Planning Engineer Interview Assignment 01 by using Primavera P6 | Construction of Office Building

Поделиться
HTML-код
  • Опубликовано: 9 сен 2024

Комментарии • 46

  • @SoftEdemy
    @SoftEdemy  11 месяцев назад +1

    File Link www.softedemy.com/product/p6-interview-assignment-01/ ‎

  • @ammarkhan8548
    @ammarkhan8548 10 месяцев назад +3

    Thanks alot SoftEdemy for Such extensive Contents for Planning field❤

  • @Aleemkiyani
    @Aleemkiyani 10 месяцев назад

    Great effort. A detailed and informative video. Thanks for sharing your experience

  • @niazhussain2993
    @niazhussain2993 7 месяцев назад

    Thanks, it's very informative and interesting for working planning engineers

    • @SoftEdemy
      @SoftEdemy  7 месяцев назад +1

      Welcome

    • @niazhussain2993
      @niazhussain2993 7 месяцев назад

      @@SoftEdemy excellent work 👌

    • @niazhussain2993
      @niazhussain2993 7 месяцев назад

      @@SoftEdemy "Could you please consider creating a video on helpful Excel formulas and techniques that can significantly save time for planners and boost their productivity?"

    • @SoftEdemy
      @SoftEdemy  7 месяцев назад

      @niazhussain2993 sure I will consider in future

  • @rajasekarr4516
    @rajasekarr4516 10 месяцев назад

    Very useful it was. Thank you so much.

  • @user-gk6je5cc7m
    @user-gk6je5cc7m 7 месяцев назад

    Great video Sir

  • @abdullahriaz033
    @abdullahriaz033 10 месяцев назад

    Please such important concepts as i have to shift ksa in next 10 days it will be beneficial for me

    • @SoftEdemy
      @SoftEdemy  10 месяцев назад

      This assignment is KSA assignment . Watch all our videos

  • @danishhasware3762
    @danishhasware3762 10 месяцев назад

    sir the content was excellent need more assignment which are used in corporate level like having more than 2500 activities

    • @SoftEdemy
      @SoftEdemy  10 месяцев назад

      These are just interview assignments, not complete projects.
      We will also upload complete projects.

    • @balakrishnanharishanth1071
      @balakrishnanharishanth1071 10 месяцев назад

      I am waiting for that video sir

    • @SoftEdemy
      @SoftEdemy  10 месяцев назад +1

      @balakrishnanharishanth1071 it's your choice. As we have a busy schedule. We don't promise for that. If you are professional, then you will know the commitment of planner.
      So we cannot promise. Without wasting your time, please find any trainer at your end.

  • @AliRaza-kv9hm
    @AliRaza-kv9hm 3 месяца назад +1

    Use ctrl + shift+ arrow 🔝🔚🔜⬇️ to move the wbs

    • @SoftEdemy
      @SoftEdemy  3 месяца назад +1

      Good info thanks

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      We haven't focused on it because we don't load wbs manually. We use our tools.
      Please check assignment 03 . How we do it . Without using any shortcut key

    • @AliRaza-kv9hm
      @AliRaza-kv9hm 3 месяца назад

      I'm also at the beginning stage to learn about primavera P6 from RUclips.
      Always share knowledge with others..

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      @@AliRaza-kv9hm sharing is very good

  • @kedareknathbankar
    @kedareknathbankar 3 месяца назад

    Good 👍😊

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      Thanks for your comment

  • @soorajkrishna7234
    @soorajkrishna7234 3 месяца назад

    Hi, Thanks for the detailed explanation.
    I have a small doubt. MEP WBS duration was supposed to increase by 60 days as per the assignment. But as activities are running in parallel, will the overall MEP duration increase by 60 days in this case?.

