Metro Manila Skyway Stage 3 update as of August 2017

Поделиться
HTML-код
  • Опубликовано: 2 окт 2024
  • Hello! This is our 42nd update for the Metro Manila Skyway stage 3 series. In comparison to the previous video, there were not mucn noticeable additions. There was an accident that offucred over pier 23 in section 1 where the rebars collapsed.
    Intermittent GPS connection grrrr!!!!
    0:07 - Toll Plaza on existing skyway
    Section 1
    1:37 - re-installation of rebars on pier 23
    2:01 - to your right an entry ramp
    Section 2
    Heard over some grapevine that the alignment for section 2 was redesigned. The alignment will now pass San Juan River and will be longer than the originally planned. (grapevine source)
    5:40 - the columns where cylindrical in shape
    Section 3
    More girders installed along Araneta avenue
    Section 4
    12:46 - a narrow entry ramp at the center (i guess it is an entry ramp)- might be a problem for volume of vehicles someday...
    13:23 - another entry ramp at the center?
    I added a part of section 2 at the end of the video..

Комментарии • 74

  • @mikesjourneycontinues7979
    @mikesjourneycontinues7979 7 лет назад +1

    With the passion in you about roads, wish you could work in DPWH. I do believe you are a good guy and incorruptible.

  • @raultanglao8601
    @raultanglao8601 7 лет назад +3

    Due to the right of way issue especially on the section 2 quirino section nothing done so far.Four more years before it was finally completed .Do u see the perspective two layers must be completed but so far only one layer yet be complete.

    • @silentbutdeadly1925
      @silentbutdeadly1925 7 лет назад +1

      Actually they are just waiting for the final design and costing of the North Rail and South Rail projects. Skyway Stage 3 wont be completed on January 2019.

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      Yeah January 2019 is a far fetch date for completion. How about section 1 sir . partial opening? any target date so far?

  • @alfredpacot6647
    @alfredpacot6647 7 лет назад +2

    WOW! daming nagbibigay ng info d2 sa project, keep it up guyz... and thanks sir dmitrivalencia .. :)

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      thank you din for watching sa mga nagbibigay ng right info :-)

  • @alexternative
    @alexternative 7 лет назад +2

    Thank you for keeping us updated with this project!

  • @newmsioworld3525
    @newmsioworld3525 7 лет назад +3

    NLEX-SLEX Connector for SMC is under construction and the completion date is Jan. 2019!

    • @reylanomalza2223
      @reylanomalza2223 7 лет назад +2

      New Msio World 1 mpic po ang slex-nlex connector

    • @silentbutdeadly1925
      @silentbutdeadly1925 7 лет назад +6

      Please be informed that NLEX-SLEX Connector is different from Skyway Stage 3. They havent start the construction yet due to right of way issue. Also, the final design and costing of north rail and south rail projects adds up to the delay of NLEX-SLEX Connector to START...

  • @leesong4487
    @leesong4487 7 лет назад +1

    Hi dmitri. Can you please enlighten me on the araneta aurora blvd part of the skyway stage 3? I really have no idea where the flyover is headed to. Will it cross
    Aurora and go towards San Juan? Thanks in advance. Cheers!

  • @rcangelbautista4880
    @rcangelbautista4880 7 лет назад +1

    Nice background music Sir @dmitrivalencia. Chilling while watching the progress! :)

  • @tuxedo32mania
    @tuxedo32mania 7 лет назад

    kailan ia upload yung video ng skyway stage 3 for september 2017? inaabangan ko kasi yun eh.

  • @christophers.o622
    @christophers.o622 7 лет назад +1

    Great video, great update, enjoy ang Skyway 3 updates very much, salamat

  • @CraigRodmellMusic
    @CraigRodmellMusic 7 лет назад +4

    Thanks for posting. Interesting to see where the crossbeams had collapsed. I see they STILL haven't got the power pylon out of the way on Araneta.

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      the one after the Buendia Flyover or near the end of the flyover... Pier 28 if i remember it right..

    • @1959olet
      @1959olet 7 лет назад +1

      no not pier 28 but pier 23 after the buendia ramp and it is now nearing completion of coping beam as you see in the video

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      thanks for the correction

  • @kevinwestbrook9270
    @kevinwestbrook9270 7 лет назад +1

    sir any idea kung maapektuhan yung mga residential area with land title along sta.mesa area....slmt po

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      there is a re alignment daw so i guess the motels are safe (Old sta mesa area) hehehe.. as for the residential properties.. i am not privy to that sorry.

