Method to Eliminate Out of Sequence Activities

Поделиться
HTML-код
  • Опубликовано: 7 янв 2025

Комментарии • 73

  • @IbrahimSiddiqui-cr4ie
    @IbrahimSiddiqui-cr4ie 9 месяцев назад +2

    Managing out-of-sequence activities can be a headache, but this method offers a clear and structured approach to address them effectively. Thank you for sharing this valuable technique!

  • @creativekashaf5668
    @creativekashaf5668 2 года назад

    Nice sharing

  • @aghanajfi5595
    @aghanajfi5595 2 года назад

    Good sharing

  • @HamnaRehan
    @HamnaRehan 6 месяцев назад

    Nice sharing ☺️

  • @amnasaad5499
    @amnasaad5499 2 года назад

    very nice sharing.......

  • @sarganitvchannel6723
    @sarganitvchannel6723 2 года назад

    Good sharing very nice

  • @asmazahid7419
    @asmazahid7419 2 года назад

    wooowww nice sharing........

  • @imanzahra8198
    @imanzahra8198 2 года назад

    Amazing sharing

  • @fareehanouman2109
    @fareehanouman2109 2 года назад

    keep sharing such info.........

  • @moosa-nsgroup
    @moosa-nsgroup 2 года назад +1

    Informative video

  • @shmriz561
    @shmriz561 9 месяцев назад

    Very nice and very informative

  • @iqrabtool6766
    @iqrabtool6766 2 года назад

    Very nice and good work

  • @dollysentertainedvlogs350
    @dollysentertainedvlogs350 Год назад

    Keep sharing

  • @asiyaahmed3957
    @asiyaahmed3957 2 года назад

    bht allaaaa.........

  • @danielsugritharaj8979
    @danielsugritharaj8979 Год назад +1

    Very nice to explain thanks sir

  • @mskitchen3136
    @mskitchen3136 Год назад

    Good information for us

  • @anmolatif1477
    @anmolatif1477 2 года назад

    Good work........

  • @ManiKandan-os9bz
    @ManiKandan-os9bz 15 дней назад +1

    Thank you for your lecture engg..is this applicable for only started activities or while preparing the baseline at that time can we use this method to reduce the Out of sequence ?

    • @projectmanagementcontrol-b8737
      @projectmanagementcontrol-b8737  13 дней назад

      Hi, in baseline there is no out of sequence activities, if there is it needs to be checked
      Out of sequence activities always generated in updated program as actual site conditions vary from planned
      You can find videos on "PROJECT MANAGEMENT AND CONTROL by ASIF" which gives definition of Out of sequence activities

  • @muhammadsarkar4778
    @muhammadsarkar4778 3 месяца назад

    Nice video. But one question, why i have to assign SS relationship for the case 3 where successor has been completed already. This SS relationship is with the completed successor activity. Should I not make relationship with any new/another activity?

  • @mohammedzeeshan4405
    @mohammedzeeshan4405 8 месяцев назад

    After importing from excel to P6, while i click on finish i receive a notification of An application event has been intercepted. Please note the event code for reference. Event Code 'TASK-2775-6. Event Time 17-April-24 16:1:49. How to resolve this issue, please help me.

    • @projectmanagementcontrol-b8737
      @projectmanagementcontrol-b8737  8 месяцев назад

      Hi Zeeshan
      Hope things are well with you، don't worry P6 somtimes have unexpected results which maybe because of General negligence، just check that in your Excel file which you import doesn't contains any formulas means all formulas are converted to values?
      Always be patient and pay full concentration while import/export in P6، somtimes small things make big issues، good luck

  • @amnahaider2701
    @amnahaider2701 2 года назад

    good work.......

  • @Mahikhan-kj8ot
    @Mahikhan-kj8ot 2 года назад

    Good information

  • @sherarana-ok7qs
    @sherarana-ok7qs 2 года назад

    Good effort bro

  • @sadiaiqbal7470
    @sadiaiqbal7470 2 года назад

    nice info...........

  • @asmaishtiaq9763
    @asmaishtiaq9763 2 года назад +1

    Keep it up 👍

  • @amnahaider2701
    @amnahaider2701 2 года назад

    good job..........

  • @ashaa3307
    @ashaa3307 Год назад

    Good informative vid

  • @bikelovergirl206
    @bikelovergirl206 Год назад

    Informative

  • @muhammadkashif7613
    @muhammadkashif7613 2 года назад

    Good information 👍

  • @sadiaanjum6693
    @sadiaanjum6693 2 года назад

    keep it up..........

  • @MaheshNevase-t4o
    @MaheshNevase-t4o Год назад

    Nice video.thanks

  • @anandvishnums7621
    @anandvishnums7621 2 года назад

    While in case 3 predecessor is task dependent and successor is finish milestone i am not able to change to SS relation.. Pl help??

