how to derive labor and material cost for skim coating per m2

Поделиться
HTML-код
  • Опубликовано: 4 окт 2024

Комментарии • 10

  • @eldriannelouieopon6695
    @eldriannelouieopon6695 9 месяцев назад

    thank you for this knowledge sir!

  • @likha360
    @likha360 9 месяцев назад

    thank po

  • @likha360
    @likha360 9 месяцев назад

    quantity surveyor po ba kayo dati..ano po recommended nyo na books etc..for bagohang qs

    • @axcelengineering
      @axcelengineering  9 месяцев назад +1

      actually site engr. ako ...last position ko is pic...kahit hindi qs dapat as civil engr. kaya mo dapat mag derive...ung books eh fjardo at toralba...ang mahalaga eh site recording...tandaan o e record ung mga experiences mo.

    • @likha360
      @likha360 9 месяцев назад

      thanks po sa tutorial.
      @@axcelengineering

  • @BobBaldesancho
    @BobBaldesancho 7 месяцев назад

    Boss Axcel Productivity rate ng Gabion installation.thanks

    • @axcelengineering
      @axcelengineering  7 месяцев назад

      hindi ko pa na experience gabion!!!pero cge e search ko...

    • @axcelengineering
      @axcelengineering  7 месяцев назад

      I have made a research on gabions eto nadampot ko...productiviy 1.25cum to 1.5 cum-1man-1day..mukhang may project ka na river control o retaining wall.sa productivity kasama na ung cage fabrication.

    • @BobBaldesancho
      @BobBaldesancho 7 месяцев назад

      @@axcelengineering thank Boss Godbless

    • @axcelengineering
      @axcelengineering  7 месяцев назад +1

      @@BobBaldesancho boss baka pede mo i share channel ko lalo na dun sa mga newly grad. makatulong eto sa kanila tnx.