Honnacotts M Week 40 - Slating continues, plaster-boarding, first fix electrics, truss ready plot 2

Поделиться
HTML-код
  • Опубликовано: 22 авг 2024
  • Wk 40
    • Plot 1 - work is virtually finished on the truss roof with dormers built and and structural boarding in place.
    • Plot 2 - with scaffolding up, steel lintels are in ready for trusses to be fitted..
    • Plot 3 - first rows of blocking starts.
    • Plot 4 - dormers are readied for render. First fix electrics goes in.
    • Plot 5 - Slating continues, the front being finished looking lovely. Slating starts on the back. Plaster-boarding progresses..
    A 18-month project to create 5 beautiful, homes, inspired by old country buildings, filled with character combining old and new. A wealth of natural materials in energy efficient homes. Weekly updates on progress on our channel.