  • @lb1923
    @lb1923 4 года назад +1

    Thanks, great explanation. Gives more clarification
    Question: how about for example, a paint job for 5 days of work. Then, a painter has rate of 1d. I need to deploy 5 painters to just finish the job for 1d. How to show it on ms project, having 5 painter working on certain activity?

    • @vision6D
      @vision6D  4 года назад +1

      Thank you for your comment and your question. You can create a resource called painters. This resource will have in the unit max a value of 500%, which shows a capacity of 5 painters. Have a great day.

    • @lb1923
      @lb1923 4 года назад +1

      @@vision6D Thanks master, have a productive week ahead

  • @carlosfigueira345
    @carlosfigueira345 6 месяцев назад

    Hi, I'm not sure I got it. where do the 25% come from did you set these in the resource assignment? I would expect to just enter the duration and after that enter the amount of hours and the units would appear automatically. I also find it complicated when at some point I decide to add another engineer to a task I should not need to create another make-up resource that is made of two people.