Make This Awesome Gantt Chart in Excel (for Project Management)

Поделиться
HTML-код
  • Опубликовано: 21 ноя 2024

Комментарии • 268

  • @adelinogoncalves9963
    @adelinogoncalves9963 8 месяцев назад +21

    The most intelligible Gantt Chart tutorial I´ve seen by far, thanks a lot Kenji, great job!

  • @deansdrone
    @deansdrone 7 месяцев назад +27

    Thank you so much really fun learning this. In the formula =EN(H$7>=$C10;H$7

    • @ondrop
      @ondrop 7 месяцев назад +2

      same here :) thanks man!

    • @annablarin6092
      @annablarin6092 2 месяца назад +2

      In the above formula I'm not being able to clear the "$" symbol

    • @furkanyildirim3644
      @furkanyildirim3644 2 месяца назад +2

      We considered 1 week as 5 days. Therefore, we need to multiply cell E10 by 1.4 and write it into the formula. As a result, the final form of the formula will be as follows:
      =AND(H$7>=$C10;H$7

    • @Marlon-yx1gg
      @Marlon-yx1gg 3 дня назад +1

      @@furkanyildirim3644 Thank you, I was pulling my hair out trying to figure out why it wouldn't work for values above 50%.

  • @thanh-tunglai8778
    @thanh-tunglai8778 8 месяцев назад +3

    Thank you, Kenji, I wish I had found your channel sooner.

  • @pushparajput5209
    @pushparajput5209 8 месяцев назад +4

    again, I find my interest to learn excel, after listening you. thank you

    • @KenjiExplains
      @KenjiExplains  8 месяцев назад +1

      that's awesome to hear thank you!

  • @BrendaDolloff
    @BrendaDolloff Месяц назад +5

    Can you explain how to calculate the progress figures; it looked like you just entered random numbers. Thank you!

  • @jnerikaat
    @jnerikaat 12 дней назад

    Omg, how did you become such a genius at such a young age. Awesome! Thanks!

  • @danguardo9501
    @danguardo9501 8 месяцев назад +2

    great video, thank you. i also had some issues using network days. is there a solution? can you create predecessors or dependants?

  • @HotButteredCorn
    @HotButteredCorn 4 месяца назад +18

    Kenji: Outstanding! Very helpful. Thank you. However, for those of us who actually practice project management, there are a few items missing in many Excel Gantts. Tasks often need to include one of the following:
    Finish-to-Start (FS): Task A must be complete before Task B begins.
    Finish-to-Finish (FF): Task A must be complete before Task B can be complete.
    Start-to-Start (SS): Task A must have started before Task B can start.
    Start-to-Finish (SF): Task A must have started before Task B can finish
    Any ideas about how to include this? 🙄😀

    • @probodhnayak3167
      @probodhnayak3167 2 месяца назад

      I too have a problem with designing this in the excel Gantts Chart

    • @davidcollins6976
      @davidcollins6976 5 дней назад

      In lieu of any better solution (and I'm sure there is one), I just manually decide on start and end dates for those relative tasks

  • @Consultelainewilliams
    @Consultelainewilliams 5 месяцев назад +5

    This is the most straightforward Gantt chart I’ve come across. I completed it and felt very accomplished. Thank you.

  • @chrisbillingtonhughes78
    @chrisbillingtonhughes78 3 дня назад

    This was so useful Kenji, thank you. I have subscribed.

  • @me2507b4u
    @me2507b4u 7 месяцев назад +7

    Thank you, Kenji! This video was a life saver. Really well explained. I was able to create a project plan so easily. Much gratitude to u!

  • @VishnuVardhan-sj6nd
    @VishnuVardhan-sj6nd 8 месяцев назад +5

    Hey Kenji! Great Lesson as always :) I noticed that when I apply 'Networkdays()' in the 'Days' cell, the final 'dark green fill' doesn't get tabulated properly. I switched to simple subtraction of 'end date' - 'start date' and the fill works perfectly.

    • @KenjiExplains
      @KenjiExplains  8 месяцев назад +1

      Thank you! Awesome that you figured that out 👍

    • @sudhakarnote
      @sudhakarnote 8 месяцев назад

      Excel file link ..pls share

    • @pinko-u6y
      @pinko-u6y 2 месяца назад +3

      the final "dark green fill" didn't work for me either but your comment inspired me to figure out what the issue was. So apperently the rule we created for the dark green fill didn't take weekends in account. So we need to modify the formula =AND(H$10>=$C12, H$10

    • @JBIFSGuides
      @JBIFSGuides 24 дня назад

      @@sudhakarnote make it yourself friend.

