CPM in Project Management & Operations Research | How to do a Critical Path Method
HTML-код
- Опубликовано: 16 июл 2024
- In this video, you will learn how to do a critical path method in the most easiest way.
CPM is an important scheduling technique. This method is used when the duration is known or certain.
The steps involved in CPM:
1. Network Diagram
2. Identify the critical path
3. Calculation of Early start time, Early finish time, late start time and late finish time.
4. Calculate the float, free float and independent float.
#CPM #Criticalpathmethod #freefloat #independent float #float
00:00 -Intro
00:43 -Network Construction
02:30 - Critical Path
04:59 -Early Start Time
06:04 - Late Finish Time
8:34 - Early Finish Time
09:08 - Late Start Time
09:57 - Total Float
11:02 Free Float
13:49 Independent Float
Keep Watching, Keep Learning
I always have mental block with this topic. But thank you very much for making it so clear, palatable, and easy to understand. You are an amazing educator!
Kenzo I'm glad this video helped you .Stay tuned for more such videos
@@karpagamqtcorner8764 float and slack both r sam ma'am?
@@kranthikumar4665 yes
pl
Thank you 💕
YOU ARE SO ORIGANIZED AND GENIUS TEACHER. IT'S WOW!
Simple and great teaching. I never understood clearly this topic either during my college days or during my service till today. You made so clear . Thank You Madam.
Watched so many vedeos regarding free float,total float, indipendent float. But can't get it untill I see ur vedeo.Finally I understand this topic. Thank you for your excellent explonation.
had an exam today, watched this video yesterday with 0 prior knowledge and still managed to nail these problems correctly. Great Video, Came back here to say Thank You!
thanks dear porf
god blees you
two days i was watching the different videos related to this lecture.
fortunately your lecture solved my problems in 10 minutes .
This is fantastic. Learning it online and you've made it easy for me to understand 👍
very nice video. tomorrow is my exam
Same bro
Us bro
Today is my exam, I am in bus going to college and watching this video
Can u share the question paper?@@04_ritampaul87
Hi Miss, I from Malaysia. I really appreciate that finally I can find someone with good knowledge and widely share. Thank you 😊
Thank you, Madam..for your wonderfull explanations..Helps me lot for my MBA in Engineering Management exam. I was little confused...you explains better..Love from Malaysia.
Wonderful explanation, each and every step is clearly explained! Thanks Ma'am.
Thanks for watching the videos. The chapters are added here.
00:00 -Intro
00:43 -Network Construction
02:30 - Critical Path
04:59 -Early Start Time
06:04 - Late Finish Time
8:34 - Early Finish Time
09:08 - Late Start Time
09:57 - Total Float
11:02 Free Float
13:49 Independent Float
Keep Watching, Keep Learning
Ma'am slack and float both are same?
maaam the duration from 1 to 2 is 12 not 13
I am having an exam related to topic and was confused with the formulas. Thanks to u mam now I am clear with everything. The topic was taught very clearly and easy to understand. You are doing a great job and please continue helping people with your way of teaching.
Glad to hear that Santhosh.
The best explanation for self study students. Very easy to understand
you are an amazing tutor ,, thanks for making it so simple to understand
Greeting from Kenya. This is very simple to understand. Thanks very much for the clarification 🙏
I didn't understand it in my class. I also found it very boring. But this is now very clear and enjoyable to me.
Thank you for this amazing video!
I love the way She made everything easy, I understood everything She said.
My mission is to break complex concepts into a simple concept. I'm glad that you have enjoyed the video Unathi Febane .
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam......
Just the perfect explanation.Thank you
Thank you Ma'am for this easy-to-understand video tutorial.
Your teaching, is so amazing. Am so clarified and refreshed by your teachings. Thanks alot
Thank you so much
It's very easy to learn!
It's help me alot ❤️
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam❤️❤️......
I always have mental block with this topic.but thanks for making it clear and easy to understand. Your educating method short, precise, easy and very simple to understand....You're unstoppable
This is on point. Thank you 🙏
Thank you maam for explaining this topic beautifully in 16 mins. i was facing problem while understanding this topic and reading the boring ppts
This problem process after 5 mins heading is rounding.. Super telling mam thank you so much
I forgot I saw this and realized it again...Thank you ㅠㅠ
Urs teaching way is easy understand by this topic mam... In my clg my mam doing this topic I felt fear how to do but I saw this vedio easily I understand ..tq so much mam
Thank-you very much,concept become crystal clear.
Thank you so much! Extremely helpful!
Thank you mam .... i do not understand cpm example but,your support and explaination are understand example
It is really well-explained ma'am, thank you so much ma'am for this video.
The method of study is very simple and more effective than others.
mam, you have explained it soo clearly and politely, thanks
Very clear teaching. Thank you
I will follow your learning video always, but a great thank's for this topic. Thank you so mach.
