Blue line | ORR METRO | K R Puram to Silkboard JUN 2024 Updates

Поделиться
HTML-код
  • Опубликовано: 8 июн 2024
  • Blue line | ORR METRO | K R Puram to Silkboard junction JUN 2024 Updates
    Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM
    ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ
    ***********************************************
    JUNE 2024 Updates
    Recorded Date : 09-JUN-2024
    Civil Contractor :
    PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement
    PKG2 - Shankaranarayana Constructions PVT ltd - 9.744 KM
    ಸಿಲ್ಕ್‌ ಬೋರ್ಡ್‌ನಿಂದ ಕಾಡುಬೀಸನಹಳ್ಳಿಯವರೆಗಿನ ಪ್ಯಾಕೇಜ್‌ -1 ನಿರ್ಮಾಣ ಗುತ್ತಿಗೆಯನ್ನು ಆಫ್ಕಾನ್ಸ್‌ ಸಂಸ್ಥೆ ಪಡೆದಿದ್ದರೆ,
    ಕಾಡುಬೀಸನಹಳ್ಳಿಯಿಂದ ಬೈಯಪ್ಪನಹಳ್ಳಿಯವರೆಗಿನ ಎರಡನೇ ಪ್ಯಾಕೇಜ್‌ನ ಗುತ್ತಿಗೆಯನ್ನು ಶಂಕರನಾರಾಯಣ ಕನ್‌ಸ್ಟ್ರಕ್ಷನ್‌ ಪಡೆದಿದೆ.
    Stations in the stretch :
    Central Silk Board Station ( Interchange with Yellow line ) : All pier cast up to concourse level. CC Connector erection in progress
    HSR layout Station : All pier cast up to concourse level. CC Connector erection in progress
    Agara Station : All Piers cast up to platform level.CC and PF arms being erected.
    Ibbalur Station : All pier cast up to concourse level.
    Bellandur Station : Concourse slab casting works in Progress.
    Kadubeesanahalli Station : U Girder erection by LG in progress.
    Kodibeesanahalli Station : All pier cast up to platform level. CC and PF arms being erected.
    Marathahalli Station : Concourse beam casting in progress.
    ISRO Station : All piers cast up to platform level.CC and PF Connector erection in progress
    Doddanekundi Station : All pier cast up to concourse level.CC Connector erection in progress
    DRDO sports complex Station : Concourse and platform slab casting works in Progress
    SaraswathiNagar Station ( Mahadevpura ): Concourse and platform slab casting works in Progress
    K R Pura Station ( Interchange with Purple line ) : Concourse and platform beam being cast
    #bmrcl #bangaloremetro #ORRMetro
    ------------------------------
    Track: Dance With Me - Next Route [Audio Library Release]
    Music provided by Audio Library Plus
    Watch: • Dance With Me - Next R...
    Free Download / Stream: alplus.io/dance-me-nr
    ------------------------------

Комментарии • 37

  • @IndianRailwaysjourneys
    @IndianRailwaysjourneys 5 дней назад +1

    Nice upload.. Cheers 👍

  • @shreyass5664
    @shreyass5664 29 дней назад +4

    Nice video work progress is really good.Hoping they open the silk board to kr puram line by 2025😊

    • @BhavishKumar-hl3fl
      @BhavishKumar-hl3fl 4 дня назад

      Brother when will bengluru be organised,clean and green 😢😢

    • @shreyass5664
      @shreyass5664 2 дня назад

      @@BhavishKumar-hl3fl Once all metro lines opened we can see good improvement in traffic.Altready BLR is improved from 2nd to 6th point in tom tom index 👍

  • @user-jj9rk7no1z
    @user-jj9rk7no1z 29 дней назад

    Good morning 🌄❤

  • @AbHi-tm5dh
    @AbHi-tm5dh 29 дней назад +2

    Great video!!!! Can you please provide update on pink line also

  • @sasanka7474
    @sasanka7474 24 дня назад

    this flyover is like next apprisal will see hike as by manager

  • @harishkakaraparthy3036
    @harishkakaraparthy3036 7 дней назад

    As per the progress of works , they should be able to open by 2025 ending of 2025 mid. But they are saying by 2026 September , they will open. Not sure why so much time from this point. Viaduct is completed in mostvof the places. Metro station works are also progressing well. Track laying and signalling should be completed in any year from now. So ideally by 2025 ending all works should be completed

  • @nithinkumarr2923
    @nithinkumarr2923 29 дней назад

    Can you do video on suburban rail project..?

