For material reconciliation purpose below items way of working out material co-efficient consumption with reference of CPWD code. 1. Solid Concrete block masonry works - 8", 6" and 4" Block works 2. Vitrified tiles flooring 3. Ceramic Dadoing works (Tile) 4. Tiles skirting 5. Granite / marble/ kota stone/ tandur stone flooring 6. Lift granite cladding 7. way of workout grouting powder requirement for tiling work 8. Plaster mesh fixing with cement mortar 9. External (high rise above 10 floors) plastering 10. Plaster bands 11. Grooves in plaster 12. SSM work 13. IPS flooring 14. Screed concreting
Amount: 1 cubic foot (cu ft - ft3) of volume Equals: 43.30 kilograms (kg - kilo) in weight Converting cubic foot to kilograms value in the beach sand units scale.
Sir m very glad to learn about civil engineer practical knowledge from your channel... Sir I request you to make for me one vedio, for type lV residential building billing, that will be very helpful in future. And i hope you will make it very soon...
Sir i appreciate your lecture and it is so brief and easy understanding. the only thing which I missed, what is the quantity of water ? how to calculate ? is there any thumbrule ? if it is there then plz rply me sir.
Salaam Alekum bhai , aap buhut achhi information, knowledge dete ho, Allah aap ko salamat rakhe bhai aap flate ki measurement kese karte hain jab ke room ki dono taraf ki widths aur lengths baraber nahon iske bare me bhi please bataye shukriya
SIR.. mje agaya smjh m jo appne smjhaya... ab mje ye janna hai ki estimate, no of steel, bricks, vol of concrete kese nikaalte hain??? kya ye janne k liye site pr jana padega ya ap smjha skte hai???
hello sir,.Please small request u are prepared lot of videos from rcc , at the same you can make to formwork videos .please sir diffrent types of formworks , falure of jock maxmm span , how many nos used.. etc..
I appreciate your assistance for civil Engineers,additionally I would like ask you to prepare steel bar layout work lectures in foundation,column beam and slab.
I’m not an engineer but would like to know. How do you convert sand cft into volume like 0.483cft of sand for for the proposed dimensions. How much sand is that in volume?
Sir, please tell me, During calculation of quantities of material Why we take 33% for plastering & 54% for concreting. Tell relation between this wet and dry volume.
Sir I have some question The amount of cement required for 1m cubic plaster in 1:5 ratio and another questions the amount of cement required for 1m cubic mortar 1:6 plaster plzzz solve it sir actually important for this
N plz make a video sir all mortar proportion of all construction field... As per is code... I m so confused see different different answers... Plz make it fast if possible...
For joint filling a certain % age nearly 20% is added over wet volume by other engineers, thus creating a confusion. which one is correct may kindly clarify.
For material reconciliation purpose below items way of working out material co-efficient consumption with reference of CPWD code.
1. Solid Concrete block masonry works - 8", 6" and 4" Block works
2. Vitrified tiles flooring
3. Ceramic Dadoing works (Tile)
4. Tiles skirting
5. Granite / marble/ kota stone/ tandur stone flooring
6. Lift granite cladding
7. way of workout grouting powder requirement for tiling work
8. Plaster mesh fixing with cement mortar
9. External (high rise above 10 floors) plastering
10. Plaster bands
11. Grooves in plaster
12. SSM work
13. IPS flooring
14. Screed concreting
Thank you for teaching us about building
I don't know why i m herw on ur video....but i want to say ur writing is beautiful
Thanx sir...
Apse bahut kuch seekha ...
Love you sir
Nice video sir very good idea
Nice video sir easy to learn everyone
very easy way to caculate.thanx
Amount: 1 cubic foot (cu ft - ft3) of volume
Equals: 43.30 kilograms (kg - kilo) in weight
Converting cubic foot to kilograms value in the beach sand units scale.
Sir m very glad to learn about civil engineer practical knowledge from your channel... Sir I request you to make for me one vedio, for type lV residential building billing, that will be very helpful in future. And i hope you will make it very soon...
NICE VIDEO,,,,, PLZ tell how to calculate consumption for Random Rubble masonry
Sir i appreciate your lecture and it is so brief and easy understanding. the only thing which I missed, what is the quantity of water ? how to calculate ? is there any thumbrule ? if it is there then plz rply me sir.
Which one is better for plastering
sir your all lec best for learning sir request plz aplod how to mark column footing position actual site
Sir Mai aapki video se rate analysis sheeka Ho.... thanks sir
Salaam Alekum bhai , aap buhut achhi information, knowledge dete ho, Allah aap ko salamat rakhe bhai aap flate ki measurement kese karte hain jab ke room ki dono taraf ki widths aur lengths baraber nahon iske bare me bhi please bataye shukriya
SIR.. mje agaya smjh m jo appne smjhaya... ab mje ye janna hai ki estimate, no of steel, bricks, vol of concrete kese nikaalte hain??? kya ye janne k liye site pr jana padega ya ap smjha skte hai???
Achi video ha...samaj Aya sara
please discuss on analysis rate for carriage of material
respect from pakistan great effort keep it up bro
Thanks sir ji
Excellent video sir. Thnx a lot.
Thanks u sir for give me teaching
very well explained
hello sir,.Please small request u are prepared lot of videos from rcc , at the same you can make to formwork videos .please sir diffrent types of formworks , falure of jock maxmm span , how many nos used.. etc..