    • @projectmanagementcontrol-b8737
      @projectmanagementcontrol-b8737  2 года назад

      Dear Mr. Ananad,
      Greetings,
      In case-3, is mentioned in the video as General Scenario. In special case as you highlighted, it can be simply deleted. e.g. if this milestone is related to acquire all AUTHORITIES APPROVAL to start the work but some certain work is completed without these approval/s means this Milestone is no more applicable to this activity and it can be considered as redundant and can be deleted.
      I hope it will clarify your concerns, and I will be more than happy to assist you in any further queries..
      Thanks & regards

  • @mariawattoo924
    @mariawattoo924 2 года назад

    Amazing content

  • @CAV433
    @CAV433 Год назад

    Keep it up bro ☺️☺️

  • @FRSCLUB
    @FRSCLUB Год назад +1

    What we do if we have SF ?

    • @projectmanagementcontrol-b8737
      @projectmanagementcontrol-b8737  Год назад

      Hello Dear, thank you for contacting,
      SF is very rarely used relationship type therefore if encounter as "Out of Sequence", the type of relationship should be adjusted to suited with current conditions as SS and/or FF. I recommend to do it manually so that we can understand situation and modify the relationship accordingly.
      As I am Construction Planning professional, we are using 3-types of relationships (FS, SS & FF) in our design & execution projects, I never encounter for SF relationship. However me too always very keen to know where we can use SF?
      SF is preferred for (Bottom to Top) planning, means you know the required date and you want to plan for pre-requisite/s for it. In construction field, it maybe that I know when a certain material will be required at site for execution and then i use SF relationship to compute the Plan dates for Engineering & Procurement activities (for example date of submission of Pre-Qualification, material & Shop Drawing submission, order date etc...
      As far as my work, FS is the best relationship for "Top to Bottom" planning however whenever SS or FF are used, they should be closed with corresponding SS and/of FF with appropriate Lag duration
      One more reason to avoid SF relationship is that during Update of the project, it may effect the results...

    • @FRSCLUB
      @FRSCLUB Год назад

      Thank you
      @@projectmanagementcontrol-b8737

  • @anandvishnums7621
    @anandvishnums7621 2 года назад

    I have one doubt can u clarify.. If out of sequence is having more than one predecessor and successor what we will do??

    • @projectmanagementcontrol-b8737
      @projectmanagementcontrol-b8737  2 года назад

      Dear Mr. Anand,
      Greetings,
      Sorry for late reply,
      In general, most of the activities are having more than one predecessors/successors, we need to rectify only relationship/s which causes OoS phenomenon, the rest can be keep remains same because other relationships are still valid. One important point need to understand is that the Number of OoS activities shown in the LOG files includes all these relationship which need to be modified, so once you are rectifying one of the relationship and you notice some other relationships which need to be rectified you can rectified them at the same time instead of going and check the Log files again and again.
      I hope it will clarify your point, if you need further clarifications please feel free to contact.
      Thanks & regards

  • @sarganitvchannel6723
    @sarganitvchannel6723 2 года назад

    Nice video

  • @ansarisahb
    @ansarisahb 2 года назад

    Thanx For sharing

  • @asmamaqsood6519
    @asmamaqsood6519 2 года назад

    like it alot........

  • @jahangirmaria4982
    @jahangirmaria4982 2 года назад

    Amazing

  • @salaarshin2479
    @salaarshin2479 2 года назад

    Good

  • @sakeena2846
    @sakeena2846 2 года назад

    Nice

  • @sarahaider5337
    @sarahaider5337 2 года назад

    infomative...........

  • @musukitchen6960
    @musukitchen6960 Год назад

    Goof video

  • @VentureVia
    @VentureVia Год назад

    Beauty

  • @jahangirmaria4982
    @jahangirmaria4982 2 года назад

    Nice sharing

  • @sagani2897
    @sagani2897 2 года назад

    Good sharing

  • @shehrsworld2925
    @shehrsworld2925 Год назад

    Informative video

  • @bullajeevlogs9939
    @bullajeevlogs9939 9 месяцев назад +1

    Good information

  • @noorhasan6727
    @noorhasan6727 2 года назад

    Thanx For sharing

  • @ijazhussain6963
    @ijazhussain6963 2 года назад

    Nice video

  • @MaryamKhan-dl2cs
    @MaryamKhan-dl2cs Год назад

    Amazing

  • @mjw7865
    @mjw7865 2 года назад

    Nice sharing

  • @mesumabbas7548
    @mesumabbas7548 Год назад

    Nice video

  • @MuhammadAzam-rr4hj
    @MuhammadAzam-rr4hj 7 месяцев назад

    Amazing

  • @aleenanino9358
    @aleenanino9358 2 года назад

    Nice sharing

  • @shehrskitchen5237
    @shehrskitchen5237 9 месяцев назад

    Nice video

  • @artandcraftwithfun8174
    @artandcraftwithfun8174 2 года назад

    Nice sharing

  • @khadijapinko2057
    @khadijapinko2057 2 года назад

    Nice sharing

  • @mariawattoo924
    @mariawattoo924 2 года назад

    Nice sharing

  • @Ahmed-bf5mk
    @Ahmed-bf5mk 2 года назад

    Nice sharing

  • @rashidagee8342
    @rashidagee8342 2 года назад

    Nice sharing

  • @fatimanoor2802
    @fatimanoor2802 2 года назад

    Nice sharing

  • @mariaadii7016
    @mariaadii7016 2 года назад

    Nice sharing