  • @timbo4519
    @timbo4519 16 дней назад +1

    gonna take me some time to wrap my head around this but I like this approach

  • @mr.alsifat1504
    @mr.alsifat1504 8 месяцев назад +4

    It was a breakthrough for me,
    So easy way to understand and creating a gantt chart. Thank you.

    • @KenjiExplains
      @KenjiExplains  8 месяцев назад

      That's awesome to hear thank you for your comment :)

  • @kinesiology-moves9598
    @kinesiology-moves9598 7 месяцев назад

    Thank you Kenji. Great tutorial. I am a complete Xcel Beginner, so I don't know where these formulas all come from. How can I learn more about that?

  • @packard37
    @packard37 21 день назад

    WOW. solved so many doubts in such a short video

  • @Edgardo-c2g
    @Edgardo-c2g 9 дней назад

    Very nice and easy to understand tutorial ever..more power to you Kenji.

  • @rexencatz9075
    @rexencatz9075 8 месяцев назад +1

    Hello Kenji thank you very much. How about if you want to revise the end date while still reflecting the original end date? Example you want to extend the end date by 2 more weeks. Thank you for noticing..

  • @ijeunachukwu8925
    @ijeunachukwu8925 7 месяцев назад +1

    THE BEST SO FAR

  • @daisysarming3546
    @daisysarming3546 7 месяцев назад +1

    Thank you so much for that insightful easy to follow tutorial.

  • @MSshorts..-iq7os
    @MSshorts..-iq7os 7 дней назад

    Love you sir Your are best teacher in the world❤

  • @kutub52
    @kutub52 6 месяцев назад +4

    This video deserves more likes and more views, awesome content

  • @pete7019
    @pete7019 6 месяцев назад

    This is really great! Got mine set up! I did notice though that the -1 fix doesn't work for all of the bars. I changed my progress % to all 100 and there was one bar that wasn't showing full. When changed to all 0%, two bars showed a start. Rest of it work great!

    • @pete7019
      @pete7019 6 месяцев назад

      Actually, removing the -1 is what causes the two green bars but the rest show no progress

  • @kabeerjijel4688
    @kabeerjijel4688 5 месяцев назад +3

    Thanks.Great job. I completed the Gantt chart and am very excited to implement it. You are excellent, sir

  • @jayscore7182
    @jayscore7182 5 месяцев назад +1

    Thank you helps a lot! What can I add to my function so weekends don't become highlighted on gantt by the dates for start and end?

  • @md.anwarulkabir3020
    @md.anwarulkabir3020 Месяц назад +1

    Hi Kenji. Thanks for this, really awesome!!! Just one point if the end date exactly matches with the date of the calendar then the last cell doesn't take the green color due to this minus 1 in the formula. Could you please check and suggest how can I clear it? Appreciate!

    • @robinjohansson685
      @robinjohansson685 20 дней назад

      I had the same problem, but seemed to have solved it by adding +1 to the day counting formula. So the number of days are correct. Otherwise it seems to now count first or last day. 1 day activities show 0 days etc. So in column for Days I write: =IF(C11="";"";D11-C11+1) So adding the +1 before last ) compared to video.

  • @MitchellArgall
    @MitchellArgall 6 месяцев назад +1

    I did not have the "freeze pane" in my Gantt chart. Makes it much more appealing now. This was an awesome video and your speaking tone was spot on and easy to follow along.

  • @ayushikar25
    @ayushikar25 10 дней назад

    Thank you! This video was very helpful and informative

  • @thefuturepacesetters
    @thefuturepacesetters 4 месяца назад

    Great work done. It was fantastic one. However, when I got to the percentage side, I was getting True throughout. What could be the problem?

  • @sapaktam2550
    @sapaktam2550 3 месяца назад +4

    this is very good. i have been doing this manually. draw and update the bar chart manually. i got 2 problems with this template:
    No. 1: when my starting date for an activity is in the middle of the of the week. the schedule marking in green show the following week.
    No. 2. if my starting date and finished date fall in the middle of the week, the green schedule does not appear at all.

    • @anouko.9001
      @anouko.9001 3 месяца назад

      I have the same problem(s) and I haven't figured out how to fix it. I concluded that: if start of the week is 29-07-24 but the start of task is 1-08-24 it is somehow not considered greater than or equal to 29-07-24... :(

    • @ennurbardakc6966
      @ennurbardakc6966 17 дней назад

      does anyone know the solution?

    • @thularematlaba196
      @thularematlaba196 9 дней назад

      Check your Conditional Formatting formula as well as the area it Applies to. Mine changed itself and I had to correct it before it worked.

