How to Build a Steel Building - Erection Rundown

Поделиться
HTML-код
  • Опубликовано: 11 июн 2024
  • In today's episode we will go over the entire erection process of building one of our pre-fabricated steel buildings from start to finish. These steps should apply to pretty much any metal building project not just one of ours.
    In future videos we will continue to go over each step of the process in greater detail. You can also find a step by step guide in our erection manual. Like and Follow us to stay up to date as we release more tutorials, tips and videos and Build Great!
    For those of you just discovering us:
    Great Western Building Systems supplies high-quality pre-engineered steel buildings. On this Channel, we host videos of our featured projects, tutorials, how-to, tips and tricks, DIY suggestions, and answer frequently asked questions that new builders and customers commonly have. We hope that with our help anyone can learn how to put up a steel building. Many of our customers put their buildings up themselves, and this channel is a resource to help them every step of the way. Enjoy!
    Tour the Factory Online: bit.ly/GWB360
    Visit Us ►► hello.gwbuildings.com/RUclips
    Get a Quote ►► hello.gwbuildings.com/RUclips
    Or Call Us - +1 (800) 497-2135
  • ХоббиХобби

Комментарии • 14

  • @ThePracticalMechanic
    @ThePracticalMechanic 3 года назад +2

    Thanks for the run down on the shell erecting process.

  • @danmowry3509
    @danmowry3509 7 дней назад +1

    is it normal when you lap the girts/purlins that the holes need to be reamed out?

    • @GWBuildings
      @GWBuildings  7 дней назад

      Hello Dan, Eric here, If the holes need to be reamed that is a sign of something else going on. However.... it is not abnormal - a simple issue with anchor bolts being 1/4 - 1/2" off can lead to some difficulty with laps - so it's a consideration of what is easier to do. Most people, even seasoned erectors, can miss minor deviations with bolts, squarness/plumbness of the building, etc... and not catch it until they are flying purlins - at that point - reaming purlin slots is a lot easier than taking the steel down to ream or slot somewhere else.
      Correct flange lapping and the use of a spud wrench should minimize this. If the holes have to be drilled or moved - it's a good idea to stop work and figure out the root cause - Calling construction support is probably a good idea at that point as well.
      Thanks

  • @Morganexvavation
    @Morganexvavation 2 года назад +3

    Awesome video!

  • @kencoconstruction9236
    @kencoconstruction9236 2 года назад +1

    Nice video. The modulation you talked about is solved easily by securing a tape measure to the first rib. Then you eye on the other side to match. Helps me stay efficient anyway.

  • @josephhalas1676
    @josephhalas1676 2 года назад +3

    You need a complete beginning to end constitution video. There alot of information, visual reference that is missed with these short videos. My building is coming from you guys and I really need more info. There really needs to be a very detailed video on exactly how to do everything from start to finish without these quick rambling videos. PLEASE

    • @Dozz70
      @Dozz70 2 года назад +1

      I'm looking at them for my building. Did you look at other Steel Vendors and why did you choose them? I'm looking at doing a 40 x 50 x 16 or 40 x 60 x 16. Any information would be great for me at this point.....thanks Mark

  • @jeremyreinhold3620
    @jeremyreinhold3620 2 года назад +3

    He he... he said erection...