Hi everyone. To find the variance , Please use the formula (tp-to)/6)^2. The chapters are added here : 0:00 - Intro 1:47 - Time estimate 8:11 - Network diagram 13:16 -critical path 20:04 -Standard deviation 20:40 - Variance of the critical path 22:25 - Probability of completing the project. Keep watching, Keep learning
Really very well explained ma'am, thanks a lot. A learner like me is understandable easily. Because I am not a student of math's 12th Bio and graduated within the BA stream and working for the last 13 years in IT (as a UI/UX Designer) even then I am getting 98% of your teaching. I am pursuing MBA from Jaipur Manipal online.
Thank you so much for making this so easy to assimilate. I need clarification on how to calculate the minimum duration after arriving at the critical path using this same activity.
The probability of the project by 35 weeks will be = 77.34% mam ..you have taken variance value is 4 mam but actually it is 2 in calculations it was right then when u written by miss it will happen mam 😊.. But ur explanations is too good thank u mam❤
Dear Mrs. Arvin, I hope this message finds you well. My name is palak, and I am an aspiring digital business student with a strong interest in supporting content creators in growing their online presence. I have been following your exceptional work and am truly inspired by the impact and quality of the content you produce. I believe that with some targeted strategies, your reach and viewer engagement can be significantly enhanced. I would be delighted to offer my services, free of charge, to assist you in areas such as improving video quality, optimizing audience engagement, and implementing growth tactics specific to your content. My aim is to help you continue delivering high-value content while expanding your audience base. If you are open to discussing this further, I would be thrilled to collaborate and contribute to your success. Thank you for your time and consideration. Best regards, Palak aggarwal.
Thank you so much for making this so easy to assimilate. I need clarification on how to calculate the minimum duration after arriving at the critical path using this same activity.
Hi everyone.
To find the variance , Please use the formula (tp-to)/6)^2.
The chapters are added here :
0:00 - Intro
1:47 - Time estimate
8:11 - Network diagram
13:16 -critical path
20:04 -Standard deviation
20:40 - Variance of the critical path
22:25 - Probability of completing the project.
Keep watching, Keep learning
Ma'am I have one doubt variance calculate me last wala 0.4444 kese aaya
SD = Sqrt(Variance)@@ShubhamSharma-st3hd
(a)How can I calculate the expected time for the completion of the project?
(b)how can I calculate the individual slack of the parts?
Madam, why we are not calculating standard deviation of the critical path by adding the SD value of each critical activity?
This explanation is very clear and easy to understand. Thank u so much mam
Excellent mam... you've made a difficult problem into a simple one for me!!!
Really very well explained ma'am, thanks a lot. A learner like me is understandable easily. Because I am not a student of math's 12th Bio and graduated within the BA stream and working for the last 13 years in IT (as a UI/UX Designer) even then I am getting 98% of your teaching. I am pursuing MBA from Jaipur Manipal online.
The explanation is very clear and easy to understand. Thank you for sharing this online.
Wow, u have explained it really well, I appreciate ur effort
Very simplified presentation. Awesome. Want to see more similar videos particularly for project management end. Cheers
you are so wonder full.. you have fully talented on good explanation thanks a lot
This is very helpful. Thank you so much for your generosity 😊
Worthy content and easily understandable
Madam am from Tanzania, actually i understood your lessons, thank you
Glad you enjoyed the video ! Aptunalex
Thank you so much for making this so easy to assimilate. I need clarification on how to calculate the minimum duration after arriving at the critical path using this same activity.
Great teacher 👏 thank you so much
Hi, your explanation is clear thanks for your support.
wish ,,,if you took our operations research paper. it would have been so much easier, :') you explain in such a simple way. you make it easy for us
Thank you for this.youre a life saver
Thank you! I really appreciate your presentation
Well explained indeed 👏
best teaching in you tube
This video saved me. Thank you so much!
Very well explained
Thank you so much. Stay blessed!
Madam, why we are not calculating standard deviation of the critical path by adding the SD value of each critical activity?
amazing the way you explain
The probability of the project by 35 weeks will be = 77.34% mam ..you have taken variance value is 4 mam but actually it is 2 in calculations it was right then when u written by miss it will happen mam 😊..
But ur explanations is too good thank u mam❤
thank you so much maam for explaining this topic
Thank you so much, ma'am
Thank you very much mam for this video.
Good explanation thanks mam
Thank you, ma'am. You're awesome!
Nice explanation tnx!
Excellent presentation ma'm. One doubt...should we alwsys divide with 6 for grtting SD ? And...a diverging activity is burst...right ?
its the part of the formula
This is really good explanation thanks ma'am 🙏🏽
if the value of Z become Minus how to select from table, for example? I got a critical path value of 34 days and a project completion value of 30 days
Good class mam
Can you please share some details about PRIDE analysis?
Thank you,
Can you enlighten me how can I determine a,b,m duration at the start of the project? Thank you
very useful this lecture
Ma'am you're Good. Thank you so much
VERY HELPFUL
at 23:28 0.7874 will round off to 0.79 thwn we have to take 0.7 and 0.09 ? am i correct??
Yuppp
understanding clearly mam tq
How did you get the variance I'm not getting please
Ma'am you're too good!!!
Thank you ...very much..
How did you arrive at the variance?
She had to square the standard deviation to reach to the values on the variance..
Thanks mam 😊
THANK YOU A LOT.
it nice clarification please put each formulas in the note form
Thanks so much madam
Simplified 😊
Thank you very much
Thanks mam ❤️
Thank you ❤️❤️
Thank you madam
Mam how to calculate variance..??
Hello mam! I have a problem related to crashing. How can i share my pdf to you. Thanks
Thank you
Thank you Ma'am
Last value is wrong for variance..??mam if possible can uh please clear it
Mam how to calculate mean time
Hi mam..if u don't mind can u please update on jz drawing network diagram from basics
Mam how to find variance and delay value?
Yeah, the video skips there. I figured out the variance is the standard deviation squared. The delay probability is 100% - 78.23%.
Variance how find?
How to find delay time
Thank you mam
Dear Mrs. Arvin,
I hope this message finds you well. My name is palak, and I am an aspiring digital business student with a strong interest in supporting content creators in growing their online presence.
I have been following your exceptional work and am truly inspired by the impact and quality of the content you produce. I believe that with some targeted strategies, your reach and viewer engagement can be significantly enhanced.
I would be delighted to offer my services, free of charge, to assist you in areas such as improving video quality, optimizing audience engagement, and implementing growth tactics specific to your content. My aim is to help you continue delivering high-value content while expanding your audience base.
If you are open to discussing this further, I would be thrilled to collaborate and contribute to your success.
Thank you for your time and consideration.
Best regards,
Palak aggarwal.
Thank You maam
How to find variance
Formula to find tp tm and to
It will be given in the problem
36/6=6
Hello mam please send me pdf
36÷6=6
poor audio .. not able to understand anything
how do you find variance ?? @karpagam QT corner
[(tp-to) /6]^2
variance is simply the square of Standard Deviation
Do u have a network diagram, seperate videos to understand ....pls take few simple problems before solving bigger problems
hey, can i get your email?
Thank you so much for making this so easy to assimilate. I need clarification on how to calculate the minimum duration after arriving at the critical path using this same activity.
Thank you ❤
Thank you 🙏♥️
thank you 💕
Thank you 💕