WHY HAS MY CRITICAL PATH DISAPPEARED? AND, HOW TO FIX IT. MS PROJECT MADE EASY TUTORIAL NO. 43

Поделиться
HTML-код
  • Опубликовано: 21 янв 2025

Комментарии • 32

  • @speedman223344
    @speedman223344 7 месяцев назад

    You made my day. A separate task calender made my critical path disappear prior to the task.

    • @TomStephensontraining
      @TomStephensontraining  7 месяцев назад

      Great, yes it’s frustrating if you don’t know why it does these things. Happy that I was able to help you!

  • @augustoremollino7527
    @augustoremollino7527 11 месяцев назад

    Hi Mr. Tom, thank you so much for sharing your knowledge and expertise in MS Project and CPM. I learned a lot and now my understanding of this is getting deeper and deeper. God Bless sir

  • @DarrellBailey-g4k
    @DarrellBailey-g4k 4 месяца назад

    Thanks so much - part of my critical path would not display and it was driving me mad; it was due to the special calendar that I'd created for that part of the project period. I'd beene battling with this for a good few hours before I watched your tutorial - much appreciated.

    • @TomStephensontraining
      @TomStephensontraining  4 месяца назад

      Yes I’ve been there, it took a while to figure out the reasons. Every day I’m still learning new nuances. I thing with this program and others you roll with some by figuring out work arounds and learning what not to do even though the program seems to encourage it.

  • @richbatton9683
    @richbatton9683 Год назад

    Excellent video! Great troubleshooting tips. This still didn't fix my problem, but I learned a few things. I found out that one more way your critical path can disappear is if it goes through a task that's "inactivated". I have RISK line items that I inactivate or activate depending on whether they need to be deployed and this unfortunately eliminates the critical path. Shoot.

    • @TomStephensontraining
      @TomStephensontraining  Год назад

      Did you try linking the predecessor to the the successor of the inactive activity Rich. Just curious now. Thanks for the kind words

    • @richbatton9683
      @richbatton9683 Год назад

      @@TomStephensontraining​​⁠yes sir. My boss won’t accept a project schedule with any predecessors or successors un-linked. All were linked and auto scheduled to soonest possible. Using what I learned in your video I traced back to the point the critical path dropped off and it was an inactive “risk” line item.

  • @raycarlone2005
    @raycarlone2005 3 месяца назад

    great video.
    Do you have a video that resolves the "special calendars" critical path issue? I made a special calendar half way through the project when it switch to 6-day work week to accelerate the schedule. Now i have critical path issues not related to constraint dates.

  • @EraVeronica
    @EraVeronica Год назад

    Hi Tom ..
    On Ms Project 2016, Baseline Cost and Total Contract same Price .. but why on Cost not same, has different Price. Thank you

    • @TomStephensontraining
      @TomStephensontraining  Год назад

      Im not sure where you are looking but if you have a baseline and anything changes it will affect any variable costs by either adding or lowering the total cost. You should then see the variance on the cost sheet

  • @bryonpotter558
    @bryonpotter558 6 месяцев назад

    I just started a trial period on MS Project and mine doesn't like this at all. The top tool bar is missing completely. It looks very simplified down to just task lists in the grid, board, timeline and chart views. There is no plethora of tools and no excel chart to inform the timeline and critical path the way you're showing here. Do you know the reason?? Did they completely change the design of MS Project recently?

  • @antonyjuwono2079
    @antonyjuwono2079 Год назад

    Prof, how to calculate manpower which need in a project and implement it to ms project

    • @TomStephensontraining
      @TomStephensontraining  Год назад

      Hi Antony, estimating durations is a big topic that requires education, experience, collaboration. There is data that can be purchased through RS Means and others, but really I would such taking some project management, site management and estimating courses and combining that with real world experience coupled with ongoing accurate historical data which MS Project will provide you with when used properly. Also, things always take more time then you expect so have a management reserve and a contingency reserve. Checkout my Site Management playlist for assistance. Hope that helps.

  • @esmashkurti6626
    @esmashkurti6626 9 месяцев назад

    Hii,I created a gant chart and network diagram and I don’t know why every single action is red ,can you please help me?

    • @TomStephensontraining
      @TomStephensontraining  9 месяцев назад

      Likely you have done everything finish to start so everything is on the critical path. If something’s are concurrent and have different durations then some will be blue, non critical.

  • @KT-io3jh
    @KT-io3jh Год назад

    Hi Tom, I am working on a project on P6, and there is quite a lot of float in it. Client wants to see critical path, I am not sure how to generate critical path if the float is above 0, can you point me in the right direction please? Thanks

    • @TomStephensontraining
      @TomStephensontraining  6 месяцев назад

      There is always a critical path. Other thing may have float but the longest path to complete is the critical path. P6 msproject does not mater just make sure everything is connected and the logic Is how you would like to build it

    • @KT-io3jh
      @KT-io3jh 6 месяцев назад

      @@TomStephensontraining Ty for your reply. Yeah I figured it out a long time ago, still appreciate your reply. I have been working quite a lot in P6 and I love it.

  • @danielhrp1
    @danielhrp1 11 месяцев назад

    thanks for the clear explanation. one question, for the tasks with 100% progress, can it be still shown as critical task while previously it was (as planned).

    • @TomStephensontraining
      @TomStephensontraining  11 месяцев назад

      Hi Daniel if It is done it won’t show critical. If it is partially done even 99 percent it will still show critical. Once done it cant move therefore not critical

    • @TomStephensontraining
      @TomStephensontraining  11 месяцев назад

      Thanks for watching

    • @danielhrp1
      @danielhrp1 11 месяцев назад

      @@TomStephensontraining thanks for the explanation!

    • @raycarlone2005
      @raycarlone2005 6 месяцев назад

      @@TomStephensontraining hi tom, i have an issue where as soon as i put any percentage on a critical task, the predecessor shows no longer critical. The link is a FS -2days so the successor starts before the predecessor ends. I know i have something setup wrong but i cannot figure it out. I have no constraints assigned to the tasks. Any advise would be greatly appreciated please.

  • @jacobraphalane2837
    @jacobraphalane2837 Год назад

    Thank you very much again Prof.

    • @TomStephensontraining
      @TomStephensontraining  Год назад

      You’re welcome Jacob, thanks for watching the videos and leaving comments. Very appreciated

  • @najamkhan3781
    @najamkhan3781 Год назад

    Thank you sir

  • @RAJIVINSANEUROPE
    @RAJIVINSANEUROPE 6 месяцев назад

    nice