government have left the work unattended and are least bothered of completing on time. Seriously bunch of shameless buggers exist in the local administration and authorities.
Freebie effects
What is the lag in this stretch ? expect for delays due to tree permission, traffic permission for work front availability and some unchartered utility shifting, thigs are going fine. Finance of this line is fully tied and there is no delay due to that. compared to earlier phases this phase work is progressing at better pace. in fact during the sub-structure work there was immense pressure from our junta to stop working during night mostly between Marathahalli to Agara citing disturbance. and there is only so much the agencies can do when working on a busy road as ORR
@@Utubecommentsu r biased
@@ayushgarg7033 you are not accepting what karnataka home minister said. They are short if funds
Trains carrying loads of people seeking jobs from "developed" countries of BIMARU pradesh or Gods own country land in Bengaluru to notice pathetic infra & shameless local govt!!! Thr native state govt is most "honest", every village, town & city is clean, roads are skate board, buses & bus stands puts London airport to shame!!......
Iblur.. any update on the design change ?
They have started barricading in the defense area on the left , probably for the portal piers and moved in supporting slurry tank for Piling rig. so should start sooner.
@@SunilHPtheres a design change? will this delay it btw
Iblur will take a long time now with double decker flyover on the deck. Say 2027
Double decker is only in Phase 3 SJP-HBL line. In the current scope only cross over point they are doing and this where the held up was , along wth Gail gas shifting and tree permission in the defense land. with those cleared, should be done now.
@@SunilHP What's cross over point bro?
This is how you give progress updates: Delhi Metro, Magenta Line, and Drone coverage, with a before-after comparison.
ruclips.net/video/ibVdJ1lQ_8A/видео.html
Looks nice. Please take initiate for BLR and give similar updates. People will really be grateful
Bro when will blue line get completed?