How to prepare recovery schedule in P6 | Recovery Plan P6 Step by Step Complete Guide

Поделиться
HTML-код
  • Опубликовано: 2 дек 2024

Комментарии • 41

  • @SoftEdemy
    @SoftEdemy  Год назад +1

    EV=PV revised schedule video
    ruclips.net/video/iwiMyK_9_eo/видео.html

  • @SoftEdemy
    @SoftEdemy  2 года назад +1

    To read the article visit at www.softedemy.com/how-to-prepare-recovery-schedule-in-p6/
    Introduction
    Overview of Recovery Schedule
    Difference between Revised schedule and recovery Schedule.
    Recovery Schedule
    Revised Schedule
    What are the methods or techniques of schedule recovery?
    Crashing Technique
    Fast Tracking Technique
    What is Recovery Schedule?
    How to prepare recovery schedule in P6?
    Earned value management concept during prepare recovery schedule in P6
    How Global change applies to activity types during recovery schedule in P6
    Step-by-Step Guide to prepare recovery schedule in P6 practically
    Step-01. Remove the baseline if any assigned
    Step-02. Add any additional scope of work
    Step-03. Fix out of sequence activities
    Step-04. Fix unsatisfied relationships
    Step-05. Fix finish dates to existing dates or new approved dates
    Step-06. Fix remaining early start dates for in-progress activities to be = data date + 1
    Step-07. Add or fix cost loading activities if any required
    Step-08. Fix remaining duration decimal if any required
    Step-09. Fix actual Start dates of in progress activities
    Step-10. Perform Global change for completed and In progress activities
    Three Ways To Fix The Issue With In-Progress Activities
    First Way
    Second Way
    Third Way
    Video demonstration of the whole article on how to prepare recovery schedule in P6
    Conclusion

  • @mohdmuzu142
    @mohdmuzu142 День назад

    I noticed you're using Global Change to reduce the original duration of activities and have applied a filter for activity status not equal to 'Completed.' However, this approach also impacts in-progress activities. My question is: when the % Complete Type is set to 'Physical,' reducing the original duration of in-progress activities doesn't affect their finish date because the remaining duration remains unchanged, and the finish date is calculated based on the remaining duration. How can we effectively perform crashing for these in-progress activities as well? please correct me if i am wrong. also let us know easy method to do crashing or fast tracking, as I have 40,000 activities schedule.

    • @SoftEdemy
      @SoftEdemy  День назад +1

      @mohdmuzu142 I don't think you fully understood the video. There are many additions and changes required, and we will update the content to provide more comprehensive details.
      First, there is no filter in the global change for setting the activity status as "not equal to completed."
      Second, we never instructed you to change the percentage. Please review the formula used to calculate the new start date and remaining duration. A lot of important details were missing due to video editing.
      For a more thorough understanding, please refer to the article where the process is described in detail.
      However, before closing, I must emphasize that this is not the final version. We plan to release an updated tutorial, which might take some time, but the technique is now more refined and detailed.
      Keep in mind that this is an older video, but it may still be useful for certain cases or projects.
      If it helps you, feel free to continue using it; otherwise, consider updating the method.

  • @SoftEdemy
    @SoftEdemy  Год назад

    WhatsApp:wa.me/+923155537580
    Website : www.softedemy.com
    For any query contact us on our email : info@softedemy.com

  • @laraSheDigiConstruct
    @laraSheDigiConstruct 2 года назад

    Thank you for this in depth explanation.

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Welcome, Long time to see you. how is the work going on.

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Welcome,your feedback is appreciated

  • @NANYANG-ju3su
    @NANYANG-ju3su 6 месяцев назад

    Hi Sir , I 'd like to know how can I get that column named A-new start actual start Date ? It can be set by myself ?

    • @SoftEdemy
      @SoftEdemy  6 месяцев назад

      User defined field

  • @BedarBukhat
    @BedarBukhat 5 месяцев назад

    Hii Sir ,
    When we getting approval of baseline from client/ Consulta nt then from this baseline we we prepare recovery plan and adding percentage of each activity and adding actual dates of each activity? Before adding actual dates and percentages we remove the assign baseline?

    • @SoftEdemy
      @SoftEdemy  5 месяцев назад +1

      @@BedarBukhat recovery baseline are prepared on update schedule not baseline schedule

    • @BedarBukhat
      @BedarBukhat 5 месяцев назад +1

      @@SoftEdemy we take copy of baseline and then we update the schedule ?

    • @SoftEdemy
      @SoftEdemy  5 месяцев назад +1

      @@BedarBukhat no use previous weekly and monthly updated schedule

    • @BedarBukhat
      @BedarBukhat 5 месяцев назад

      @@SoftEdemy if we don’t have previous updated schedule and if I am doing first time update the schedule then I can do this?

    • @SoftEdemy
      @SoftEdemy  5 месяцев назад

      @@BedarBukhat yes then you can do this. First update the schedule them recovery schedule

  • @hamzarehman4948
    @hamzarehman4948 3 дня назад

    How u add A - integer??

    • @SoftEdemy
      @SoftEdemy  3 дня назад

      @@hamzarehman4948 user defined field column

  • @mohammedzeeshan4405
    @mohammedzeeshan4405 2 года назад

    Sir, after removing baseline from the schedule my baseline finish date & finish date is not showing same. What should I do?

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Contact to my WhatsApp number given at the end of video.thanks

  • @businessshout228
    @businessshout228 Год назад

    I dont have integer column, how i will have this column ?

    • @SoftEdemy
      @SoftEdemy  Год назад

      It's user defined field add from user defined field

    • @hamzarehman4948
      @hamzarehman4948 3 дня назад

      Add as a text or integer??

  • @malikkhan7510
    @malikkhan7510 2 года назад

    Thank you

  • @Juankuribe
    @Juankuribe 2 года назад

    Why are you changing the actual start dates? why this this change being performed? So now the schedule will show different actual dates different than the project records

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Read the article pinned in the comments
      You will understand everything

    • @Juankuribe
      @Juankuribe 2 года назад

      @@SoftEdemy Thanks for the article. I

    • @SoftEdemy
      @SoftEdemy  2 года назад

      @@Juankuribe welcome

  • @muhammadsaad883
    @muhammadsaad883 2 года назад

    please , can you send me the file in this video?

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Please get the downloadable file from the below link
      www.softedemy.com/product/recovery-schedule-july-2022/

  • @yuminxu4806
    @yuminxu4806 2 года назад

    STEP 6 is not been explained

    • @SoftEdemy
      @SoftEdemy  2 года назад

      Read the article for detail .All the doubts and answers of questions have been given in it

    • @SoftEdemy
      @SoftEdemy  2 года назад

      See the end of the video ,their is other method to fix actual start date.thats also step6 . For more in detail .Read my article

  • @patrickpat9721
    @patrickpat9721 Год назад +1

    Ur all video is quite informatics. However, u need to improve ur since way of explanation

    • @SoftEdemy
      @SoftEdemy  Год назад

      Thanks for your feedback. I will improve. I like it.

    • @patrickpat9721
      @patrickpat9721 Год назад

      @@SoftEdemy
      Is is mandatory to assign cost in schedule to reflect the schedule %complete at wbs level

    • @SoftEdemy
      @SoftEdemy  Год назад

      @@patrickpat9721 yes

    • @patrickpat9721
      @patrickpat9721 Год назад

      @@SoftEdemy
      Does schedule %complete will reflect at wbs level if we assign only resource labor without price or anything.

    • @SoftEdemy
      @SoftEdemy  Год назад +1

      @@patrickpat9721 without cost no scedule and performance percent complete