  • @PeterSimons-d5h
    @PeterSimons-d5h 3 месяца назад

    Just used Kenji's explanation to make my first construction timeline. Easy to understand and translate to my own works
    Thanks!!!!!!!

  • @PavankumarHarapanhalli
    @PavankumarHarapanhalli 6 месяцев назад +4

    Thank you for the great explanation; If the number of days is

    • @V21IC
      @V21IC 4 месяца назад +1

      The percentage status is per week or part of a week.
      It's either 100% or 0% of a week.
      There's another technique that requires a lot of formulas and some coding.

  • @arpanatikekar8699
    @arpanatikekar8699 Месяц назад

    Thank you for such a brilliant and detailed explaination!

  • @raja.mubbasshir9072
    @raja.mubbasshir9072 5 месяцев назад +5

    Thank you so much, just a questions, the %completion not working fine with small duration tasks, like say the task is 7 days or so with weekly scale

    • @sukocoimam4519
      @sukocoimam4519 4 месяца назад

      or small sub task just for 1 day

  • @suhass7164
    @suhass7164 2 месяца назад

    Thanks Much for explaining with lot of patience and highlighting about formulas in detail

  • @RCSMgmt
    @RCSMgmt 4 месяца назад +1

    This is brilliantly executed; informative, concise, yet thorough-not to mention polished. Thanks very much taking the time, it's been extremely helpful.

  • @araze3195
    @araze3195 8 месяцев назад +10

    Hi the progress bar and timeline doesnt coordinates when you use network days, can you please tell how to fix it?

    • @furkanyildirim3644
      @furkanyildirim3644 2 месяца назад

      We considered 1 week as 5 days. Therefore, we need to multiply cell E10 by 1.4 and write it into the formula. As a result, the final form of the formula will be as follows:
      =AND(H$7>=$C10;H$7

  • @kamaldhamija3288
    @kamaldhamija3288 6 месяцев назад +2

    Thanks Kenji, it was total fun to learn this from your video, keep progressing and if possible can we show the delayed task in this gantt chart

  • @KevinOKeefe-qw8cl
    @KevinOKeefe-qw8cl 5 месяцев назад +1

    Thanks. Very helpful for making a quick gantt chart for simply tracking projects without having to use MS Project.

  • @heshamhaboob3285
    @heshamhaboob3285 Месяц назад

    Thank you very much, sir, but I have a question. If I have an activity for a period of time and there are two days off during that period, what is the equation that I can enter so that the period of implementation of this activity is extended for two additional days?

  • @alizameeruddinkhan3916
    @alizameeruddinkhan3916 5 месяцев назад +5

    can you provide a downloadable link for this Gantt chart ?

  • @BKZ897
    @BKZ897 Месяц назад

    awesome video .... most useful video I have ever seen for project management 🙏🙏🙏

  • @chukwudichukwuma3309
    @chukwudichukwuma3309 Месяц назад

    Please, which formula did you use for the progress, that converted it to percentage or did you manually type the figures?

  • @tahirif1138
    @tahirif1138 6 месяцев назад +2

    This the 1/3 excel gantt chart video I seen and tested that actually works. Great work keep it up.

  • @udaysinhbhosale788
    @udaysinhbhosale788 8 месяцев назад +4

    Thanks for this video, seems there is issue in formula. week numbers are derived by adding +7 for each week, however for progress you have considered only workweek (5 days i.e =AND(H$7>=$C10;H$7

    • @zinzinrhea
      @zinzinrhea 7 месяцев назад

      =AND(H$7 >= $C10, H$7

    • @furkanyildirim3644
      @furkanyildirim3644 2 месяца назад

      We considered 1 week as 5 days. Therefore, we need to multiply cell E10 by 1.4 and write it into the formula. As a result, the final form of the formula will be as follows:
      =AND(H$7>=$C10;H$7

  • @okasanjaya6587
    @okasanjaya6587 6 месяцев назад +3

    Thank you for the amazing content, very helpful in making the Gantt Chart easier with the simple explanation in this video, god bless you Kenji 😇💚

  • @dblo01
    @dblo01 5 месяцев назад +2

    I love how the "Most replayed" slider bar looks like a mountain range with the amount of people going back to see how you did stuff.

  • @themosdiary
    @themosdiary 6 месяцев назад +1

    Thank you so very much for the insightful video, this was truly simple and easy to follow. I have just made my first gantt chart with no cheat and I feel proud.

  • @kaanmai
    @kaanmai 3 месяца назад

    Kenji, How do you add start and end dates to the chart bars? for each project timeline.