  • @kkvindia822
    @kkvindia822 29 дней назад

    Please explain what is happening..🎉

  • @JCMenon76
    @JCMenon76 29 дней назад

    Thank you Sunil. Can you bring out an update on the trail run progress of the yellow line.

    • @SunilHP
      @SunilHP  29 дней назад +1

      So far only static trials. Getting access from bmrcl is very tough

  • @sachinjogi1995
    @sachinjogi1995 27 дней назад

    When do you think realistically metro service will start from KR Puram to SilkBoard?

    • @SunilHP
      @SunilHP  26 дней назад +2

      KR Puram to SB : Viaduct works are in advanced stages, Station work is picking pace now. System contracts are mostly awarded. Realistically 2026 first quarter is doable with some commitment and push.

  • @sugureshireddy4590
    @sugureshireddy4590 26 дней назад +1

    This metro construction has totally destroyed beauty of the city

  • @dvlogs6965
    @dvlogs6965 28 дней назад

    Iblur station will be bigger. Because it should accommodate Sarjapur section too

    • @SunilHP
      @SunilHP  28 дней назад

      Ibblur will have 2 stations side by side. In current AFCONS scope only one will be built and other one will be later during SJP-Hebbal line

    • @vikass8039
      @vikass8039 28 дней назад +1

      @@SunilHP rv road thara pakka pakka ne iratha athva silk bord thara 200 -300 m doora iratha

    • @SunilHP
      @SunilHP  28 дней назад +1

      @@vikass8039 they will right next to each other. Where the flyover down ramp is currently towards SB is the location for the future station. This is similar to as you pointed RV Road and the new KR Pura interchange under construction.

    • @vikass8039
      @vikass8039 27 дней назад

      @@SunilHP TQ

  • @sachinjogi1995
    @sachinjogi1995 18 дней назад

    Do you know why is yellow line testing taking so long?

    • @SunilHP
      @SunilHP  18 дней назад +1

      actually line testing is only recently. Any new rolling stock has to first do elaborate static and dynamic tests and get certified by RSDO. With this line testing, speed testing results are tabulated and shared with CMRS for inspection and certification. In our case since we have only one train so far, it further adds up.

  • @newbiekhyber
    @newbiekhyber 28 дней назад +5

    Ever since there is a congress government in Karnataka, the metro progress has been very slow. The people of Karnataka should have known the consequences of voting for Congress.

    • @SunilHP
      @SunilHP  28 дней назад +8

      Metro project progress has no bearing on who is in power since the projects have all funds tied through external agencies and is run independently. Worker shortage due to elections and they returning back to their states is not dependent on any party in power. Let us keep political commentaries outside of this.

    • @bengaluruhudga6985
      @bengaluruhudga6985 28 дней назад +3

      WhatsApp University student😂

    • @newbiekhyber
      @newbiekhyber 26 дней назад

      @@SunilHP This is living in a fool's paradise. Did you not know that funds by any external agency are to be guaranteed by the central government. It means if the state government fails to pay back the loan, the central government will do so. It is only then that these agencies release the funds. With a different political party in power at the center and another one at the state, all approvals take longer or don't come at all. The bottom line is state governments can hardly do anything without the center's nod. That's why they say - vote carefully.

    • @newbiekhyber
      @newbiekhyber 26 дней назад

      @@bengaluruhudga6985 Come to Delhi and see how fast infrastructure projects get completed and launched.

    • @SunilHP
      @SunilHP  26 дней назад +1

      @@newbiekhyber Please keep your knowledge and political advices to yourself. I am very much aware of how sovereign loans work and what is the role of CG in them. In a democracy no body can guarantee that one party will be at the helm in both the state and centre. And in the spirit of being a Union of states and federal structure of governance this is the least expected. Go back and look how many approvals , how much financial assistance wsa received when Karnataka had BJP in power and how enthu they were to track the progress of metro. I dont want to take this further and the sole purpose of the videos is to give an update and if you don't like it, you are welcome to ignore.

  • @tejass4657
    @tejass4657 29 дней назад +1

    Tejas.s

  • @ChandraSekhar-no5ts
    @ChandraSekhar-no5ts 23 дня назад

    You need to buy a Drone now. We need to view the top view amid track laying might start in coming months.

  • @sasanka7474
    @sasanka7474 24 дня назад

    this flyover is like next apprisal will see hike as by manager