I've been following the videos you've posted over the years. I have learned a lot from your video and put it into practice when using Ms Project. Please publish more videos for me and everyone to learn together. Wish you and your family all the best. I am in Vietnam and would like to say hello to everyone. Cordially greet!
Thank you for the video, very informative. Are we able to apply multiple filters? Ex. Show 6WLA tasks including unfinished tasks before the date range?
Did you find it? If not slide your mouse all the way to the left of your screen right click mouse button and you will see a list of screens, choose resource usage.
Hello, thanks for your reply, i found it, but there is some issue in the project because there were issue shared ressources from differents project, so even changing the date the number of ressources doesn’t change. I have created one excel file, how i can share it with everyone
professor, you always inspire me to drag more in schedule management!!! thank you!
Thanks Gordon, I enjoy making these videos for learners like you
I've been following the videos you've posted over the years. I have learned a lot from your video and put it into practice when using Ms Project. Please publish more videos for me and everyone to learn together. Wish you and your family all the best. I am in Vietnam and would like to say hello to everyone. Cordially greet!
Thanks so much Sinh, hello right back. Have a great day and keep on learning
Thanks for video❤❤❤❤
Thanks so much Mahesh!
Thank you for the video, very informative. Are we able to apply multiple filters? Ex. Show 6WLA tasks including unfinished tasks before the date range?
Unfortunately not easily yet, thanks for watching
@TomStephensontraining thank you for confirming 👍
this is great, i came all the way from P6, i can't find the ressource usage speadsheet
Did you find it? If not slide your mouse all the way to the left of your screen right click mouse button and you will see a list of screens, choose resource usage.
Hello, thanks for your reply, i found it, but there is some issue in the project because there were issue shared ressources from differents project, so even changing the date the number of ressources doesn’t change.
I have created one excel file, how i can share it with everyone
Can you Filter resources allocated only? So you can see all the contractors tasks in isolation?
Yes go to view, filter, pick your resource