Good and nice explanation. Pls put video for cost loading. Where BOQ is available with Qty and Rates are also available. Rates are on per sqm, sft, cum, cft basis. Example concert rate per cum, plastering rate sqm basis.... ( post item rate contract for Civil works )...
Dear Tom, Thanks a lot for your videos they are very helpful to us. I would like to politely request you if possible to please generate an electrical project schedule for the Construction of MV and LV lines (electrification) starting from making a schedule, then assigning/linking resources, and identifying how much it will cost you? vs the planned budget.
Good morning Tom, I have a question regarding Work roll up, and ultimately cost. In my resource pool I have all my resources including (People, Equipment, WorkCenters, and Vendor) This is a need for me. My issue is this. Lets say Task 1 requires 1 person, 1 machine, and the workcenter the machine is located in. The task is set as a Fixed Work and 8 hours. The total "Work" for that task/operation is 24hours, which technically... is correct for MS project. But I only want to capture the "Work" for the person. Would a custom field be the best option for this or would there be some way to define that in the resource sheet or "work" field. Thank you.
Thanks Tom. How do we apply general, direct or indirect costs? rents, utility bills, insurances, bonds etc? Should we define separate tasks for them? Many thanks for your time.
You could apply them as tasks or perhaps if they are recurring fees create a monthly recurring task called admin fees and under the cost table apply them as a fixed cost on the individual months, keep fixed tasks prorated and the cash flow should be evenly distributed.
Yes check out work usage screen by sliding to the left of the screen, left click your mouse and select resource usage. Its more complicated but if you wanted to see the screen
Thank you for the video Tom. I see how you have type "Cost" for subcontractors. If I want to create a cashflow report, is it possible to apply a resource name to a schedule task so its not just applying the total at the end or the start? Given the project type a given task could last more than a month and subs typically have progress monthly billing. i.e. if drywall last 2 months for one level at $100,000 but they bill 50k for each month I'd like to show that progression in the cashflow report.
Thank you for the tutorial, it is very helpful I have a question What would be the case if the supplier/subcontractor get their payments in payments plan?, meaning: Downpayment, Progress payment and final payment. how could I load the cost
Hi Samar, Add the costs directly to the activities that you intend to pay them. Eg assign resource to start milestone and add resource with cost added. You can also add
Nice Tutorial. I wish Mr Tom would consider to naming his Tutorials on each subject like, say.. Tutorial 4 of 10 or 1 of 6...etc so that it is easier to follow one after the other. Otherwise many thanks for sharing your knowledge.
Yes I run out of allowable characters in the naming. Check my playlists i think they should be in order but i will check as well. Thanks for the advice
Your mouse icon is hard to follow sometimes, should try and highlight so I people are working on project professional following along they can track icon faster
I can’t thank you enough for making these amazing videos
Thanks Sebastian, I’m glad they help you!
Thank you Tom. I really like your videos.
Great I’m happy they help you
Very informative, thank you Tom.
Thanks Isaac glad it helped
Thank you for your videos, they are really helpful 🙂
Appreciate the Video Tom, really informative for beginners like me trying to get our hands on this powerful tool
Thanks Shiva, I’m glad they help.
Good and nice explanation. Pls put video for cost loading. Where BOQ is available with Qty and Rates are also available. Rates are on per sqm, sft, cum, cft basis. Example concert rate per cum, plastering rate sqm basis.... ( post item rate contract for Civil works )...
Dear Tom, Thanks a lot for your videos they are very helpful to us.
I would like to politely request you if possible to please generate an electrical project schedule for the Construction of MV and LV lines (electrification) starting from making a schedule, then assigning/linking resources, and identifying how much it will cost you? vs the planned budget.
Wish I could help but not my specific expertise
Hey tom great video's as i'm a site super, headed into project management! Keep up the good work, these are helpful!
Thanks Tyronne glad they help.
Woooow this is great 👍
Thanks Asamany for the kind words!
Good morning Tom, I have a question regarding Work roll up, and ultimately cost. In my resource pool I have all my resources including (People, Equipment, WorkCenters, and Vendor) This is a need for me. My issue is this. Lets say Task 1 requires 1 person, 1 machine, and the workcenter the machine is located in. The task is set as a Fixed Work and 8 hours. The total "Work" for that task/operation is 24hours, which technically... is correct for MS project. But I only want to capture the "Work" for the person. Would a custom field be the best option for this or would there be some way to define that in the resource sheet or "work" field.
Thank you.
Hi Chris, have you tried adjusting the hours in work usage table?
Also, can we load cost for item Rate contracts in MS project / in Primavera or it is difficult to do. Pls reply...
well done
Thanks so much
Thanks Tom. How do we apply general, direct or indirect costs? rents, utility bills, insurances, bonds etc? Should we define separate tasks for them? Many thanks for your time.
You could apply them as tasks or perhaps if they are recurring fees create a monthly recurring task called admin fees and under the cost table apply them as a fixed cost on the individual months, keep fixed tasks prorated and the cash flow should be evenly distributed.
@@TomStephensontraining many thanks!
Great video Tom as always. Is it possible to calculate manpower utilization in Ms Project?
Yes check out work usage screen by sliding to the left of the screen, left click your mouse and select resource usage. Its more complicated but if you wanted to see the screen
Alright. What I meant is does MS Project automatically calculate the % utlization of labourers, for instance?
Great! Thank you so Much!
You are welcome Jaime, I’m happy that it helped you.
Thank you for the video Tom. I see how you have type "Cost" for subcontractors. If I want to create a cashflow report, is it possible to apply a resource name to a schedule task so its not just applying the total at the end or the start? Given the project type a given task could last more than a month and subs typically have progress monthly billing. i.e. if drywall last 2 months for one level at $100,000 but they bill 50k for each month I'd like to show that progression in the cashflow report.
Hi Tony, in that case you could have it prorated instead which would indicate 20 days into a 50 day task 40% cash for that task
Thank you for the tutorial, it is very helpful
I have a question
What would be the case if the supplier/subcontractor get their payments in payments plan?, meaning: Downpayment, Progress payment and final payment. how could I load the cost
Hi Samar,
Add the costs directly to the activities that you intend to pay them. Eg assign resource to start milestone and add resource with cost added. You can also add
Thank you!
Thanks Vasu
Nice Tutorial. I wish Mr Tom would consider to naming his Tutorials on each subject like, say.. Tutorial 4 of 10 or 1 of 6...etc so that it is easier to follow one after the other. Otherwise many thanks for sharing your knowledge.
Yes I run out of allowable characters in the naming. Check my playlists i think they should be in order but i will check as well. Thanks for the advice
Your mouse icon is hard to follow sometimes, should try and highlight so I people are working on project professional following along they can track icon faster
Thanks Adam check my most recent video is. That better?