Solving Primavera P6 Schedule % Mismatch: Aligning Excel-based S Curve and Schedule Percent Complete

Поделиться
HTML-код
  • Опубликовано: 7 ноя 2024

Комментарии • 8

  • @GulfCvCourier
    @GulfCvCourier Год назад +2

    Thank you sir,for fixing and identifying the root cause of this problem that not only I but many planning Engineer on managerial level were facing it while handling the P6, but actually we are unaware of root cause.You explained it Very well again Thank you for fixing this problem and helping the others..
    JazakAllah kher🎉

    • @SoftEdemy
      @SoftEdemy  Год назад

      Welcome. Appreciated on giving us your valuable time for feedback

  • @muslman8881
    @muslman8881 4 месяца назад

    İ was searching it's cause. Thank you very much)

    • @SoftEdemy
      @SoftEdemy  4 месяца назад

      @@muslman8881 welcome

  • @durgeshk9204
    @durgeshk9204 Год назад

    Hi, can you solve my query once again. What does the values of y-axis in either side of resources usage profile or s-curve means? If it's cost, units, labour hour and cumulative values then why it's not matching with the values in resources?

    • @SoftEdemy
      @SoftEdemy  Год назад +1

      Left side shows cumulative and right side shows maximum time interval based units or cost. The vertical bars highest value can be studied from right side while the S Curve rather units or cost will be read from left side of y axis.
      Both values lies on right and left side of resource usage profile

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy thanks again, can you also clarify how this left side cumulative values and right side values are calculted, how this limit black line draws across specific values.

    • @SoftEdemy
      @SoftEdemy  Год назад

      @durgeshk9204 the black line shows limits . What are your maximum units/time for the selected resource.
      Cumulative is calculated by adding all the resource units in the time interval
      For example if on 12 August their are 10 units and 13 their are 20 units Then the Cumulative will be 30 on left side and right side the maximum axis value will 30 also if you have assigned 15 max hnits/time than 5 will be your overallocation