Can you help me with this please 1. In a typical 7-day period, the planning department of the pizza company programs its "Pizzamatic" machine for 148 hours. It knows that changeovers and set-ups take 8 hours and breakdowns average 4 hours each week. Waiting for ingredients to be delivered usually accounts for 6 hours, during which the machine cannot work. When the machine is running, it averages 87% of its design speed. An inspection has revealed that 2% of the pizzas processed by the machine are not up to the company's quality standard. Calculate the OEE of the "Pizzamatic" machine.
If OEE is low for example 70%, do we need to run the plant for longer to get the same throughout put if OEE was 100%. In case of 70%, should we run the plant for existing run time/0.7 to get the desired throughput?
Hello. How do you calculate an ideal cycle time when the machine that you are measuring has to be operated by a human? Do I need to include an allowance for tiredness? How your performance will behave? Woould it be normal and correct to see perfomance higer than 100%, cause operator in some hours may not be tired? Can we consider the stoppage of equipment as a relief for operator fatigue? Hope you or anybody can aswer my questions.
That's great! I'd would like to ask a question If I may. How many 1% of the OEE would represent in production volume more or less? Thank you Joek! Roger,
Thanks for the video, and making is understandable. I have a problem with Good, Rejects and total pieces. To me the Total is Good + Rejects. Someone had to make the rejects too, right? In your calculations your total is the same with Good. How can that be?
This is OOE (overall operations Effectiveness) where the planned op time is the denominator. TEEP is inclusive of all available Time (24hours* 365days). For OEE the denominator should be 420 (480- planned downtime)
Dear, Please confirm performance calculation. • Performance = (Total Units x Ideal Cycle Time) / Real Run Time. But you mentioned total units / ideal cycle time.
OEE is a nonsense number. "OEE is like using our weight times our height times our systolic blood pressure, as a measure of how good looking we are." - Dr Wheeler
Simple yet helpful, thank you so much for doing this!!!
Enjoyed that, I just need to be able to remember this. Thanks
Simple and easy to follow, thanks for the video.
Your awesome!! Thanks so much 🎉
You maked verry simple in 6 min. THX!
thanks for making this so simple
Can you help me with this please
1. In a typical 7-day period, the planning department of the pizza company programs its "Pizzamatic" machine for 148 hours. It knows that changeovers and set-ups take 8 hours and breakdowns average 4 hours each week. Waiting for ingredients to be delivered usually accounts for 6 hours, during which the machine cannot work. When the machine is running, it averages 87% of its design speed. An inspection has revealed that 2% of the pizzas processed by the machine are not up to the company's quality standard. Calculate the OEE of the "Pizzamatic" machine.
Could be simpler (855/2.6)/480 = same thing
always used for cross-check
If OEE is low for example 70%, do we need to run the plant for longer to get the same throughout put if OEE was 100%. In case of 70%, should we run the plant for existing run time/0.7 to get the desired throughput?
Hello.
How do you calculate an ideal cycle time when the machine that you are measuring has to be operated by a human?
Do I need to include an allowance for tiredness?
How your performance will behave?
Woould it be normal and correct to see perfomance higer than 100%, cause operator in some hours may not be tired?
Can we consider the stoppage of equipment as a relief for operator fatigue?
Hope you or anybody can aswer my questions.
That's great!
I'd would like to ask a question If I may. How many 1% of the OEE would represent in production volume more or less?
Thank you Joek!
Roger,
How to calculate ideal run rate?
Sach a great method
Should come out to 78.3% OEE
Thanks for the video, and making is understandable. I have a problem with Good, Rejects and total pieces. To me the Total is Good + Rejects. Someone had to make the rejects too, right?
In your calculations your total is the same with Good. How can that be?
that calculation is wrong because of that ...i agree with you
this helped a lot, thank you
Hello what are the steps which we need to follow if the oee calculated is below 85%
Thank you!
awesome
availability value can be divided by 420 not 480 ok
Is this really OEE? I think that this is TEEP. For OEE you should callcullate the "Planned op. time" = 480 - 15 - 15 - 30 (planned down times) = 420
Agree with you
exactly, breaks and lunchtime are planned
i have a question on which setup time is also mentioned in problem.is the setup time also considered a planned down time???
True
This is OOE (overall operations Effectiveness) where the planned op time is the denominator. TEEP is inclusive of all available Time (24hours* 365days). For OEE the denominator should be 420 (480- planned downtime)
Can u make this vid again with Close-up
Dear, Please confirm performance calculation. • Performance = (Total Units x Ideal Cycle Time) / Real Run Time. But you mentioned total units / ideal cycle time.
@joek15
OEE is a nonsense number. "OEE is like using our weight times our
height times our systolic blood pressure, as a measure of how good
looking we are."
- Dr Wheeler
Thank You!