  • Samsung E & C America, Inc. (“SECAI”) is the lead general contractor for the Taylor Texas plant.
    The original Samsung Austin Semiconductor factory has been in operation for 27 years. Taylor will make chips using Samsung’s new 4 nm designs.
    ***Additional investments recently announced April 15th, 2024.
    More than a factory, Samsung is building a cluster of capabilities.
    The Taylor site is a $17 billion investment, part of more than $47 billion the company has invested in the U.S. since arriving here in 1978. Over the planned project duration, the company could potentially build multiple labs here as a secondary cluster to their Austin site. Construction was going on in parallel on an array of supporting buildings for chemical and gas supplies, a utility building, an office building, the manufacturing facility, and a parking garage. In addition, there is also a massive “back house” infrastructure going in, including bulk gas facilities, a water reclamation facility, and an electrical substation.
    Samsung's cluster in Taylor, just northeast of Austin, would include two factories that would make four, and newly announced, two nanometer chips. Also, there would be a factory dedicated to research and development, as well as a facility for the packaging that surrounds chip components.
    The first factory is expected to be operational in 2026, with the second being operational in 2027.
    ***The 1200-acre Taylor site is almost twice as large as Samsung’s flagship Pyeongtaek Campus in South Korea. And the vision for this site is to be vertically integrated and self-reliant as much as possible, much as they are in Korea.
    buymeacoffee.com/airwavedynamics

Комментарии • 23

  • @michaeljohnson1805
    @michaeljohnson1805 2 месяца назад +8

    This is such a huge factory to make such small chips

  • @frankcoffey
    @frankcoffey 2 месяца назад +2

    The US really needs chip fab capability and this is a nice start.

  • @damiengariepy4267
    @damiengariepy4267 2 месяца назад +1

    Help build this the first phase of this site, cool to see it coming along !

  • @richmargin6082
    @richmargin6082 2 месяца назад +3

    Thank you for covering this factory

    • @AirwaveDynamics
      @AirwaveDynamics  2 месяца назад +1

      You're most welcome. It sure is massive!

  • @Robert8455
    @Robert8455 2 месяца назад +3

    Sure takes up a lot of space to make 4nm chips. Also looks like it will use up a lot of electricity too. Great drone footage.

    • @AirwaveDynamics
      @AirwaveDynamics  2 месяца назад +2

      Thanks!
      It appears they're building a lot of their own utility infrastructure too. Almost like a micro city of some sort. Which is a good idea considering Taylor is a very small town.

  • @Mrbfgray
    @Mrbfgray 2 месяца назад +5

    We badly NEED these in the USA.

    • @michaeljohnson1805
      @michaeljohnson1805 2 месяца назад +1

      This is in the USA…Texas

    • @Mrbfgray
      @Mrbfgray 2 месяца назад

      @@michaeljohnson1805 Really? Thought it was Austin, Cuba.

    • @michaeljohnson1805
      @michaeljohnson1805 2 месяца назад +1

      @@Mrbfgray then you should say we badly need more of these in the USA

    • @Mrbfgray
      @Mrbfgray 2 месяца назад

      @@michaeljohnson1805 That's what I said. Pay attention and avoid assumptions.

    • @michaeljohnson1805
      @michaeljohnson1805 2 месяца назад +1

      @@Mrbfgray that’s not what you said and you should learn better grammar

  • @anneamateasderossi893
    @anneamateasderossi893 2 месяца назад +1

    уровень автомобилизации впечатляет
    мы приветствуем ^_^

  • @theatx379
    @theatx379 Месяц назад +1

    Samsung's Giga Texas

  • @pauleklink
    @pauleklink 2 месяца назад +1

    What is the estimated completion date?

    • @AirwaveDynamics
      @AirwaveDynamics  2 месяца назад +2

      It's supposed to be partially operational by this summer I think. Full operations for this facility along with plans to expand it even more...could be another 2-3 years? I'll have to find a recent article.

  • @TuanNguyen-uq8gz
    @TuanNguyen-uq8gz 2 месяца назад +1

    do you have a rendering for this project?

    • @AirwaveDynamics
      @AirwaveDynamics  2 месяца назад +1

      An official one via Samsung? Wish I did 🙂

  • @lourdessilva6442
    @lourdessilva6442 2 месяца назад +1

    Grata