PV=EV Revised Schedule P6 Tool | Planned value Equal Earned Value | Schedule % Equal Performance %

Поделиться
HTML-код
  • Опубликовано: 1 дек 2024

Комментарии • 9

  • @SoftEdemy
    @SoftEdemy  Год назад

    Tool Link : www.softedemy.com/product/pv-ev-revised-schedule-p6-tool/

  • @234saranyacr2
    @234saranyacr2 4 месяца назад

    Can you please explain how can we convert start finish dates into baseline start and finish dates

    • @SoftEdemy
      @SoftEdemy  4 месяца назад

      @@234saranyacr2 use global change. Check video secondary part of global change. Apply that global changes to in progress and completed activities

  • @AhmedAli-dj9jo
    @AhmedAli-dj9jo Год назад

    Great work
    Thank you so much
    Just one question
    As built dates and original duration will change or not?

    • @SoftEdemy
      @SoftEdemy  Год назад

      Original Duration will be remain same , No dates charge, Even performance percent or Earned value cost will be remain same.

  • @XpectNothing07
    @XpectNothing07 Год назад

    Great Video Sir.
    Sir Can you make a detailed video on Delayed Analysis and Extension of Time?

    • @SoftEdemy
      @SoftEdemy  Год назад

      In future their will be complete playlist of Delay analysis and Extension of time. But not right now. If you have any urgency you can contact to WhatsApp we will guide you how to prepare it. if you have a good planning practice and you understand very well planning, monitoring and controlling.

  • @taimurhassan3800
    @taimurhassan3800 8 месяцев назад

    Dear Sir, Can you make a video on Extension of Time . That How to submit EOT and Claims

    • @SoftEdemy
      @SoftEdemy  8 месяцев назад

      I will see . If I found spare time