You are most welcome Amanuel Getaneh :-)
Good afternoon, I am a Ghanaian from West Africa, and I really enjoy your presentation.
This is fantastic. Learning it online and you've made it easy for me to understand
Glad to hear that George Ogalo
It didn’t took even 5 minutes to understand. Thank you ma’am
Very informative video !!! Thank you
Simple and clear networking am done thank you so much mum
The way of teaching is brilliant 💓thanks alot
You are amazing ma'am. Thank you so much. Lots of love.❤
Thank you very much ma'am. I'm subscribing. I have an exam tomorrow and this really helps❤
Thank you, it's clearly understood
Thank you so much Ma'am -- Very Nicely clearing the concept.---"Hope This is the best way you teach".
Thanks for liking. Stay tuned for more such videos
❤❤❤ Thanks very much for the precise procedure ...easy to understand and lovely
Thank you so much ma'am
Very useful for cma final level costing
Thanks you so much you are amazing teacher.
You are amazing instructor ❤
I like your way of teaching.
The best explanation for self study students. Very easy to understand. Thank you Ma'am.
Glad to hear that Kaushini
Watching this a couple of days before CMA Finals.... And this is the best video I've come across for network analysis.... Thanks a lot ma'am 🙏
Same here😅.. All the Best!!
@@alishakashyap4431 You too!!
Tomorrow is my exam i have no one to help me so you are my only hope
thank you very much to identify simple to more understand
Thank you for this video.
Thanku ma'am for that much simpler explanation 👏👏
Thank you so much mam.Your video is most important to understand this CPM Method easily and after seen this video now i will solve all type of sum in this method.Once again thanks a lot mam.😊🥰
Very explicit
Thank you very much ma'am
Very clear video. Thanks
Most helpful .it's clearly explanation
The clarity of mam's teaching is remarkable
TQ mam I have understood very clearly it is very useful for my exam mam
Ma’am i am sufaila. Thank you for such an amazing video❤you made the concept simple n easy to understand! Now i got a clear picture about cpm, all credit goes to you!
made it so easy. thanks
thank you mam for the video , its simple to understand this topic through this video .
Very clarified way 🙏🏻
Thank you so much mam 🎉❤️ very clear and easy explanation 💫just perfect 💯😌
Thank u so much
May god bless u 😇🙂
Thank you ma'am your video is really helpful for me 😊 the day after tomorrow is my exam 😃 so thank you 😊
Thank you Mam. Clearly Explained
Simply understood
Thank you for this amazing video!😍😍😍🌹🌹🌹
Thank you so much mam, i have understand the concept of this math Very clearly. Thanks again mam
It's my pleasure Julekha Juthi
Thank you very much for nice explained
for backward pass at step 2 , 26-15 = 11 is minimum , compared to 28-15= 13
So what did you take 11 or 13??
Because it make sense..jaisa forward process gya tha waisa hi backward jana chahiye and mam ne wo 2-4 wali line calculate nai kri jisse 11 Aa rha h minimum.. Ya to esa ho skta ki aage jake wo 11 - 13 krke - 2 ho rha hoga islie nai lia..?? Somebody clear me plz😭
On the critical path i.e 1-2-5, there will be no float. Because it is already taking the maximum time, we cannot shift the start or finish without adversly affecting the end time i.e 28 . Hence logically the EST and LFT will be the same.
This is a nice asynchronous learning
That was very well done,.. easy and simple, you get my subscription
oh my Gosh. you saving grace.
Getting you very well from Tanzania” Mathematics Unite all the people despite our differences”
Indeed it is true Obilla Ezra
You are a good Teacher. Very good explanation. thanks
You are welcome!
thank you so much🥰, you taught it very well
Best vid on cpm ❤❤❤
OMG!! Thank you so much ma'am! finally i understood this topic!
Most welcome 😊
Thank you, very very helpful
I am really Thankful to you mam
Very nice work! Thank you so much ma'am!
Thank you too! Keep Watching
Thanks so much I was able to understand this
amazingly explained, thankyou🥰
very easy to understand, thank you ma'am
Very helpful thanks for saving my semester
You're so welcome! Madaraka Deche
very east and good explanation, thank you
Thanks.. mam you teach it so easily 🥰
thank you very very very....... Much Mam.
This is very very..... Help full for me 🤗🤗🤗🤗🤗
I havr understood the concept very clearly thank u so much ma'am 😊
Most welcome 😊 Vaishnavi R
Thanks a lot for this.
with 20 minutes i got it clear, thanks mam.
U said in independent float if the value is negative & u made it 0, the same is applicable for Total float and free float.Thanks in advance
Mam, Thank you. Very nicely explained.
Excellent explanation 👍🙌👏