  • @jaydj
    @jaydj 7 лет назад

    so around 20 minutes from SLEX to NLEX assuming not much traffic and go sa stoplights bale?

  • @petergo4782
    @petergo4782 7 лет назад

    I wish someone from DPWH is watching this video and take some road repair along Araneta Ave and A. Bonifacio, potholes everywhere.

  • @tuxedo32mania
    @tuxedo32mania 7 лет назад +3

    pwede ka rin ba gumawa ng video about dun sa NLEX Harbor Link?

    • @1966bluemax
      @1966bluemax 7 лет назад +1

      Rion Cervantes I second that

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +2

      I think it is not accessible via vehicle, have to do some ninja moves to get some shots. MPIC has been diligently updating their progress :-)

    • @1966bluemax
      @1966bluemax 7 лет назад +1

      dmitrivalencia the harbor link should have been done last year pa. The right of way delay is so frustrating

  • @babesocampo717
    @babesocampo717 7 лет назад

    PINOY JOYRIDE GOOD NEWS 2018 PA BUKASAN 8 RAMPS NG SKYWAY STAGE 3 FROM GMA NEWS

  • @joseyorro9014
    @joseyorro9014 7 лет назад

    Medyo mabagal ang gawa sa Quirino Ave. Pag yan ang natapos malaking ginhawa. Sana po bumilis.

  • @clementecolayco7513
    @clementecolayco7513 7 лет назад

    Ngayon at tayo na ang mga poste, Bakit hindi isabay sabay ang pag latag ng mga beam at floor ng skyway para mapabilis? Parang wala ng nag isip pa bilisin ito, para bagang hindi pinag mama Dali ito...

  • @roysescon9931
    @roysescon9931 7 лет назад

    Sana po maisama nyo ung sa nlex slex segment 10..ang tagal na nun ehh..baka ho progress na.

  • @mhackysaldo
    @mhackysaldo 7 лет назад +1

    Wow! Hoping it will done by 2018!

    • @newmsioworld3525
      @newmsioworld3525 7 лет назад +1

      Due to the delays of the project will be completed on January 2019

    • @jimjamssi
      @jimjamssi 7 лет назад +1

      Hah hah. You mean 2029?

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      lets just pray for a miracle for section 1 - it is hard to assume deadlines as of the current situation and if we imposed deadlines, structural integrity might be an issue.. we wont like a ala-cypress road freeway in San Fo to happen in the Philippines wag naman po sana...

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      wala na ako rito kapag 2029 hehehehe tigok na sa kakahintay :-)

  • @tfhermoso
    @tfhermoso 7 лет назад +1

    Dim, may I suggest you have still photos of the highlights or notes? Example the section 4 entry ramp on 12:46 and 13.23. The part of section 2 too. Its good to have an overview of the realignment of section 2 - revised vs. planned.

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      will PM you a grapevine picture sir :-) not official but it seems dun dadaan

  • @rangera3806
    @rangera3806 7 лет назад

    sure ba yung sa nakita kong description na yung sec 2 sa san juan river at hindi na sa sta mesa

  • @babesocampo717
    @babesocampo717 7 лет назад

    PINOY JOYRIDE MAY NAKITA PO AKONG PABABAGO SECTION 3 AT SECTION 4 SA G ARANETA PO

  • @babesocampo717
    @babesocampo717 7 лет назад

    PINOY JOYRIDE MAY PAGBABAGO PO SAMAY A BONIFACIO SGT RIVERA AT G ARANETA

  • @tuxedo32mania
    @tuxedo32mania 7 лет назад +1

    ano nga pala balita sa slex tr4? tuloy pa ba yun?

    • @gabrieldominic2381
      @gabrieldominic2381 7 лет назад

      Rion Cervantes as per DPWH website, last June pa po ang construction ng TR4 and is expected to be completed around 2020. ;)

  • @dinotrillo-ho952
    @dinotrillo-ho952 7 лет назад

    meron ba kayo update for the month of september?.

  • @johncalvinmelendez9612
    @johncalvinmelendez9612 7 лет назад

    Mrt 7 update naman pi sunod niyong videohan

  • @Funnysong877
    @Funnysong877 7 лет назад

    Pogi b c dmitriv...pkita mo nman itsua mo....

