    @dannyames5089 7 дней назад +1

    This is the most basic grid tied installation you will ever see.
    Just replaced two SMA-2500U's with a single Growatt after my SMA failed for a 4th time I was done. Been using SMA for over 21 years. At 65 pounds each are very heavy to deal with compared to the 33 pound Growatt. Using a MIN 5000TL-XH-US, it was so easy to install. SMA's have a 7 year warranty and I had to pay for 3 separate repairs over the years, what a pain to remove - pay to ship and repair and replace etc. I'm done with SMA. Growatt makes grid tie easy and cheap, and if it craps out - easy to replace.

  • @wolfroad
    @wolfroad 2 месяца назад

    Great video. Two questions. Is the unit waterproof and can be installed outside like you did? Can you sell back to the grid if you have net metering with this set up?

    • @_willalexander.88
      @_willalexander.88  2 месяца назад +1

      Yes it does have an IP rating. Yes if you're net metered it will push back into the grid what's over produced.

  • @dalv086
    @dalv086 Месяц назад

    maxim power from solar panels 2000w?

  • @charliewill4509
    @charliewill4509 2 месяца назад

    so how difficult is it to get a permit and inspections done for your unit and whats the costs / process to do that?

    • @_willalexander.88
      @_willalexander.88  2 месяца назад

      Not bad at all. You will need some structural drawings if you're mounting on the roof which is the worst part. To make sure your roof can support it. About 250$ for those. The rest is an electrical riser diagram, site plan and specs. Permit was about 200$. Contact your county for a list of what you need to obtain a permit and you need to contact your service provider to fill out some stuff with them. They do an inspection after the county permit is finalized. Good to reach out before your install to see there requirements.

  • @cyumadbrosummit3534
    @cyumadbrosummit3534 2 месяца назад

    Been running off grid with no permit for 4 years now with 23kw of roof solar and 66kWh of recycled Tesla S/X modules. If you live in an area with frequent blackouts/ brownouts a grid tie system is worthless. WTF is the point of solar if you powerless like everyone else in an outage? Lastly you'll pay retail for power from the grid only to receive 10% of what you pay (if you're lucky) when you sell energy back.

    • @_willalexander.88
      @_willalexander.88  2 месяца назад

      So, the point is to knock down your high $ bill and make your money back quick. I have a super inefficient rv hooked up full time that uses more power then my house. My power company is with it and we never lose power even during hurricanes. If we do, flip the main and plug in the generator, my solar will assist and let the generator idle mostly. I would not grid tie to make money, only to reduce my bill.

    • @onecrazywheel
      @onecrazywheel 19 дней назад

      You'd have to almost have an inverter generator to work. I years ago hooked up my propane generator 6000w and the grid tie solar system shut off due to frequency issues.

    • @_willalexander.88
      @_willalexander.88  18 дней назад +1

      @onecrazywheel going to test soon. Thanks