Interview Assignment 03 for Planning Engineer by using Primavera P6 | Building Works
HTML-код
- Опубликовано: 3 дек 2024
- WhatsApp:wa.me/+9231555...
File Link : www.softedemy....
Store Link: www.softedemy....
Contact us on info@softedemy.com
Interview Assignment 03 for Planning Engineer by using Primavera P6 | Building Works
1:15 - Overview of Today's Assignment
2:11 - Discussing WBS Level 3 and Long Lead Items
3:09 - Estimation of Productivity Rate and Labor Equipment Resource
4:03 - Allocating Material Resource & Unit Cost
5:04 - Baseline Assignments and Reporting Proficiency
5:55 - Starting the Assignment with Excel
6:45 - Setting up the Spreadsheet and WBS Levels
11:38 - Adjusting Milestone Dates and Remarks
16:28 - Check Project Cost for Verification
17:21 - Weightage and Cost Analysis
17:36 - Organizing Cost Data
17:50 - Breaking Down Work Breakdown Structure (WBS)
18:10 - Introduction to Procurement
18:26 - Distinguishing Construction vs. Installation
18:49 - The Role of Substructure Work
19:00 - Importance of Lead Long Items
19:23 - Work Breakdown Structure Level Three
19:35 - Earthwork in Building Analysis
20:00 - Superstructure Work Overview
20:18 - Understanding Concrete Work
20:38 - Architectural Work Details
21:10 - Mechanical HVAC and Plumbing Walkthrough
21:52 - Electrical Systems Overview
22:06 - Testing and Commissioning
22:55 - Procurement Process Steps
26:00 - Activity Codes & Their Importance
28:48 - Differences Between Activity Codes & ID
32:37 - Creating Activity Names and Descriptions
34:02 - Introduction to Material Resource Codes
34:37 - Updating Pay Item Numbers and Assigning Weights
40:46 - Setting Up Productivity Columns and Rates
44:02 - Introduction to Productivity Rate Sheet
46:04 - Explanation of Hour per Quantity vs. Quantity per Hour
51:33 - Calculating duration and peak availability
53:36 - Organizing sections and clarity enhancement
55:05 - Creating the resource dictionary
55:42 - Introduction to productivity rate
56:04 - Initiating WBS in Excel tool
56:35 - Calendar creation and modification in Primavera P6
57:45 - Adding project details in Primavera P6
59:10 - Default settings and date setup in Primavera P6
1:01:14 - Filtering and setting up the resource dictionary
1:02:37 - Equipment categorization and resource export
1:10:05 - Using WBS (Work Breakdown Structure) Codes
1:11:05 - Organizing Contractual Milestones and Submissions
1:14:04 - Duration Estimates and Activity Planning
1:18:03 - Activity ID Mapping and Importing to Primavera P6
1:19:06 - Resource Management: Next Steps and Considerations
1:23:16 - Finalizing Resource ID and Cost Parameters
1:30:38 - Perform CPM Scheduling
1:41:00 - Exploring Work Sheets and Project Duration
1:43:00 - Recap: Comparing Dates and Duration Adjustments
1:52:40 - Scheduling and understanding the timeline dependencies
1:54:34 - Assigning and maintaining baselines
1:54:58 - Setting Primary baselines and project reflections
1:55:17 - Generating early start and planning weekly costs S Curve
2:09:27 - Finalizing Weekly Early and Late Data Graph
2:11:52 - Extracting Monthly Manpower Values
2:12:24 - Creating a Manpower Histogram
2:16:58 - Preparing for Bulk Commodity
02:28:01 - Interacting with Commodity Levels
02:28:29 - Filtering Critical Activities in Excel
02:29:05 - Identifying Open-Ended Activities
02:31:00 - Filtering Critical Paths & Adjusting Dates
02:32:10 - Previewing and Printing Critical Activities
02:33:10 - Addressing Non-Critical Activities
2:39:10 - Introduction to Critical Path & its Importance
2:41:07 - Techniques to Monitor Project Progress
2:41:58 - Progress Measurement Sheet (PMS) Explained
2:47:35 - Conclusion & Invitation for the Next Content
Other Relevant Videos.
Resources Calculation with Productivity Rates in Projects at all Industries | Assign in Primavera P6
• Resources Calculation ...
Check out our channel here:
www.youtube.co...
Don’t forget to subscribe!
CHECK OUT OUR OTHER VIDEOS
FIND US AT
www.softedemy....
GET IN TOUCH
Contact us on info@softedemy.com
FOLLOW US ON SOCIAL
Get updates or reach out to Get updates on our Social Media Profiles!
Twitter: / faisalm15432091
Facebook: / softedemy
Instagram: / softedemy
LinkedIn: / softedemy
Telegram: t.me/Softedemy
Contact Us
WhatsApp:wa.me/+9231555...
#softedemy,#Planningengineer,#primaverap6
Disclaimer:- This channel does not promote or encourage any illegal activities and all content provided by this channel is meant for EDUCATIONAL PURPOSE only. Copyright Disclaimer: - Under section 107 of the
Copyright Act 1976, allowance is made for FAIR USE for the purpose such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statutes that might otherwise be infringing. Non- Profit, educational, or personal use tips the balance in favor of FAIR USE.