The answer for CPM question is 24. Since probability is not given but the standard deviation is non zero so the project completion time is certainly more than 20. Only one option is more than 20.
@@SHUNGA_ shunga G probability 68% par wo formula lagta hai.. aise kaho toh mai 99.9% probability par 3sigma laga deta hu... None of the option correct. Thodi self respect rakho aur selfish Mt bani
Sir, dynamic compaction can be light or heavy, so no of layers, height of fall, weight of hammer & no of blows all can vary... Therefore, none of the given answers is right... U may refer IS-2720 PART 16
Critical path.. 20-4 b toh ho skta haina phr... 24 he q... 16 b banega answer... Aur understand ye b karo ki probability jb 68% di jaati hai tb standard deviations use krte hain
@@outtinglovers8632 68% probability is +Sigma.. aur 99.9 k liye ata hai +3sigma... For 50% probability it's critical path.. aur critical path ki definition pad Lena ki kya hota hai.. usne question mai mention Kia hai it's critical path.
@@GhNabiNaik07Without any book think yourself ? First you will level the tripod and then you centr e it so that the plotted lines will be exact over station.... Then you can transit radiations by orientation but levelling and orientation is done simultaneously 😊
Padai vadai kiye ho ki nahi ? 3-4 percentage... 1/24 ko zra calculate karna kitna aata hai... Books khol kar dekhna 1/24 -1/25 ... Ya 1/30 - 1/33 ... Zyda close range mai konsa hai
Pagal analysis You want question should be straight forward Most appropriate is also an option in this exam And for your kind information for high speed trains Crossing number varies from 1 in 20 to 1 in 24 For passanger trains 1in 12 to 1 in 16 and for goods trains 1 in 8.5 You can see on Satish Chandra book who is currently JKPSC chairman
The answer for CPM question is 24.
Since probability is not given but the standard deviation is non zero so the project completion time is certainly more than 20. Only one option is more than 20.
20+- 4 so max is 24
@@SHUNGA_ shunga G probability 68% par wo formula lagta hai.. aise kaho toh mai 99.9% probability par 3sigma laga deta hu... None of the option correct. Thodi self respect rakho aur selfish Mt bani
No ways. That is when you are eliminating other options, but the question itself is incomplete. So it might be cancelled.
Actually Hona 32 chaiye..
but Hai nhi So We should consider Minimum Time.
becoz Time taken to complete the project should be minimum. So 20 is correct
Sir, dynamic compaction can be light or heavy, so no of layers, height of fall, weight of hammer & no of blows all can vary... Therefore, none of the given answers is right... U may refer IS-2720 PART 16
Sir cutoff analysis plz
Critical path=24 days . Please understand standard deviation is given.
😂😂 kaise nikale ho acha hume b btao formula...
Critical path.. 20-4 b toh ho skta haina phr... 24 he q... 16 b banega answer... Aur understand ye b karo ki probability jb 68% di jaati hai tb standard deviations use krte hain
Bhaii critical.path pee max duration hii leingee naa kamm kyun leingee I mean why to take 16 if 24 is maxm
@@outtinglovers8632 mere bhai probability ka concept pade ho ?
@@outtinglovers8632 68% probability is +Sigma.. aur 99.9 k liye ata hai +3sigma... For 50% probability it's critical path.. aur critical path ki definition pad Lena ki kya hota hai.. usne question mai mention Kia hai it's critical path.
BL gupta ne 1 in 20 dia hai earth road ka sir
Yehi correct hai SK Khanna and Made easy walu ne bhi same diya hai.. Construction wala chapter Me clearly likha hua hai.
Bohat sare kahege wo out of syllabus h but questions toh aur bhi syllabus ke baahr se the Muskingam equation etc just wait for final answer key bro
Question 105 ka answer key prr B hai. Objection raise bnta hai sir.
Sir ab agr aga prepare krna ho toh ksa kra aap bta sakta ha kuch . How much detail study for prepare.
