How to Use the Primavera P6 Excel Lite Tool : Transform Your Project Controls - Complete Tutorial

Поделиться
HTML-код
  • Опубликовано: 7 ноя 2024

Комментарии • 21

  • @SoftEdemy
    @SoftEdemy  Год назад

    Tool Link : www.softedemy.com/product/primavera-p6-excel-lite-tool/

  • @AhmedMahmoud-es1io
    @AhmedMahmoud-es1io 2 месяца назад

    there is no trial version before completing purchasing process ?

    • @SoftEdemy
      @SoftEdemy  2 месяца назад

      @AhmedMahmoud-es1io product is 100 percent fit . Do no need trail
      Demos are available to see how it works.
      Moreover customer support is provided for custom requirements

  • @durgeshk9204
    @durgeshk9204 Год назад

    Hi, can you tell, if there is 100 labours where should we input this data

    • @SoftEdemy
      @SoftEdemy  Год назад +2

      100 labor per day or 100 hours a labor day. Please explain clearly
      .
      If you have 1000 Nos of labor a day. you have a total no of 1000 manpower as labor resource.
      Then see what are your required histogram manpower
      If you have calculated 1000 no of labor days (Mandays) for certain activity.
      Then first of all recheck it's may be an hours because one single activity cannot have a huge number of manpower loaded to an activity. Their may be 1000 total labor a day but for one single activity it's impossible. Because activities are minimum split to very minimum duration.
      Now if you got the 1000 labors as a result from you productivity rate for that specific activity by dividing from quantity of activity.
      Then put them as budgeted units in the resource after assigning resource as calculated

    • @SoftEdemy
      @SoftEdemy  Год назад +2

      Please follow the below steps to assign manpower or labor resources to your schedule in Primavera P6:
      First, calculate the quantity of activities in the schedule.
      Prepare productivity rates for each activity with all types of resources.
      Calculate total budgeted units for each resource used in specific activities.
      Load into P6 at the Budgeted Units place after assigning the predefined resource dictionary.
      These steps should guide you in properly assigning labor resources to your schedule in Primavera P6. Feel free to reach out if you have any questions or need further assistance.
      Thanks!

    • @durgeshk9204
      @durgeshk9204 Год назад

      First Thanks for quick response, and I'm asking if 10 labour required for particular activity, where should we input that 10 number or can say if foundation work needs 10 labour. And kindly tell how to use shift calendar and shifts

    • @SoftEdemy
      @SoftEdemy  Год назад +1

      @durgeshk9204 10 X Duration of activity X No of hours in a working day = Budgeted units
      Then assign the labor resource to the activity, putting the budgeted units in it.
      Make sure the duration type is set to "fixed duration and units," or you can change it to "Fixed duration and units/time."
      Then there's no need to calculate using the above formula; just add 10 X Working hours a day into the budgeted units/time cell in the resources tab.
      No need to use the Shift option in P6. Instead, duplicate the activities with a second calendar in the evening hours. Create two calendars, one for evening and one for morning. That's a better way to work in shifts. If you use the P6 shift option, it may produce complex results that could be difficult for others to understand. Intelligent people like you can handle it, but it's usually better to represent something in an easy way.
      If you use the Shift option, it will only work in the resource assignment and resource usage profile sections only.

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy thanks a lot for your great assistance, its really very helpful. Good wishes.

  • @engineerkhan6458
    @engineerkhan6458 Год назад

    Very useful. Thanks alot. How to download Primavera excel elite?

    • @SoftEdemy
      @SoftEdemy  Год назад

      Welcome. The link have been given in the description of video. Visit our site

    • @engineerkhan6458
      @engineerkhan6458 Год назад

      @@SoftEdemy thanks

    • @SoftEdemy
      @SoftEdemy  Год назад

      @@engineerkhan6458 welcome

  • @durgeshk9204
    @durgeshk9204 Год назад

    Hi, Can you help me out once again. How to know no. of labour required for some quantity of steel work for given duration or how many days some labours take to do some quantity of steel work?

    • @SoftEdemy
      @SoftEdemy  Год назад

      Contact us at what'sapp

    • @SoftEdemy
      @SoftEdemy  Год назад

      175 Kgs in a day by single steel fixers and helper

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy thanks a lot but how to do in primavera p6.
      And also stuck one more place, if start and finish dates are given, means work has to be done within time period then how to redistribute the duration of activities within that period according to the weightage of duration required more or less in particular activity. Kindly solve this query also

    • @durgeshk9204
      @durgeshk9204 Год назад

      @@SoftEdemy what's the whatsapp no

    • @SoftEdemy
      @SoftEdemy  Год назад

      @@durgeshk9204 wa.me/+923155537580