Waw thanks for sharing your knowledge to us
Thnxxx sir plzzz upload a video as per drawing layout how to column mark on the field as per drawing
Excellent sir
nice video.thanks sir
I think you have to show it in right way like
1) How much water should we add W.C ratio
2) Why you take 33% 1.33
Imitiyaz Ghouri
0.4 to 0.6 approx.
bro if you can make video on how to operate auto level and dumpy level. difference between them. that will be very helpful for all freshers.
sir, can u please make a video on how a complete wall is constructed , from basic to a fully complete walls of buildings etc.
Very helpful
Thank You sir for doing such a great videos !! Sir i want to know how can we calculate labor productivity ?
what is the standard mortar proportion ratio of internal n external plaster( plz also mention how it is in single coat n double coat)
I appreciate your assistance for civil Engineers,additionally I would like ask you to prepare steel bar layout work lectures in foundation,column beam and slab.
Nice explanation keep it up, can u able to give suggestion how to calculate the building age
thanks sir..sir please one thing how to know the percentage of material...of all material... thank you
Very good.
I like your videos
Please make a detail video regarding ssm and mortar quantity
Your great sir thanks god bless you sir
nice,thanks sir
Ek no sir
Nice sir
Very good sir g
sir which wall we should keep 9inch and which wall 4.5 inch we should keep i hope u u will solve my prob fast thankyou....
good presentation
Thanks
Pls post where which ratio is used in construction on site plastering for walls
Narayan Bless 🙏 You
hi sir ....plz upload video related to concrete technology in details...used at construction site .....plz
Good work
good video👍👍
Sir plz post a video what is the quantity of water sand and aggregate in building roof construction
Achcha laga
Sir ..... Please take topic on rate annalysis of building in detail
I want to know about %of admixture addition to the concrete, and tell me which type of admixtures r use on which conditions
Super ji
Love your simplicity
hello sir, can u please tell me how to calculate the quantity of sand in CUM.You have shown in CFT in this vedio.
ruclips.net/video/C5h2F92BDrg/видео.html watch my this video Mirza. I hope this video will solve your query
Where u applied density of sand. Directly u went to cft...
this give video in proper formula........................
I’m not an engineer but would like to know. How do you convert sand cft into volume like 0.483cft of sand for for the proposed dimensions. How much sand is that in volume?
Great sir
please make a video on BBS ...I will be highly grateful to you🙌
welldone sir ...... sir please house layout method ka topic b deliver kry please
dear sir aap se request hai ki block masonry me block sand cement ki quantity ka ek video banaye
Sir please advise me how to prepare for opsc exam with video. ...
please put a video for
how to calculate a quantity of paint..?
Sir, please tell me, During calculation of quantities of material Why we take 33% for plastering & 54% for concreting. Tell relation between this wet and dry volume.
how to calculate gypsum plaster quantity for internal walls,
and
how to calculate quantity of color for internal or external painting work...
Sir I have some question
The amount of cement required for 1m cubic plaster in 1:5 ratio and another questions the amount of cement required for 1m cubic mortar 1:6 plaster plzzz solve it sir actually important for this
Hi Can you please explain if there is any difference between estimation of Cement and Sand in the first and coat and second coat of plastering..
Wow accurate
Very use full thank you sir what is 35.31 during sand calculations
1 cum = 35.31 cft
i think 1 cum sand = 1650 or 1700 cft
1 Cubic meter = 35.28 Cubic feet.
Sand Density is 1600 k.g. per Cubic meter.....
sand = 0.01596 x (6/7) x 1600
= 21.888 kg
right.....then why we need sand quantity in cft. ?
Thanks a lot-
thank you so much sir...
For 15 mm thick cement plastering 1:6 on 100 sq.m. new brick work, the quantity of cement required is
N plz make a video sir all mortar proportion of all construction field... As per is code...
I m so confused see different different answers... Plz make it fast if possible...
For joint filling a certain % age nearly 20% is added over wet volume by other engineers, thus creating a confusion. which one is correct may kindly clarify.
Nice teching
thank you sir..
nice one
Pliz do upload English version
Some people say we should take 1.27 for wet to dry
thanx sir.....
I throughly go through your lesson sir I have a problem here how to convert cft into bags or kg
Sir please upload a video about rate analysis of a building
Hello sir, plz can tell me why we increase tha thickness of outer plastering work for ex inner plastering we use 12 mm and out side 20 mm
Hi sir
my name
sameer wasif thanks to gives knowledgeable trikes
You Wecome Sameer
Hello sir ,please make a video on cobiax used in slab casting.
Sir
very use full . 1.33 dry volume.this value constant. which standard using . IS ?
Good Stuff man
Sir please upload videos on how to calculate hunch steel
It is of one wall only or all four sides wall quantity ?
super video
thank you sir. dry volume = 0.012 x 1.33 .(1.33 is how to came sir) Please tell me the explain sir.
brother please make a video of centerline method.
nice video sir
Thanks
1.33 jo he, kya ise cft ke sath bhi multiply kiya ja sakta he? Ya sirf m3 ke liye
Sir internal plaster ratio is 1:4 sir 1:6 ratio is brickwork ratio.
Pradeep gaikwad super
Is for example brother
Thank u sir
nice videos more to more videos send about civil
engneering
Thanks