Blue line | ORR METRO | K R Puram to Silkboard FEB 2024 Updates
HTML-код
- Опубликовано: 15 окт 2024
- Blue line | ORR METRO | K R Puram to Silkboard junction FEBRUARY 2024 Updates
Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM
ಬಿಎಂಆರ್ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್ ಜಂಕ್ಷನ್ನಿಂದ ಕೆ.ಆರ್.ಪುರ | ಒಆರ್ಆರ್ ಮೆಟ್ರೊ
***********************************************
FEBRUARY 2024 Updates
Recorded Date : 04-FEB-2024
Civil Contractor :
PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement
PKG2 - Shankaranarayana Constructions PVT ltd - 9.744 KM
ಸಿಲ್ಕ್ ಬೋರ್ಡ್ನಿಂದ ಕಾಡುಬೀಸನಹಳ್ಳಿಯವರೆಗಿನ ಪ್ಯಾಕೇಜ್ -1 ನಿರ್ಮಾಣ ಗುತ್ತಿಗೆಯನ್ನು ಆಫ್ಕಾನ್ಸ್ ಸಂಸ್ಥೆ ಪಡೆದಿದ್ದರೆ,
ಕಾಡುಬೀಸನಹಳ್ಳಿಯಿಂದ ಬೈಯಪ್ಪನಹಳ್ಳಿಯವರೆಗಿನ ಎರಡನೇ ಪ್ಯಾಕೇಜ್ನ ಗುತ್ತಿಗೆಯನ್ನು ಶಂಕರನಾರಾಯಣ ಕನ್ಸ್ಟ್ರಕ್ಷನ್ ಪಡೆದಿದೆ.
Stations in the stretch :
Central Silk Board Station ( Interchange with Yellow line ) : Pier casting has begun.
HSR layout Station : All pier cast up to concourse level. CC Connector erection in progress
Agara Station : All pier cast up to concourse level.CC Connector erection in progress
Ibbalur Station : All pier cast up to concourse level.
Bellandur Station : Platform level and concourse level arms launching has begun.
Kadubeesanahalli Station : All Piers cast up to concourse level.CC Connector and TL connector erection.
Kodibeesanahalli Station : All pier cast up to concourse level. CC Connector and TL connector erection.
Marathahalli Station : Concourse beam casting in progress.
ISRO Station : All piers cast up to concourse level.CC Connector erection in progress
Doddanekundi Station : All pier cast up to concourse level
DRDO sports complex Station : Concourse arms and track level arms erection in progress
Saraswathi Nagar Station ( Mahadevpura ): Concourse slab casting works in Progress
K R Pura Station ( Interchange with Purple line ) : Concourse beam being cast
#bmrcl #bangaloremetro #ORRMetro
In 3 yrs 3lines will open to public 24-yellow line,25 -pink line,26 blue line definetly 40% of traffic will solve for sure😊❤.BLR😊 now BLR has improved from 2nd position to 6th position in traffic congestion due to opening of the entire purple line👍.
By 3 years we can expect completion of suburban rail too, further reducing traffic congestion
Thank you for these sincere updates!
Really helps the citizens get up-to date with the latest progress!
And nice music too 👌
thanks.
I appreciate your hardwork on capturing and editing this video, soo beautiful and perfectly. Thanks for uploading, such a good quality video. I request all the viewers to support him by subscribing to his channel and sharing this video as much as possible.
ಸೂಪರ್ 🎉🎉🎉🎉🎉
Afcons are slowed down in case of U girders ..? Lots of piers with with caps are available. But why aren't they going ahead with the Girders !
This LG thing which was to be their strength is turning out be their weakness since it becomes serial. One cast-in-situ pier cap, or a station means they ahve to wait for it to complete and then proceed further. They have now achieved a better level. Hopefully they do better in the coming months. And plus they start using the Cranes for U girder and not solely depend on the LG's
@@SunilHP there are many places where they go ahead with cranes like Iblur , HSR , Kadubeesanahalli Underpass.
