Create Detailed Manhour S-Curve from Primavera P6 to Excel | Manpower Stacked Histogram from P6

Поделиться
HTML-код
  • Опубликовано: 27 окт 2024

Комментарии • 26

  • @phemmy2008
    @phemmy2008 Год назад +1

    You are doing great, keep it up

  • @reginaldibenne6875
    @reginaldibenne6875 2 месяца назад

    Awesome! Can we still use this method to create Cashflow S-curve?

    • @SoftEdemy
      @SoftEdemy  2 месяца назад

      @reginaldibenne6875 cash flow is something else . I Don't have video of it.
      The graph and calculation is different

    • @reginaldibenne6875
      @reginaldibenne6875 2 месяца назад

      @@SoftEdemy Okay sir

  • @ferdielopez1
    @ferdielopez1 25 дней назад

    Thanks

    • @SoftEdemy
      @SoftEdemy  25 дней назад

      @@ferdielopez1 welcome

  • @samarahmad4784
    @samarahmad4784 Год назад

    Great 👍

  • @agbasogankem7164
    @agbasogankem7164 8 месяцев назад

    Thanks for the training. Is it possible for you to write out these steps? I want to replicate what you just explained by following the steps.

    • @SoftEdemy
      @SoftEdemy  8 месяцев назад

      Check captions

  • @samarahmad4784
    @samarahmad4784 Год назад

    Sir if possible would you please make a video on cost control ...
    Like cash flow to create CBS etc

    • @SoftEdemy
      @SoftEdemy  Год назад

      Sure ,Noted I will make a detailed video on cash flow.

  • @denisagba3955
    @denisagba3955 11 месяцев назад

    I set up my plan with budgeted manhours against our total resources, but everyday the resources will be changing as some workers won’t be available. How do I show this constant change in the resources daily and how do I create an S curve for this?

    • @SoftEdemy
      @SoftEdemy  11 месяцев назад +1

      Create Planned vs actual histogram for manpower

    • @denisagba3955
      @denisagba3955 11 месяцев назад

      @@SoftEdemy So you mean changing the resources each day as they work and comparing it against the baseline resources on primavera? Or just doing it on excel?

    • @SoftEdemy
      @SoftEdemy  11 месяцев назад +1

      @denisagba3955 apply same actual on both.
      Show same curve in both P6 and excel

    • @SoftEdemy
      @SoftEdemy  11 месяцев назад +1

      @denisagba3955 you can only show actual histogram separately its also acceptable.

    • @SoftEdemy
      @SoftEdemy  11 месяцев назад +1

      @denisagba3955 you can only show actual histogram separately its also acceptable.

  • @Omer-b7p6d
    @Omer-b7p6d Год назад

    how to convert budgeted units to manpower?

    • @SoftEdemy
      @SoftEdemy  Год назад

      P6 have default column as budgeted labor units .

    • @omeryasin23
      @omeryasin23 Год назад

      @@SoftEdemy I want to show manpower (Not labor units) on a monthly basis. How can I do that?

    • @SoftEdemy
      @SoftEdemy  Год назад

      @omeryasin23 resource assignment > Group and sort by > Resources . Change the user preferences to what measures do you want like Manpower by day per hour per week or per month. Choose the unit which you need to show in resource assignment.
      Every resource per day assignment will be their.
      Make sure while doing all this your schedule is loaded with resources as per their productivity rates .
      Thanks.
      For monthly basis change user preferences units to month and time scale should be also in month