Это видео недоступно.
Сожалеем об этом.

Calculating Critical Path with Forward and Backward Pass - Key Concepts in Project Management

Поделиться
HTML-код
  • Опубликовано: 19 авг 2024
  • This video delves deeper into calculating the Critical Path on your Schedule Network Diagram by using the Forward and Backward pass. The steps are:
    1. Note the task durations
    2. Perform the forward pass to get early start and finish dates
    3. Perform the backward pass to get late start and finish dates
    4. Calculate float as Late Start minus Early Start
    5. The critical path is the path with zero float
    #PMP #PMBOK #CAPM #ProjectManagement
    See all the Project Management Key Concepts (tools & techniques from the PMBOK Guide): • PMBOK Key Concepts for...

Комментарии • 53

  • @ShihanMeegasdeniya
    @ShihanMeegasdeniya 10 месяцев назад +9

    My friend. You have no idea how helpful this is. I appreciate this from the bottom from my heart. This helped me to do my pm assignment. Thanks again. ❤

  • @MrSilviut
    @MrSilviut Год назад +9

    So many other videos just ignore the plus one minus one thing which makes it so confusing. Thank you for explaining that. Well done.

  • @andreanberry4273
    @andreanberry4273 11 месяцев назад +6

    Hi David - For people new to this please announce that you are using the "accepted convention of the project starting on Day 1." I was confused until I saw it on page 211 in the PMBOK 6th Edition. I couldn't figure out where you were getting the number 1 from. These are excellent videos by the way! Thank you so much!

  • @Jfealy
    @Jfealy Месяц назад +1

    Awesome presentation. Thank you. PMP - here I come.

  • @Bell-uf9fn
    @Bell-uf9fn 4 месяца назад +1

    Hey David! I just wanted to say a huge thank you for your help in explaining the process and providing an example. I was able to create my own version based on your fantastic example. I really appreciate your videos, and I've been sharing them with my PM colleagues too. You're really good at explaining things in a clear and concise way. So, thanks for taking the time to make these videos and sharing your expertise - it's really helped me out a lot. Thanks again!

  • @KWENDOJOHNOKWOMOLE
    @KWENDOJOHNOKWOMOLE Месяц назад +1

    simaaaaaart ....That was very reliable. A perfect presentation. Shukran madze❤❤❤❤❤❤❤❤❤❤❤❤👌👌👌👌

  • @schiefele5514
    @schiefele5514 2 года назад +3

    You are the best, better than my professors!

  • @videogamesare1
    @videogamesare1 Год назад

    Thanks David, this helped explain the backward pass very clearly.

  • @konsichguyita5246
    @konsichguyita5246 Год назад +1

    Wow you described this easiest possible way. Thank you!

  • @LekhaJD
    @LekhaJD 7 месяцев назад

    Thank you! Your explanation easily clarified a lot of my doubts.

  • @user-xk6eq4ov9c
    @user-xk6eq4ov9c 10 месяцев назад

    Excellent way of teaching

  • @HlumelaMkabile
    @HlumelaMkabile Месяц назад

    Very helpful 😢

  • @jadwigapolak2161
    @jadwigapolak2161 5 месяцев назад +1

    Very well explained!

  • @sargamkapoor1899
    @sargamkapoor1899 Год назад +1

    All your vides are great and so helpful

  • @kevinjamal836
    @kevinjamal836 2 года назад +2

    You've made this so simple!! Thanks man

  • @london12327
    @london12327 11 месяцев назад

    You made this look very simple !!

  • @charlotteybradley7579
    @charlotteybradley7579 Год назад +1

    David, You are amazing. Your explanation was so much better than.... I wont mention any names 😀🤣

  • @afshanlakdawalla
    @afshanlakdawalla 2 года назад +1

    Absolutely made simple...thanks so much!

  • @mdshahzebrahman7223
    @mdshahzebrahman7223 Год назад +1

    Very helpful, thanks!

  • @myramyra2
    @myramyra2 8 месяцев назад

    Great breakdown explanation. New subscriber

  • @Canadianehhhhh
    @Canadianehhhhh 3 месяца назад +1

    Thank you for explaining this 100% better than the garbage instructions I received from my project management essentials course at SAIT.

  • @nimmadhillonz
    @nimmadhillonz Год назад +4

    Hello David, great video, you really make it clear. The only think which through me off in your explanation is that you are using the +1 and -1 for the ES and EF. Is that necessary? In other explanations they didn't do it. Thanks for the answer!

    • @davidmclachlanproject
      @davidmclachlanproject  Год назад +2

      Yes you are right, they are not needed and it's simpler without them. I have adjusted this in my course 🙂

    • @mopremo
      @mopremo Год назад +1

      Does that mean you made a new video explaining it without the +1 and -1? 😊

  • @wflzoom6219
    @wflzoom6219 Год назад +11

    Whats been throwing me for a loop on these CPA's I have been watching a few, and the -1 and +1 to compensate for the starting ES of 1, instead of zero. is there a reason why the first activity ES in some diagrams starts with 0, and others with a 1 ? or is this just preference?

    • @mopremo
      @mopremo Год назад +1

      I had the exact same question!

    • @Alldidas
      @Alldidas 11 месяцев назад +2

      @@mopremo Same, I think the best practice is to utilize 0 as your earliest start. Typically everything else starts with 0

    • @Alldidas
      @Alldidas 11 месяцев назад +1

      @@mopremo Your early start on your second task should match the earliest finish on your first.