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      First of all , thanks for commenting. Your question is good.
      Orignal duration = planned duration also . So don't mixup duration types in P6 .
      See actual duration if you want to see increase.
      While learning don't copy steps. Listen what we are explaining. It's more beneficial.
      Keep commenting and asking from us in future also

  • @ImranKhan-fj7fh
    @ImranKhan-fj7fh 10 месяцев назад

    Dear Faisal Mukhtar, Help me also to become another Planner from KIT Family. 😀, anyhow best effort & wish you best of luck for future.

    • @SoftEdemy
      @SoftEdemy  10 месяцев назад

      Sure why not RUclips channel is their ,also my WhatsApp number is their ,You can contact me their.

  • @rajasekarr4516
    @rajasekarr4516 10 месяцев назад

    If possible please make a video on critical path analysis of a real time project.

  • @unknownperson1550
    @unknownperson1550 3 месяца назад

    I have joined as a planning engineer in Gulf for the first time, but I don't have any experience in planning before. By simply doing p6 training course and some theoretical studies,I have successfully got this job , but now I don't have any idea what exactly I have to do. Can you please suggest what I can do since I only know p6.
    Or atleast tell me specific job activities of a planning engineer in refinery means what work will be given to me. And what work on excel as well. I have still 7-8 days in hand to be shifted to refinery.

    • @SoftEdemy
      @SoftEdemy  3 месяца назад +1

      Email to our team at info@softedemy.com
      They will guide you

    • @unknownperson1550
      @unknownperson1550 3 месяца назад

      Thank you ​@@SoftEdemy

  • @msprojectplanning
    @msprojectplanning 9 месяцев назад

    Sir there is huge missing in the baseline schedule you have prepared!
    According to DCMA 14 points manuals,the float shouldn't be higher than 44 days while here i see the float is even high than 80 days even in a single activity 😊

    • @SoftEdemy
      @SoftEdemy  9 месяцев назад

      The assignment has full filled all the criteria given.
      No debate with leaners.
      Please keep learning after years you will understand what was the purpose of video . Is it baseline schedule video or interview assignment video.
      Also you will understand about float limits. What if project duration is 3 months and what if project duration is 3 years.
      So keep try to learn.Softedemy team are professionals in planning and we know what is wrong and what is right practice of scheduling.
      So keep try to learn. Also learn what are percent of activities allowed with greater float occupying activities.
      This is not right or wrong place. We always deliver filtered and more precise content at our plateform

    • @msprojectplanning
      @msprojectplanning 9 месяцев назад

      Okay thanks sir I just commented what a feel wrong.
      Anyways thanks for your kind words ❤

    • @SoftEdemy
      @SoftEdemy  9 месяцев назад

      @@msprojectplanning welcome

  • @missmikeecruz
    @missmikeecruz 3 месяца назад

    Hi. I'm following all your steps in this video but when I schedule my primavera, the total floats are the same but sub floats are completely different. Can you please explain what are the factors that made my schedule different from yours eventhough I 'm doing the same steps as yours. Thanks a lot!

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      Sorry, you have got this issue.
      May be their is some section of the video in which I have assigned other relationship .so it's possible the result would be different for other activities.
      But don't worry if the duration is OK and finish dates are OK and total float are not higher then limits. Then enjoy the skills you gave learned in this video.
      You can contact us at wa.me/+923155537580
      Or you can comment here we will reply.
      Have a good day

    • @missmikeecruz
      @missmikeecruz 3 месяца назад

      Thanks for your reply. May i know what are the limits for floats?​@@SoftEdemy

    • @SoftEdemy
      @SoftEdemy  3 месяца назад

      @missmikeecruz 5 % of activity count.
      And the higher total float may be allowed by contract 28,44,60 days
      As per total duration decided by consultant. But DCMA allow 44
      excluding milestones, engineering, procurement activities. In some projects

  • @syedamaan5520
    @syedamaan5520 4 месяца назад

    i need a copy of excel sheet sir, thanks

    • @SoftEdemy
      @SoftEdemy  4 месяца назад

      Link available in comment