Resource Leveling versus Resource Smoothing - Key Project Management Concepts from the PMBOK

Поделиться
HTML-код
  • Опубликовано: 10 сен 2024

Комментарии • 11

  • @RamachandraReddyV-og9gb
    @RamachandraReddyV-og9gb 2 месяца назад +1

    Thank you very much, David, for making the concept easy to understand.

  •  2 года назад +2

    Thank you very much! It really clarifies these two concepts.

  • @HondoGP
    @HondoGP 2 года назад +2

    as always... short sweet and to the Point

  • @faresar
    @faresar Год назад +1

    Clear and short. Thank you

  • @mojdehnaderi3768
    @mojdehnaderi3768 4 месяца назад +1

    Thanks David!

  • @sargamkapoor1899
    @sargamkapoor1899 Год назад

    Great Video - rather all your videos are extremely helpful - Thanks for such great videos

  • @mariannedoherty2321
    @mariannedoherty2321 4 года назад

    Thank you! Totally helped me understand the difference between the two.

  • @sultanah3044
    @sultanah3044 Год назад

    thanks Dvid

  • @sabrinaf918
    @sabrinaf918 7 месяцев назад +1

    Why can't Tom and Sue both work on Day 2. Why is Tom pushed out to Day 3?

    • @andrewfeliciano4544
      @andrewfeliciano4544 6 месяцев назад +1

      Activity C is a successor to Activity A and B. So Activity C cannot start until A and B are complete. So after Resource Leveling, Tom and Sue cannot complete those two tasks on the same day, it has to deal with the relationship of the activities.

    • @gombdr
      @gombdr 3 месяца назад

      I had exactly the same question after watching the video. Hope David can answer us.