    • @mopremo
      @mopremo 10 месяцев назад

      @@AlldidasThank you!

  • @TheLilboy6
    @TheLilboy6 10 месяцев назад

    Love you mate

  • @YogeshPatil-db2sc
    @YogeshPatil-db2sc 8 месяцев назад

    Amazing ty

  • @calciumdd7696
    @calciumdd7696 8 месяцев назад

    this helps me prep before my exam hahah

  • @zuzanalima8742
    @zuzanalima8742 Год назад +1

    Hello David, thank you again for all your great videos, you are doing for the PMP students. Not using anythig else now and its very efficient! 🙂But the only thing I am struggling now is to manage the time with the Diagrams questions (the Critical path questions and other one when you need to fill in all the boxes or do longer calculation. If I have in avarage 3 min for quetion, there is no change I can do it. Do you have any tips how I can improve the speed of solving these questions?? I am pretty sure, other students have the the similar problem. Thanks a lot!

  • @Ola92408
    @Ola92408 2 года назад +3

    How can you answer this kind of questions quickly on the exam without overthinking? Do you have any tips or that? Thank you.

    • @davidmclachlanproject
      @davidmclachlanproject  2 года назад +3

      With these, there won't be many questions on it (I had around 2-3 and that was before the new Agile format). They're mostly around either critical path (just calculate the longest overall path) or float (a task's late finish minus its early finish). With that, plus the general knowledge of it (i.e this video) you should do fine 🙂

    • @Ola92408
      @Ola92408 2 года назад +1

      @@davidmclachlanproject thank you. I'd practiced it on paper using your way and it totally makes sense. Thank you for the great video!

  • @MrAbitha123
    @MrAbitha123 9 месяцев назад

    Hi David, I am preparing for the PMP exam, and your videos have been incredibly helpful! I have a question, In the video, you said that the Early Finish (EF) date is calculated using the following formula: EF = ES + Duration - 1, however, the PMI website states that the EF date is calculated using the following formula: EF = ES + Duration Which formula is correct to use for the PMP exam? Thank you for your time and consideration. I appreciate your help.

    • @garrettbell8419
      @garrettbell8419 9 месяцев назад

      the plus one and minus one is just compensating for starting the first activity at '1' instead of '0'(including the work done in day 1 in your duration). It confused me as well initially. I hope this helps.

  • @yuliiavenhlovska9028
    @yuliiavenhlovska9028 2 года назад +1

    Can you please explain how the duration was calculated for activity 2? You calculated 4-3-1

    • @davidmclachlanproject
      @davidmclachlanproject  2 года назад +1

      Do you mean the late start during the backward pass? It is the late finish minus duration plus one: 15 - 5 + 1 = 11. Durations themselves are just estimated at the beginning 🙂

  • @A-Sidhu
    @A-Sidhu 2 месяца назад

    Make the first activity day 0 instead of day 1. Then you don't need to add or subtract 1 later on.

  • @shehab976
    @shehab976 2 года назад +1

    Is that gonna work all the time?i have examples that has negative floats

    • @davidmclachlanproject
      @davidmclachlanproject  2 года назад +1

      Good question. I've had a look at your video - love your program! Great stuff. For that, it is a normal PERT diagram with no ES or LS etc, you can just add up the shortest path (e.g. 1, 4, 7, 9). Using a schedule network diagram, you should have ES and LS, and I can't think of any situation where your late start would be BEFORE your early start (and hence, a negative number). Especially if doing the forward and backward pass first. I may be missing something?

    • @shehab976
      @shehab976 2 года назад

      @@davidmclachlanproject sir,those were (ls,lf,es,ef) in the image too,u just need to increase the text size at top of the app,i updated the app several times,its no more exactly that one in the video...bt i am stuck finding critical path

  • @jud3356
    @jud3356 Год назад

    The video seems to be broken? It’s not playing

  • @timmyhiggins5220
    @timmyhiggins5220 8 месяцев назад +1

    I don't understand where he got 15..6 plus 10 equals 16

    • @chakekarabo1421
      @chakekarabo1421 4 месяца назад

      Same here because in my understanding it should be ES plus Duration to get EF

    • @adaoraobed608
      @adaoraobed608 2 месяца назад

      He is just not detailed.

  • @pushpanaorem4371
    @pushpanaorem4371 Год назад +1

    you miss explaining certain thing. Please make sure u explain everything at least what u have displayed on the screen..forward and backward pass explanation is not clear

  • @agapeagapeone
    @agapeagapeone 2 года назад

    🤣🤣🤣 4:29

  • @zuzanalima8742
    @zuzanalima8742 Год назад +2

    Hello David, great video, you really make it clear. The only think which through me off in your explanation is that you using the +1 and -1 for the ES and EF. Is that necessary? In other explanations they didnt do it. Thanks for the answer!

    • @davidmclachlanproject
      @davidmclachlanproject  Год назад +3

      Yes, I think you are right! The way in this video is from the PMBOK guide, but yours is an easier way and it still gets the same outcome 🙂

    • @zuzanalima8742
      @zuzanalima8742 Год назад

      @@davidmclachlanproject Awesome. Thank you very much for the quick reply. Really appreciated!