Tutorial Project Crashing - Intro to Project Management

Поделиться
HTML-код
  • Опубликовано: 16 дек 2024

Комментарии • 4

  • @hans2400
    @hans2400 11 дней назад +1

    🔥🔥n1 dr

  • @AhmedIsLearning
    @AhmedIsLearning 6 дней назад

    in crash 2 why you take G instead of F or B since they have less slop 166,200

    • @ikingdomi
      @ikingdomi  5 дней назад

      You are only limited to choose activities on the critical path A,C,E,G