Honnacotts M Week 45 - Dot and dab plasterboarding; slating plot 4; front timbers; moving subsoil

Поделиться
HTML-код
  • Опубликовано: 11 сен 2024
  • Wk 45
    Slating on plot 4 with back completed and front stacked and ready.
    Dot and dabbing plasterboard downstairs in plot 5.
    More front timbers built in the workshop.
    Subsoil removal with over 1,000 tonnes already taken offsite to build new farm hedgebanks.
    A 18-month project to create 5 beautiful, homes, inspired by old country buildings, filled with character combining old and new. A wealth of natural materials in energy efficient homes. Weekly updates on progress on our channel.