  • @KunalJhavar
    @KunalJhavar 7 месяцев назад

    Hello,
    It is very nice and informative video. However, i am facing issues in month timeline as it was not showing proper % marking on the chart.

  • @durga8285
    @durga8285 3 месяца назад

    you were amazing! And helped save the day for me! Clear, right pace and very articulate!
    Thank you!

  • @alexmaniyacherryjoseph5689
    @alexmaniyacherryjoseph5689 5 месяцев назад

    Thanks for the video. How can I remove Saturday and Sunday if I do it on days?

  • @stellastelione8988
    @stellastelione8988 2 месяца назад

    Thank you very much for thid dynamic tool! It is very helpful in case other PM tools are not available.

  • @JoshuaTurnbull-r5s
    @JoshuaTurnbull-r5s 4 месяца назад +1

    Great Video - I am having trouble with one part though. I have 25 weeks in the project, however when my progress is at 100%, it only fills up 18 weeks (and not the full 25). It also allows my progress bar to reach 160%, and only then will all 25 weeks be green. I have set the Progress bar min/max between 0 and 1. What am I missing? How can I extend the green bar to all 25 weeks to signify 100% complete?

    • @JoshuaTurnbull-r5s
      @JoshuaTurnbull-r5s 4 месяца назад

      This might be wrong, but I managed to achieve the result by multiplying my business day column by 10/7 within the conditional formatting formula, to account for the weekends being added

  • @wendeesexton3607
    @wendeesexton3607 2 месяца назад +2

    Do you have example for gannt per hour over multiple days

  • @RoxanneWilliamson-ez8zb
    @RoxanneWilliamson-ez8zb 4 месяца назад +1

    Thank you so much ! I do a lot of data analysis and tracking so this is very helpful 👏🏾

  • @Laura-lq9ox
    @Laura-lq9ox Месяц назад

    Is it possible to use a gantt chart over a 5 year projection with the project scenarios, each with various activities? Everything I see is shorter term and wondering if it's Gantt charts have certain timeline limitations. thank you -- Laura

  • @r1cer825
    @r1cer825 5 месяцев назад

    This is one of the best, or the best tutorial I have ever seen for that kind of stuff... great job. You're really informing and smooth.... great job.... thx for that. was looking for such a video for a long time...

  • @AmaraGreyRC
    @AmaraGreyRC 4 месяца назад +1

    Very very helpful Kenji!!!!

  • @V21IC
    @V21IC 4 месяца назад

    Wow! Thank you!
    I've seen anything looking easier!
    I'll have to test it though.

  • @mohamedghadi988
    @mohamedghadi988 2 месяца назад

    Thank you for this interesting Gant Chart

  • @asselzhakenova9843
    @asselzhakenova9843 2 месяца назад

    thanks so much, I have used it today. very handy.

  • @lpaone01
    @lpaone01 5 месяцев назад +1

    Thank you, Kenji. That was priceless.

  • @TurtleMingea
    @TurtleMingea 6 месяцев назад +6

    For MAC users, you need to select new rule --> classic --> use a formula... (for the conditional formatting part with the dynamic slides) and use ; rather than ,

  • @Nabd-16
    @Nabd-16 8 месяцев назад

    My best wishes for continued success.. Is it possible to pass on the news as I am just beginning?

  • @cigartrend
    @cigartrend 25 дней назад

    hope it works tried many online templates finally can make my own

  • @lovelyespinosa1760
    @lovelyespinosa1760 Месяц назад

    Hi! I have a question. What if you have broken start date and end date, meaning you have 2 sets of dates in a single row. Can you make the progressive filled chart that will adapt to the 2 sets of date?

  • @ajanstudio343
    @ajanstudio343 3 месяца назад

    Superb! The best! Thank you very much!

  • @M1800dk
    @M1800dk 5 месяцев назад

    Hi again, and sorry, but I found out :-) In Denmark we have to ude ; instead of , so now it works fine, so tanks for a super tutorial 👍

  • @TheArcadeGirl
    @TheArcadeGirl 6 месяцев назад

    This tutorial taught me a lot. Absolute legend!

  • @KalAlam-fk8tx
    @KalAlam-fk8tx 6 месяцев назад

    Thanks Kenji, Awesome detailed vedio and you do it simply as normal.

  • @jeremymcdonald6928
    @jeremymcdonald6928 4 месяца назад +1

    This is a really great chart. I really appreciate the time you took to make this video. It is super helpful. One bit of advice, slow down when you are talking. You are moving way too fast in speech and in video. This is a VERY GOOD tutorial, but you move WAY too fast to follow - and I am experienced in excel.

  • @richardmones9617
    @richardmones9617 5 дней назад

    very Nice Sir Kenjie!

