How to Analyze Variance in Microsoft Project

Поделиться
HTML-код
  • Опубликовано: 16 сен 2024

Комментарии • 4

  • @dronepilot1840
    @dronepilot1840 7 месяцев назад +1

    Hello Howard, I'd like to see a video on reserve contingency, what it is and how to use it and how to update and track the reserve contingency

    • @DaleHowardProjectMVP
      @DaleHowardProjectMVP  7 месяцев назад +1

      Wow, that's a really good question! There are lots of ways to handle risk contingency, including for schedule, work hours, and costs. Would you please navigate to the following URL, click the Contact Me link, and then enter more detailed information for background on your need? Then I will put this question on my list of future video topics.
      www.dalehowardmvp.com/
      Thanks!

  • @tamshaytv
    @tamshaytv 3 месяца назад

    Hi, Dale
    in my Project file, we used to close the tasks form %Complete option by giving 100%, but we do not change the finish date.
    example : finish date 30 Apr, but we change the %complete to 100% on 30 May without changing the finish date. can i do analyze variance ?

    • @DaleHowardProjectMVP
      @DaleHowardProjectMVP  3 месяца назад

      If you are only entering a % Complete value, but are not capturing the Actual Start and Actual Finish dates for the task, then you will NOT be able to do variance analysis. Hope this helps.