Yes. they did. But they have been too conservative on using them. I feel they can do more.
What is LG?
@@sachinjogi1995 launching girder that you see near bellandur Station and another nearing ibbalur
Work is goin in good speed in pink line already track laying work is started out of 24 tbm 22 have completed only 2left for drilling purpose👍
Yes. And touch wood we should have a breakthrough tomorrow if all goes well.
Hi sir we are eagerly wiating for u march month metro videos 😊
Ah probably by next weekend. Got busy this weekend and hence could not shoot
Sure😊 thanks for your reply.
This year we can see good improvement in traffic management in BLR city due to below reasons 1.Opening of yellow line metro 2.Opening of green line extension metro.3.Introduction of Moderato Signal in 28 junctions.4.Opening of STRR road from Dabaspet to Hosakote.5.Opening of the new flyover at silk board junction🙂👍.BLR will definitely come out of this traffic issue very soon All Izz Well😊❤️.
Thanks for the video! Can u try to give update on the green line as well !😃
Green line as in Nagasandra to BIEC extension is it ? Will try
Today finally tbm badhra had a break through at tg halli station in pink line 😊
Are stations in this stretch expected to have dedicated space for 2/4 wheeler parking?
Station plans are not made public yet. But DULT is working with metro for the last mile connectivity plans, to eliminate this park and travel.
@@SunilHP Thanks for the reply. 👍 Some cities they have parking place at metro stations though.
@@chetan_naikWithin BMRCL too most of Phase 1 station and some of phase 2 stations have.. But along ORR as you know property prices are at a premium. so may hinder..
Could you please send the spreadsheet fot pier progress
Hi Ajish the previous sheet is not maintained anymore.
Thanks for the video.. I suppose you have taken the video sunday post noon ;)
Mostly I shoot on Saturdays either mornings or afternoons when traffic is less and a little blessing of Sun God 🌞
whats the matter of the railway bridge near isro station no construction???
No cause for worry. Piling is completed for all 4 piers. One rebar is up, and other is in the works today. There is one being on test for load . So will happen in due course.
Yellow line prototype train from Crrc china has reached chennai port today 😊.by Feb 20 it will reach blr by road 👍 then testing process will start.😊
Bro how good is the progress?
pretty good. Substructure works are coming to a close. Super structure ( U girders ) works will now pick up pace.
07:32 is the first eccentric pillar cap? Why are others not being put up?
Actually what you see in 7:32 ORP480, the second eccentric pier cap. Just behind that around 7:29 mark you can see the first eccentric cap ORP481 was placed and then U girders were erected too
Qatar or dubai jaisa road ko need and clean banana chahiye. Wire ko vi under ground karna chahiye
What is pocket track?
In the thumnail image you see they are building a short 500 meter line parallel to the viaduct. this is pocket track. for emergency to push faulty trains and allow normal operations on main line, or stable additional trains and things as such.
LOOKING AT how dirty the city i thought it was mumbai
Why change the music? :P
Apparently that is the most asked comment across my video :-) so i had to resort to
Brother , when did u take this video😂 , there is literally no traffic
I generally take video over weekends. 👍
Still Feel that Works are Very Slow No U girders are done faster as of now
Yes. This LG thing which was to be AFCONS's strength is turning out be their weakness since it becomes serial. One cast-in-situ pier cap, or a station means they have to wait for it to complete and then proceed further. They have now achieved a better level. Hopefully they do better in the coming months. And plus they start using the Cranes for U girder and not solely depend on the LG's
No matter how fast we made metro lines there is no train available to run on this, yellow lines are rotting while eagerly waiting to be fucking tested
Yellow line is ready and eagerly waiting is an assumption. stations from Silkboard to Jayadeva are just about getting completed and then 3rd installation has to happen. So far only energized by between Bommasandra to Bommanahalli. Agreed there is a delay in Rolling stock but other things are yet to fall in place too.
BJP 2024 ❤️