  • @hasanmohammadtareq89
    @hasanmohammadtareq89 8 месяцев назад +1

    Awesome! Thanks from Bangladesh.

  • @timoOAK
    @timoOAK 2 месяца назад

    Hi thanks for the video, works well overall.
    Still have some problem the %completion is not working fine with small tasks( day task) hoe can I fix that

  • @KevinDeAnda-vw7ww
    @KevinDeAnda-vw7ww 5 месяцев назад +1

    Great video, Awesome job!

  • @trudyjose9978
    @trudyjose9978 3 месяца назад

    Simply the best🙌🏾

  • @naylin6451
    @naylin6451 5 месяцев назад

    Thanks so much, bro. I moved along with your video and learned new tactics.

  • @tuncaykamas5275
    @tuncaykamas5275 2 месяца назад

    Voow many thanks, you are awesome man

  • @yoddhasingh31
    @yoddhasingh31 5 месяцев назад

    Thanks Kenji , you're a lifesaver

  • @jesseegitaine4219
    @jesseegitaine4219 4 месяца назад +1

    You are GREAT! Thank you!

  • @vtanz
    @vtanz 7 месяцев назад

    Looks good. Suggestion to include business working day Mon to Friday and exclude holidays

  • @TheSmartShoppersGuide
    @TheSmartShoppersGuide 8 месяцев назад

    Thanks for your helping me increase my excel skills

    • @KenjiExplains
      @KenjiExplains  8 месяцев назад

      that makes me happy to hear thank you!

  • @khwaab4284
    @khwaab4284 5 месяцев назад +1

    Brilliant. Loved it

  • @jk30109
    @jk30109 2 месяца назад

    Thank you sir, it is very helpful.😇

  • @jayv6960
    @jayv6960 3 месяца назад

    The video was beneficial and very well put together. However, there is one issue that I found. The colored progress bar doesn't correctly reflect the start and end date. Example: Row 11 start date is 19-Jan-2024, and the color bar is showing it starting from Wk 3 instead of Wk 2. Ideas on how to resolve that would be greatly appreciated.

  • @raviv5109
    @raviv5109 3 месяца назад

    Thank you so much for sharing!

  • @SS-bn8lp
    @SS-bn8lp 6 месяцев назад

    I'm having trouble with the If Formula in the Days column. Can you show how to add the IF condition if you're using Networkdays?

  • @JBIFSGuides
    @JBIFSGuides 24 дня назад

    Great video!!!

  • @sophykeo9639
    @sophykeo9639 8 месяцев назад +2

    please make a video , for example, task3 start date after task2 completed.

  • @JenniferShiels
    @JenniferShiels 7 месяцев назад +1

    I can't see why but the darker colour on each task doesn't work for every task. It shows the progress for the first two. I can't figure out what went wrong. Otherwise it's the best video I have found. I missed something along the way though.

  • @BetaniaMengistie
    @BetaniaMengistie 8 месяцев назад +1

    I'm trying to do the same as you but number months! instead of weeks. what do i put in the format cells - custom ???I tried mm instead of wk # but that just gives the month not the number of months???? HELLPPPPPPPPPPPPPPPPP. Thanks for this tutorial super helpful for a task i got at work related to PM :)

    • @V21IC
      @V21IC 4 месяца назад

      Set the interval to +30 instead of +7.
      And change WK# to Mnth #

  • @gauravjain1653
    @gauravjain1653 5 месяцев назад +1

    Nicely Explained....

  • @Sonicexeclub
    @Sonicexeclub 8 месяцев назад +1

    Thank you for this awesome tutorial, I know have a beautiful Gnatt chart thanks to your guidance 😁😁

  • @DhuhaAlshdid
    @DhuhaAlshdid 6 месяцев назад +1

    GREAT HELP, THANK YOU

  • @MrMatox323
    @MrMatox323 4 дня назад

    How do you add the IF formula to the NETWORK formula together?

  • @ahmedsani6591
    @ahmedsani6591 5 месяцев назад +1

    Awesome! Thank you.

  • @DesarrollosyContenidos
    @DesarrollosyContenidos 2 месяца назад

    hi Kenji, Don't you sell this spreadsheet? I would love to learn how to do it but unfortunately I don't have time.

  • @connectingmodi1328
    @connectingmodi1328 5 месяцев назад

    @kenji, Thank you for the wonderful video. I have a question wherein my start date and end date does not have either monday or friday assuming my project starts on monday then the gantt chart does not show bars shown in the right mapped to the week in green color. Please assist. Thank you

  • @akingstruth
    @akingstruth 7 месяцев назад +2

    I appreciate you for this.