what is the role of a site engr.

Поделиться
HTML-код
  • Опубликовано: 26 ноя 2024

Комментарии • 3

  • @jamessontimola1134
    @jamessontimola1134 3 месяца назад

    Good Job po Engineer! Very informative po

  • @axcelengineering
    @axcelengineering  3 месяца назад +1

    Also include the 10dia. bar and tie wire in the tabulation!!!for 1sqm. area masonry multiply by 3m bar length...ex. 84sqm/day x3m=252m...then 252 divide it by 6m length of 10dia. bar...=42pcs bars x6 days =
    252pcs/week...6m is commercial length.For tie wire get the weight of the reinforcement....
    252pcs x 6m x 0.617kg/m=933kg wt. of reinforcement...then 933 x .02kgwire/kg rebars =19kg/week tie wire...FYI

  • @mmaarena6494
    @mmaarena6494 3 месяца назад

    Can you please share the excel file?