Hello, please is there a way u can tell me the cost of everything, like how many tons of 12mm, 10mm and 16mm? Cements? Carpentery cost? Sharp sand? Granite? Workers cost? Kindly help a brother
This is the step by step cost of the expenses in TOTAL: For Casting Suckaway Carpenter 150k Iron Bender: 30k Pipe for Suckaway: 3,500 Binding wire: 18k Iron rod: 60 length 12mm Iron rod 10mm 8 length Nylon: 3k Water proof cement: 25k Cement: 10 bags Sand: 120k Transport of sand : 7k Labor Casting : 55k Water proof cement : 5k Cement: 4 bags Total extra cement: 14 Bags For Plastering of Suckaway : My remaining sand was used Cement 8 bags Waterproof cement: 5k Bricklayer: 22k Sinking of Suckaway: Carpenter 15 wood : 10k 2*3 wood : 5k Block 9: 16* 450 Local government: 50k Construction Nylon: 4000 Waterproof cement: 1500*10= 15,000 3inches nail: 500*2 = 1000 Kuper nail: 500 Cement 10 bags * 7200 = 72,000 Carpenter extra wood: 10,000 COVERING OF SUCKAWAY 12mm: 20 length * 8,900= 178,000 Transport of iron : 5,000 Carpenter: 50k Iron bender : 15k Casting of Suckaway cover: 35k
✅✅✅
Nice one, I have a job for this guys
@@princeadex5907 ok you can reach out by call or WhatsApp 07043129116, thanks
Greetings. Please what's the size of the soakaway?
This is actually a 10by 10 cos it’s on a half plot of land but most people use 12 by 12 depending on the size of the house
Thanks for your reply.
Hello, please is there a way u can tell me the cost of everything, like how many tons of 12mm, 10mm and 16mm? Cements? Carpentery cost? Sharp sand? Granite? Workers cost? Kindly help a brother
This is the step by step cost of the expenses in TOTAL:
For Casting Suckaway
Carpenter 150k
Iron Bender: 30k
Pipe for Suckaway: 3,500
Binding wire: 18k
Iron rod: 60 length 12mm
Iron rod 10mm 8 length
Nylon: 3k
Water proof cement: 25k
Cement: 10 bags
Sand: 120k
Transport of sand : 7k
Labor Casting : 55k
Water proof cement : 5k
Cement: 4 bags
Total extra cement: 14 Bags
For Plastering of Suckaway :
My remaining sand was used
Cement 8 bags
Waterproof cement: 5k
Bricklayer: 22k
Sinking of Suckaway:
Carpenter 15 wood : 10k
2*3 wood : 5k
Block 9: 16* 450
Local government: 50k
Construction Nylon: 4000
Waterproof cement: 1500*10= 15,000
3inches nail: 500*2 = 1000
Kuper nail: 500
Cement 10 bags * 7200 = 72,000
Carpenter extra wood: 10,000
COVERING OF SUCKAWAY
12mm: 20 length * 8,900= 178,000
Transport of iron : 5,000
Carpenter: 50k
Iron bender : 15k
Casting of Suckaway cover: 35k
Wow, good job❤
Thanks so much u are such an awesome man