Project Management - Critical Path - Example 3
HTML-код
- Опубликовано: 12 сен 2024
- In this video, you will learn how to draw a network diagram, how to find out the earliest and latest start and finish times of the activities, how to find out the earliest and latest occurrence times of the events along with the slack of the events. Also, you will learn 3 different methods of finding out the critical path for a project.
Great post, learned from the video.
Thank you sir
Thanks, you made it simple and straight forward.
Very good lecture. cleared my doubts. thanks a lot.
Hi, this was a really helpful lecture! I have a question though, what if during you backward pass at for example A, you realise it gives you a negative number for late start, what can be done? This is not for this example in the video.
Thank you
Well explained sir..
I had clr all may doubts.
Thnku sir😀
Good lecture!
Good job and well explained (Y) Thank you
Thank you!
Super teaching sir
thanks for this lecture..i learnt a lot. keep posting.
hi their! it's useful tips to solve the network problem, please lecture in tamil
What if I had and activity a that is start, activty b dependent on a and c and activity c is start and activity d dependent on c
thanks sir but you didnt explain FREE FLOAT how to calculate that?
thanks!! ^^
thanks,,
thanks
there is some Mistakes in drawing Project Network
gyz, this is so educative bt uyou cant start drawing a network diagram with a circle
sir you save me...
You lost me at 13:50 why is E and H, [ , 44] and F [, 35]?
EDIT: Nevermind I get it now, thanks!
E and H Should be 35
Wrong example without any condition you can not meet any activity .....
H
Good examples, what about the one you've been given the optimistic time, pessimistic time how will you solve that one