  • @feuillutrixie817
    @feuillutrixie817 7 лет назад

    Buti nawala na yung nasirang portion sa Buendia

  • @chriscortez1367
    @chriscortez1367 7 лет назад

    ilang lane po bawat wings

  • @litots5215
    @litots5215 7 лет назад

    Boss, matapos kaya ito before mag SEA games? Sana kayanin...

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      ndi ko sure, sana wala na aberya ma encounter. Pero nag bigay na ng estimate time ang DPWH diba sa section 1?

  • @1966bluemax
    @1966bluemax 7 лет назад +1

    Almost no delay from the accident?

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      well... errr.... uhm... hehehe yun lang sir :-)

    • @1966bluemax
      @1966bluemax 7 лет назад +1

      dmitrivalencia parang may progress pa rin

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      :-) i am just being impatient with the skyway :-) Slow cook braised beef is delicious.. thinking of skyway as a slow cooked braised beef hehehehehe

    • @ontheground4592
      @ontheground4592 7 лет назад

      dmitrivalencia XD like binabad

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад

      neosar5435 ay iba naman yan hehehe. There is something wrong with the case kapag tumagal.

  • @feuillutrixie817
    @feuillutrixie817 7 лет назад

    And temporarily suspended ang works nila dahil sa incident

  • @babesocampo717
    @babesocampo717 7 лет назад

    PINOY JOYRIDE GOOD NEWS SKYWAY STAGE 3 JAN 2018 BUKASAN ANG SKYWAY STAGE 3

  • @virgiliolaomuy4081
    @virgiliolaomuy4081 7 лет назад

    18 yrs no vacation , I miss the Philippines !

    • @bronzeinabangan
      @bronzeinabangan 7 лет назад

      virgilio Lao Muy tang ina. Umuwi ka na. Laki na ng pinagbago.

    • @virgiliolaomuy4081
      @virgiliolaomuy4081 7 лет назад

      +Bronze Hachi Ano pinagbago ? maraming building ? sino nakatira ? mga pilipino ? nagkalat ang mga OFW sa mundo kc wala pa rin kuwenta buhay dyan , mga POLITICIANS mga kurakot ,..yung OVERSEAS EMPLOYMENT yang POEA ginawa ng hanapbuhay ng mga POLITICIANS sa pilipinas malaki kc KICKBACK nila pati mga military officials may recruitment agencies na rin ,...masarap dyan kung may magandang hanapbuhay ka !...BOG !

    • @bronzeinabangan
      @bronzeinabangan 7 лет назад

      tama ka nga pre. maganda dito pag may pera ka at may business. okay lang mag bakasyon ditosandali pero kung titira ka dito at wala kang pera. dyan ka na lang kung nasaan ka man. haha

    • @virgiliolaomuy4081
      @virgiliolaomuy4081 7 лет назад

      +Bronze Hachi Kahit dito nga ang hirap ng maghanap ng trabaho nagkalat yung mga OFW pati mga local CITIZEN d tinatanggap kc hinahawakan ng mga MAFIA ng pilipinas yung mga company para OCW kukunin nila kc may porsiento sila mga kurakot yang mga government officials sa pillipinas , yang POEA hawak yan ng mga sindikato !

  • @babesocampo717
    @babesocampo717 7 лет назад

    PINOY JOYRIDE SALAMAT PO SA SKYWAY STAGE3 UPDATE PINOY JOYRIDE SKYWAY STAGE 3 UPDATE SEPTEMBER 2017 UPDATE LRT2 MRT7 LRT1 CALAX SEPTEMBER UPDATE 2017

  • @1966bluemax
    @1966bluemax 7 лет назад

    No skyway vid?

    • @dmitrivalencia
      @dmitrivalencia  7 лет назад +1

      1966bluemax do you guys want na or we wait for the good stuff this month hehehehe 😁

    • @ontheground4592
      @ontheground4592 7 лет назад

      dmitrivalencia we want

    • @ontheground4592
      @ontheground4592 7 лет назад

      dmitrivalencia now that there's more girders installed I hope buendia area will be finished by Dec. 2017 but the target is 2nd quarter of 2018

    • @1966bluemax
      @1966bluemax 7 лет назад

      dmitrivalencia want