  • @sachinmondkar9720
    @sachinmondkar9720 Год назад

    Both are the experts from 2 continents, I known Nikesh and I follow Mr.Hany , both are having there individual expertise …Nikesh is oracle expert and trainer 👍

  • @abdulhameedalkaseri5727
    @abdulhameedalkaseri5727 2 года назад +2

    Engg. Hani Ismail is Very generous and gentle. Regards and best wishes.

  • @bt856
    @bt856 2 года назад +2

    Excellent Interview with Engineer Nikesh
    Love your confidence, knowledge base and smart excel tool you used to create the schedule Engr. Hany Ismail
    Please accept my sincere respects for the great initiative and all your efforts to support Project Planning Fraternity
    Best Regards,
    Bhisham

  • @aftabhussain2786
    @aftabhussain2786 2 года назад +1

    You’re doing great job for Planning Engineers community 👏

  • @abdulhameedalkaseri5727
    @abdulhameedalkaseri5727 2 года назад +2

    I saw your video @Engg.Haany Ismail about importing excel file in primavera long back. You have Very good skills.
    Both of you guys having amazing skills and knowledge thanks for sharing so valuable discussion with us.
    Best regards and hope such discussion in future could benefit us more.

  • @sirtajulhaq5630
    @sirtajulhaq5630 10 месяцев назад +1

    really enjoy the interview thank you for uploading such Interviews personally i learned alot from your channel and i also share your channel with alot of my friends
    thank you

  • @AbhijeetKumar-up2xz
    @AbhijeetKumar-up2xz 2 года назад +2

    yes it was a very fantastic interview and very motivated also

  • @dineshveera786
    @dineshveera786 2 года назад +3

    Hai Engg... We need the much more knowledge about piping (oil & gas) scheduling and tracking.. Please upload next video towards piping planning engineer duties and responsibilities.

  • @abdulhameedalkaseri5727
    @abdulhameedalkaseri5727 2 года назад

    Thanks Engg. Nikesh Bihare for your advice and valuable information and knowledge.

  • @shakeeln2020
    @shakeeln2020 Год назад

    Mr. Hani is experienced in engineering field planning and management
    Good knowledge shared 👍

  • @debabraatachakraboorty1135
    @debabraatachakraboorty1135 2 года назад

    It's Great to see you in this interview and hope whatever extra you will compile from Excel will share with us to keep us updated in line with you. Let's learn with you.

  • @unnigovind4125
    @unnigovind4125 2 года назад

    Eng, Hani, You are doing great things especially these interviews. Planning engineer/Manager scope and designation in India is entirely different from Middle east. You can see Planning Managers in India with just 1year planning experience where in middle east it's difficult even if you have more than 15years experience especially in big companies . So you have to consider this while doing the interviews in India, other wise it will be misleading. A planning engineer in my team recently joined as Planning Manager, that is Senior Manager in India 🤔. It's depends on the countries and the usage of Primavera.

  • @jeevankg
    @jeevankg 2 года назад

    For 10% if you keep changing baseline, it may not be right approach. But if you mitigate the variance then that it recovery schedule, which is still on the boundry of baseline, except the schedule progress changes from that cutoff is different from baseline progress.

  • @zeeshanaliquazi8606
    @zeeshanaliquazi8606 2 года назад +1

    Everything cannot be done as per Client's will,as he hired you(Nikesh) as a professional to drive a project in a good and finish it will it goal.
    No change order is required to update baseline...

  • @marlonrojas7700
    @marlonrojas7700 6 месяцев назад

    Hi there dears Eng! very good interview, but i guess the project control in excel so many cods, and it can be more easy to control and to export to an project planning software, other wise, the major level of detail for project control is better in excel. Thanks

  • @shefequeak2440
    @shefequeak2440 23 дня назад

    As Mr. HAany described he doesn't know the baseline can be changed and also he doesn't know there is a recovery plan without change order.For changing that no need change order to be agreed by client. Moreover a planning engineer should be master in sequence of activities and well knowledge about the site conditions and practical to execute the works.To understand and forest the delay may happen earlier rather than a master in softwares. He is not a IT engineer. He is basically a civil engineer

  • @samarahmad4784
    @samarahmad4784 Год назад

    21:15 agreed

  • @osamarabie5714
    @osamarabie5714 2 года назад +1

    Eng Hany, I didn't see that course in your website, can you please share the link here?

    • @PlanningengineerNet
      @PlanningengineerNet  2 года назад

      Hello Engineer Osama. The course is not public because it is still on progress (expected to be finish by end of this month). However, if you want to start now and study the finished lessons (around 70% completed) you can find it in this link: planningengineer.net/courses/construction-project-planning-intermediate-level-with-p6-excel-powerbi/

  • @ankit31189
    @ankit31189 10 месяцев назад

    Hello sir, Can I get the Excel sheet. It can be helpful to me.

  • @khanabulaas7321
    @khanabulaas7321 8 месяцев назад

    Sir any demo session for planning Engineer

  • @mkd.2023
    @mkd.2023 2 года назад

    It is unfair to underestimate the software tools which are being used for planning ,it is hard to acquire skill in software tools and need lot of efforts and time. all major industries like airports, railways, banks .etc..systematically Manages their operations by using some kind of software tools only.otherwise it is impossible .
    Planning is not just preparing schedules and reports using primavera or any other tool . But project planning in EPC environment is impossible without using so said planning tools like primavera or ms project etc..How a project can be tracked without knowing the critical path atleast. A well prepared cost loaded / resource loaded P6 schedule is a valuable asset which eliminates many headaches.Only such a schedule is enough for preparing daily, weekly, monthly reports including other project summary reports quickly. Moreover presenting details by using graphs, charts or diagrams are much more effective than using boring spread sheets or tables in many occasions. It has been seen
    Many mangers whore are arised from construction field specifically show their less interest in project schedules or planning softwares for the reason their are not comfortable with it or they they don't have much control on it.

  • @MD-lk4qr
    @MD-lk4qr 2 года назад

    I would like to connect with you and consult about my career.. how can i reach out to you?

    • @PlanningengineerNet
      @PlanningengineerNet  2 года назад +1

      You are welcome.
      WhatsApp: +201277767728
      Email: Info@PlanningEngineer.Net

  • @ZakeerMuback
    @ZakeerMuback 9 месяцев назад

    Seems like indian manager is talking based on theory not in practical..