Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || July 2023

Поделиться
HTML-код
  • Опубликовано: 7 июл 2023
  • Blue line updates from Airport to Hebbal. Recorded Date : 08-Jul-2023
    Phase 2B - Airport to Hebbal
    ***********************************************
    JULY 2023 Updates
    Civil Contractor : PKG2 - NCC LTD - 11.678 KM
    PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
    Piling Works Happening and Pier casting Picking up pace.
    Package 2 :
    Hebbal Station :- No Works Yet
    Kodigehalli Station :- Piling Works in Progress
    Jakkur Cross Station :- Pier casting in progress
    Jakkur Plantation Station ( probable, Not confirmed ) : No Signs Yet.
    Yelahanka / Kogilu Cross Station :- Piling Completed. Pier casting yet to begin.
    Bagalur Cross Station :- Pier casting upto Concourse level and Concourse beam casting started
    Package 3 :
    Bettahalasuru Station : No Works Yet.
    Chikkajala Station : Piling Completed. Pier casting yet to begin.
    Doddajala Station : Pier casting work in progress.
    Stations done by KIAL :
    Airport City : No Works
    KIAL Terminals : Work on Full Swing
    ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B

Комментарии • 24

  • @ayushgarg7033
    @ayushgarg7033 Год назад +5

    I feel they should have divided this section in 2 - 3 phases and allotted work accordingly, 2026 deadline is really too late. Bangalore needs infra very urgently, we don't have the liberty to undertake important projects for 5-7 yrs deadlines

  • @rajeshhs8
    @rajeshhs8 Год назад +2

    Thank you for the metro report

  • @mahidhars6778
    @mahidhars6778 Год назад +2

    It'll be really helpful if atleast stretch from hebbal to airport is expedited and completed before, since the traffic in this stretch is not as much as ORR it can be completed sooner and will benifit many people.

  • @madhusudhanv4684
    @madhusudhanv4684 Год назад +4

    Bro please make the video at 2x speed 36min is long 20min will be good at 2x speed also we can see clearly the progress

    • @SunilHP
      @SunilHP  Год назад +1

      Thank you for the feedback. The updates apart from progress, is also used by other Metro - SSC community members for tracking progress minutely. If I increase at source the compression would mean they cannot get the details like pier numbers and so on. As a work around I would suggest you click on the settings and select the playback speed suited to you and enjoy. thanks again.

    • @kirtikunjdas717
      @kirtikunjdas717 Год назад +2

      there is an option to increase/decrease video speed for viewers

  • @maxia1066
    @maxia1066 Год назад +1

    Hello there. Do you know where exactly is the Bettahalasuru station coming up? I am looking for a house around there. This info will be very useful 🙏

  • @Anu-ux3tw
    @Anu-ux3tw Год назад +3

    Hi, Great work!! You update it every month!! Can you tell me whether Phase 2A is getting constructed slowly or quickly?
    And can you also explain how metro works near the airforce?

    • @SunilHP
      @SunilHP  Год назад +3

      Phase 2A is in much better shape than 2B since it started early. Both SNC and AFCONS are doing well having gone through they hurdles. In 2B pkg 1 between KRP to Hebbal lags because of the 4 months work stoppage due to the unfortunate incident. But it is back since a month and slowly getting into rhythm. pkg 2 and 3 are doing quite well.
      Near the AF , the line is planned to go below grade and will rise up near Hunasamaranahalli. Since it is a small stretch, it would be cut and cover method and no TBM is employed.

    • @ayushgarg7033
      @ayushgarg7033 Год назад +1

      2A will now progress slow as their priority was to decongest the road but station work is not progressing rapidly as viaduct work did

    • @Anu-ux3tw
      @Anu-ux3tw Год назад +1

      @@SunilHP The unfortunate incident happened in phase 2A ORR road right?

    • @SunilHP
      @SunilHP  Год назад +1

      @@Anu-ux3tw No. 2B - Pkg 1 - ORR , near nagavara

    • @Anu-ux3tw
      @Anu-ux3tw Год назад +1

      @@SunilHP Oh ok, Got it, I feel sad for that though,
      I still wonder how did that even happen?

  • @nbharath5097
    @nbharath5097 Год назад +1

    Any idea about hebbal station - where it will be built

    • @SunilHP
      @SunilHP  Год назад +2

      It is within the BMTC depot that is on the corner when you turn from Airport road towards ORR.

  • @Anu-ux3tw
    @Anu-ux3tw 11 месяцев назад

    Why there are some mysterious pillars next to the flyover in 34:03 ?
    Is it a part of metro?

    • @SunilHP
      @SunilHP  11 месяцев назад

      Ignore these. these were piers done by BDA on the Hebbal junction improvement and abandoned since a lot of changes have happened since then.

    • @Anu-ux3tw
      @Anu-ux3tw 11 месяцев назад

      @@SunilHPtq for the information

  • @Anmol4824
    @Anmol4824 Год назад +1

    Do you think there is good progress in airport to hebbal section??

    • @SunilHP
      @SunilHP  Год назад

      Yes Absolutely. They are doing quite well.

    • @vijaysrini27
      @vijaysrini27 Год назад +1

      Yes. Hope that this corridor upto Hebbal be opened by mid 2025 atleast. Then they can expand.

    • @Anu-ux3tw
      @Anu-ux3tw Год назад +1

      @SunilHP But I'm not able to see any workers inside
      Edit 1: Oh yeah I saw them working

  • @prasannasandur8238
    @prasannasandur8238 9 месяцев назад

    BLR Metro is known for extending deadlines. I think they lack expertise in technical administration like chosing the right contractor, progress of work based on duration etc. With this they lack interest and willingness to deliver. Their attitude is "Use Metro when it is ready" with infinite time lines. They have also destroyed the asthetics of Bangalire city. It is pathetic.