Materials Procurement Scheduling in a Baseline Programme

Поделиться
HTML-код
  • Опубликовано: 5 май 2022
  • Materials tracking is very important to project success. in this video I will show you how to create Materials Procurement Scheduling in a Baseline Programme to track the materials as per the following sequence:
    1- Material Submittal
    2- Material Approval
    3- PO Issued
    4- Delivery Period
    5- Manufacture Started
    6- Shipment Date
    7- Custom Clearance
    8- Delivery to Site / Store
    Download the materials tracking template from this link: planningengineer.net/material...
    ---------------
    Keep in Touch:
    Join our email Newsletter, we send useful free content regularly: planningengineer.net/newsletter/
    WhatsApp: +201277767728
    Email: Info@PlanningEngineer.Net
    Linked in: / planning-engineer-est
    FaceBook Page: / planningengineerdotnet
    FaceBook Group: / 1138400132963230
    Twitter: / planningeest
    Instagram: / planningengineerest
    ---------------

Комментарии • 15

  • @saramostafa4808
    @saramostafa4808 2 месяца назад

    Jazak Allah kol kheir, I'm transferring my career from sourcing spare parts to procuring construction materials and this video and sheet are life savers.

  • @ahmedradwan1175
    @ahmedradwan1175 2 года назад

    Thank you engineer Hany

  • @sanketsakpal8121
    @sanketsakpal8121 8 месяцев назад

    thank you for help. It was required

  • @engrma3
    @engrma3 2 года назад

    Very useful video thanks for sharing excel sheet.

  • @hanningtonopondo8907
    @hanningtonopondo8907 2 года назад

    Nice Video, I hope one may also learn preparing Materials schedule from a finalised project BOQ .

  • @mohammedabu-elghiet5652
    @mohammedabu-elghiet5652 2 года назад

    Great job as usual from your side... May you upload video, illustrates how to check dangling activities using excel?

  • @abdul1258
    @abdul1258 2 года назад

    Can You please develop a video for E1 & E2 ? it would be very helpful. thanks

  • @jorgeorozco5634
    @jorgeorozco5634 8 месяцев назад

    Got a question, how do you manage when More than 1 PO is required for a certain item you put the actual date for PO once the last PO is placed? same happened to all the Procurement Stages? we are going to put actual dates once last item done?

  • @azharbashir8208
    @azharbashir8208 2 года назад

    Sir please kindly made video on revision and recovery schedule separately...As I tried alot but at the end my Schedule percentage doesn't matches with Actual Performance percentage...😒😒

  • @messivscristiano5987
    @messivscristiano5987 13 дней назад

    The template please

  • @samueldarerotimi1592
    @samueldarerotimi1592 2 года назад

    I can't find the link

  • @syedobaid8598
    @syedobaid8598 2 года назад

    Dear Eng. I am planning to Enroll but there is no response from the Whats app, Please do reply

  • @azharbashir8208
    @azharbashir8208 2 года назад

    Please create a dummy project and change the schedule and recovery plan for the project.... On both of these, I'm completely baffled.

  • @samehelmedany1617
    @samehelmedany1617 4 месяца назад

    Template plz

  • @LAST_Knight2
    @LAST_Knight2 24 дня назад

    ده أنكليزي يا مرسى 😂 و الله تتكلم عربي احسن من هذا الخرط