TRACK your PROJECT ACCOMPLISHMENT with this ONE Simple System

Поделиться
HTML-код
  • Опубликовано: 6 сен 2024

Комментарии • 6

  • @ninetofiveengineers
    @ninetofiveengineers  11 месяцев назад

    Hi everyone, just to inform you that we have Facebook group, a venue where you can ask questions and share your knowledge in project planning, and primavera. facebook.com/groups/572488634916619/?ref=share_group_link

  • @joepherguilingan94
    @joepherguilingan94 3 месяца назад

    Thanks sir....

  • @Sam_1417
    @Sam_1417 11 месяцев назад

    Thanks sir, very helpful po

  • @karlovincicaballero4156
    @karlovincicaballero4156 7 месяцев назад

    Thanks

  • @masayahingkusinera5142
    @masayahingkusinera5142 7 месяцев назад

    Thank for the tip that you provide sir but what if the BOQ is greater than the actual quantity even the actual reaches 100% accomplishment? How can we solve this issue? Thank you

    • @ninetofiveengineers
      @ninetofiveengineers  7 месяцев назад

      If the BOQ qty is higher, you may want to consider the following formula:
      (BOQ Qty - Balance QTY in actual)/BOQ QTY.
      Example:
      BOQ Qty = 500 sqm
      Actual Qty = 300 sqm
      Accomplished Qty = 200 sqm
      Balance Qty = 100 sqm
      % of completion = (500-100)/500 = 80%