why are we creating a seperate sheet? We should do this materia tracking in Primavera so that we can link procurement phase with construction activity. In this way, If our activity execution date changes, material procurement dates will also be changed accordingly.
Indeed, Faisal Gulzar You are correct; we can manage in Primavera P6, which is the most effective approach to handling everything. In fact, we already do that in our practice. The tutorial was published for those who are unfamiliar with Primavera P6 or who work in the procurement or administration departments. As a result, the planner will provide them the ledger to follow and then they will send updates on a daily, weekly, and monthly basis. Furthermore, 40-50% of planners are still creating monitoring sheets and other documents using Excel. Thank you
Thanks for the video but can there be a way to automate this so you don’t have to retype everything from the Primavera. I have used Power Query to pull data and refresh from Primavera. It’s a waste of time retyping everything that already exists in the database
Please specify which section of the video you are referring to. We can complete this job using a number of other programs and approaches, so pay close attention to the approach that the video explains. You can write to us here if you have any concerns.
@@PLANNINGP6 the section where you were retyping the materials into the spreadsheet. Imagine I have 500 materials in P6, do I have to type or copy over all the 500
@@ebenasare8661 The primary goal of the video is to demonstrate the concept. You can choose to manually enter data into the sheet or transfer from Primavera P6.
why are we creating a seperate sheet? We should do this materia tracking in Primavera so that we can link procurement phase with construction activity. In this way, If our activity execution date changes, material procurement dates will also be changed accordingly.
Indeed, Faisal Gulzar You are correct; we can manage in Primavera P6, which is the most effective approach to handling everything. In fact, we already do that in our practice.
The tutorial was published for those who are unfamiliar with Primavera P6 or who work in the procurement or administration departments. As a result, the planner will provide them the ledger to follow and then they will send updates on a daily, weekly, and monthly basis.
Furthermore, 40-50% of planners are still creating monitoring sheets and other documents using Excel.
Thank you
Thanks Brother for so useful Vıdeo
Most welcome
Thanks for the video but can there be a way to automate this so you don’t have to retype everything from the Primavera. I have used Power Query to pull data and refresh from Primavera. It’s a waste of time retyping everything that already exists in the database
Please specify which section of the video you are referring to.
We can complete this job using a number of other programs and approaches, so pay close attention to the approach that the video explains. You can write to us here if you have any concerns.
@@PLANNINGP6 the section where you were retyping the materials into the spreadsheet. Imagine I have 500 materials in P6, do I have to type or copy over all the 500
@@ebenasare8661 The primary goal of the video is to demonstrate the concept. You can choose to manually enter data into the sheet or transfer from Primavera P6.
Can in get soft copy sir.
Please share the excel.sheet link through Google drive.
Okay will upload, as soon as possible.
Can i get the soft copy, sir??
The file preparation technique that has been demonstrated is simple. You must pay the small fee for the file if you still require it.