Forward Pass and Backward Pass to determine project duration

Поделиться
HTML-код
  • Опубликовано: 11 дек 2024

Комментарии • 23

  • @princewivedi3619
    @princewivedi3619 Год назад +2

    Great explanation!
    Made the concept crystal clear...

  • @muhdkhairulamirinum3985
    @muhdkhairulamirinum3985 Год назад

    TQ sir. this tutorial is straight to the point

  • @lyonya4spam
    @lyonya4spam 3 года назад +2

    simple and clear, thanks!

  • @AbrehamDemsis-rh7op
    @AbrehamDemsis-rh7op 11 месяцев назад

    Thanks it is quite clear 🎉

  • @terry-annjohnson5237
    @terry-annjohnson5237 5 лет назад +2

    This gave me a better understanding of forward and backward pass. Thank you !

  • @leolau-i2o
    @leolau-i2o Год назад

    dont really get the rational of es/ef having same duration as ls/lf...is that something common?

  • @19yashghotkarsyit62
    @19yashghotkarsyit62 2 года назад

    kaka mai 500th subscriber hu

  • @abraarahmad9203
    @abraarahmad9203 2 года назад

    U deserve my like

  • @beatriceogolla8908
    @beatriceogolla8908 4 года назад +1

    Thank you so much. This gave me the much needed understanding.

  • @theremotecoder
    @theremotecoder 3 года назад

    A question about the network paths:
    Are these mutually exclusive, or should they be worked on in parallel? Expressed in project terms: Are *all* tasks of *all* paths needed to complete the project? /OR/ are the paths variants of each other, where only the best fit is chosen?
    In this example: going the top path (A->B-D-G->H) will this be the whole project, and all that's needed?
    That's quite abstract, hope someone can understand what I mean, thanks ... :D

    • @muralimohan977
      @muralimohan977 2 года назад +2

      Yes, all tasks in the network diagram need to be completed to complete the project.
      In the example, Critical Path (CP) (A->B-D-G->H), will determine the shortest time (32 days) required to complete the project. In other words, you cannot complete the project in shorter time than this.
      For any reason if you don't do any work on non critical tasks (C,E &F), then over the period, these tasks and the corresponding paths will become critical and extend the project duration beyond the original/baseline of 32 days.
      For example: The Total float for task E is LS-ES= 19-9= 10 days. Therefore 10 days is the maximum time task E can be delayed. If it delays beyond 10 days, then this task will become critical extending the project completion beyond 32 days.
      Please note that CP is dynamic in nature and will change during the execution of the project, as per the actual progress achieved. Therefore CP has to be monitored periodically (as per schedule tracking process) and mid-course correction(s) taken accordingly to keep the project on track.

  • @abhishekbaranwal5801
    @abhishekbaranwal5801 5 лет назад +4

    B can start only after A is finish on 5th day, so B can start from 6th day only???

    • @paulascappini8910
      @paulascappini8910 5 лет назад +1

      this was the issue I had as well. If you are using day 5 to complete task A - then task B cannot start until day 6. this is off by one day for forward pass according to my calculations.

    • @MrActionRadar
      @MrActionRadar 3 года назад

      I think so.

  • @hussutp
    @hussutp 4 года назад +3

    minor correction at display time 6.28 on the free float = LS - ES instead mentioned FF= ES-LS
    Thanks for the sharing!

  • @muralimohan977
    @muralimohan977 2 года назад +1

    The difference between LS & ES or LF & EF is "TOTAL FLOAT" and NOT "FREE FLOAT", as explained in the video.
    TOTAL FLOAT is the float/slack available for all the tasks combined in that particular path. Whereas FREE FLOAT is the float/slack available for an individual task in the path.

  • @baadnewz017
    @baadnewz017 5 лет назад +1

    Great presentation :)

  • @kk10-
    @kk10- 5 лет назад +1

    Thanks, Big help!

  • @therapysg7205
    @therapysg7205 5 лет назад +1

    Very simple

  • @sworupgautam7243
    @sworupgautam7243 Год назад

    That's a TOTAL float not FREE float :/

  • @dipanjannanadiroy1205
    @dipanjannanadiroy1205 2 года назад +2

    Learn to teach !!!! Rather than self teaching lol