Sir as per MM Aggarwal
Recommended by RDSO. its 1in 20
Can you send the pdf
Sir cutoff prediction ?
Sir isi ka screenshot le ke reference de skte hain.
Objection kasa krni h please koi bta do
Sir apnai jo sugar kai barai mai bola ki retard karai ga...wo galat hai...
87 current score..it might be 89-91 after revised key..any chance in om
In h bhai
Sir plzz cut off bato.. We eagerly waiting for cutoff analysis
Sir.. Irrigation k question mai NIR krne k lye effective rainfall nhi de k hai.. Objection. Ho sakti h??
5% ana chahiye in earthern road ,,cuz we prepare for worst condition
Sir agar 0.837 hai
But most appropriate tou 0.876 he aayai ga na...Kyu Ki options tou 1 sai zyada hai...
D/None of option may be claimed for raising objection
Aur haan sir none of these option b nhii hai ismai...tou most appropriate tou 0.83 tou aayai ga na...
How many students do u know with more than 72 Marks
Please reply
4
Apko kya lgta ha cutoff kitna hoga
9
@@arandomstory4663
77 max
Otherwise 74 to 75 om
Sir cutoff
Sir Plane tabling wala question ma doubt ha
Sequence kya rahega oska?
Centring-Levelling-orientation, yehi na
@@junaidsaleem341 is this sequence correct?
@@GhNabiNaik07Without any book think yourself ? First you will level the tripod and then you centr e it so that the plotted lines will be exact over station.... Then you can transit radiations by orientation but levelling and orientation is done simultaneously 😊
@@malikmusharib4613 agr slope hoga toh phr pehle leveling kr ke centring karenge toh kaam kharab hoga ...think about it
Genuine questions for representation.. Only 6
Degree curve
Cpm pert
Rise fall survey
Soil incomplete question
Sugar retarder
Camber
Gradient for high speed trains is 1/20
@@abdulbasit-lo7ly not used in India bro... Question m india mention kiya tha... Ye question RRB m 2 bar aaya hai and same answer 1/12
@@b.honest ok
Missing one, belong to pert with fulkerson rule
Sir what about the equipment question
PERT is event oriented
Why 1/24.....camber is between 3 to 4%...which shows 1/30 is correct
Padai vadai kiye ho ki nahi ? 3-4 percentage... 1/24 ko zra calculate karna kitna aata hai... Books khol kar dekhna 1/24 -1/25 ... Ya 1/30 - 1/33 ... Zyda close range mai konsa hai
@@yasirsh008 u can't go below 3 or above 4....these are limits, value should be between these two
Absolutely bro...1/30 is the correct answer. It lies between 1/25 to 1/33.
@@user..12352 yes bro, i already did. And ours is more safe, because it lies within the limits.
@@user..12352 yes bro, maine daali. Aap bhi daalo!
Cutoff analysis Video Sir Please 🙏🙏🙏
Already uploaded
Cutoff pai vedio batao sir
Agr fair howa Tu 78-80...agr fair ni tu 87+
@@b.honest Bhai ye tum un 6 question k revision k baad keh rhe ho na ? Qki mere wo 6 k 6 sahi honge Jo tumne comment mai likha hai
@@yasirsh008 yes with all... Aur dekhna yehi 6 chg hoge aur koi ni
Pagal analysis
You want question should be straight forward
Most appropriate is also an option in this exam
And for your kind information for high speed trains Crossing number varies from 1 in 20 to 1 in 24
For passanger trains 1in 12 to 1 in 16 and for goods trains 1 in 8.5
You can see on Satish Chandra book who is currently JKPSC chairman
1/12 is correct answer
Kar Aaraam
Last main Pata chale ga
Right ho ap bhai..
Passenger train 1 in 12
goods train 1 in 8.5
exceptionally high 1in 16 to 1in 20 jo India me use nhi hota
Vicat appartus needle glt boul rhe ho ap..... Kya knowledge hai ap ke😂😂😂😂