Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing? By CivilGuruji
HTML-код
- Опубликовано: 26 июл 2021
- #RCC #Footing #Calculation #BBS Steel
Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing?
Start Your TRAINING NOW
Enroll and get started :- www.civilguruji.com/s/store/c...
Download Detailed PDF : tinyurl.com/PracticalModule
For More Details Call Now : 9111001234
ABOUT THIS VIDEO :-
In this video Er. Akash Bohare, Corporate Trainer of Civil Guruji (Civil Engineers Training Institute) explaining about Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing?
Bar bending schedule (BBS) of an concrete footing provides the reinforcement details and the total steel quantity required for the footing construction. The BBS and quantity of steel reinforcement required for a simply isolated footing are calculated and explained by means of a workout example.
Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing?
The cross-sectional plan and section of an isolated footing. The details of reinforcement used in the footing are calculated from the detailed drawing of the structure prepared by the designer. The structural drawing provides the reinforcement location and their specifications.
Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing?
From the figure, the following parameters are determined:
Number of Main Reinforcement Bars ( X-Bars)
Number of Distribution Reinforcement Bars ( Y-Bars)
Cutting Length of Main Reinforcement Bars (Cm)
Cutting Length of Distribution Reinforcement Bars (Cd)
Steel Quantity Required
Bar Bending Schedule of Footing - How to Calculate Quantity of Steel in RCC Footing?
From the given details, the following values are calculated: 1. Calculation of Number of Main Reinforcement (X- Bars) From the figure-1(c), the x-bars are distributed along the y-direction. Hence the number of bars
the best platform to learn civil engineering skills ..lots of love and respect from pakistan kpk..
भाई तू सचमुच गरीबों का गुरू है !
1 हिन्दी में समझाता है, 2 वीडियो यूट्यूब पर उपलब्ध कराता है, 3 इतना धीरज से और आसान तरीके से हरेक बारीकी समझाता है, 4 एक दसवीं बारहवीं पास हैल्पर मजदूर को भी इन्जीनियर जितना योग्य बना देता है, 5 पैसे नहीं होने से पढाई छोड़ चुका मुझ जैसा बालक तेरे इन वीडियो को देख समझकर आज बुढापे में इन्जीनियर की पढाई कर पा रहा है ।
सादर पाँव धोक ! पैरी पौना ! चरण-स्पर्श गुरू जी ! 🙏🙏🙏
Thanku so mch sir..itna easily apne ache se smjha dia ...you are best teacher in civil engineering sir....thanku so mch sir..🙏🙂🙂
Aap इंजीनियर हो क्या
Hello sir
@@user-wp9nw4xk1q qq QQ qqqqqq QQ qqqqqqqqqqqqqqqqqqqqqqqqq hu ki q QQ q ki qq QQ q QQ QQ q qq hu q
Total steel use in footing=428kg
Hi
Sir itne teachers ka video dkha h maine lkn aap ka samjhane ka tareeqa bht bht bht zabardast h sir.
MIND BLOWING SIR.....YOUR TEACHING IS SUPERBLY BRILLIANT AND BRILLIANT AND BRILLIANT......BLESSINGS FROM INDIA GUJARAT.......🙏🙏🙏🙏🙏
Cutting length along A direction=1.55 meter
Cutting length along B direction=1.53 meter
Total Steel quantity=224kg.
Total amount of steel @50=Rs.11200
Binding wire =2.24Kg.
same here dear same answer
hahahah
Bai app ko 48 mm subtract krna tha app ny 48 mm ki jaga 480 mm subtract kr dia Hy 😊😊
Love you 🎉 Bhai
Sir please elaborate how it comes
Bhai tum marketing thodi kam karo ... education ko marketing ki kuch jarurat nahi ...my honest review
Free me jitna mil Raha le lo thoda bhut to sabhi karte h bhai
Very good Trainer ,fantastic thank you.
सर् नमस्ते आपने बहुत ही अच्छी तरह आपने एक्सप्लेन किया आपका बहुत बहुत धन्यवाद 💐💐👏👏👏👏👏
Sir your teaching method is great ...God bless you
Thank you very much for your Love and Support . I appreciate your expression of support and goodwill. Let us continue to learn and share knowledge together.
Very good teacher I will be using your teaching when I will start building construction work thanks
Thank you very much sir,
Ye collage vale bhi itna shanti se nahi samjhate jitna aap ne samjhaya hai ,, thanks alot sir,❤❤❤❤
Thank you! Aapka pyaar humein aur bhi zyada inspire karta hai! Hamara lakshya hamesha se yahi tha ki hamara content aap tak sahi tareeke se pahunchaye aur aapko samajh mein aaye.
Is video me jo bhi aapne bataya wo mujhe phle se pata h ..Lekin aap itna acche se batate ho ki maine apka pura video dekha... Good job sir 🙏
Asad thank you for your words it motivates to make more video.. 👍 keep learning keep sharing 😊
Thank you so much you are the best teacher in civil engineering
Akash Bohare Sir 👍👍👍👍👍👍👍 explanation outstanding 🙏🙏🙏🙏🙏❤️❤️❤️❤️❤️
Sadik thank you for your support 👍 keep learning keep sharing😊😊
F2 footing total steel 480kg
Thankyou sir,
First time see easily you clearly BBS
No. Of Bar= 10 NOS in A direction and 10NOS in B Direction.
Cutting length in A direction= 1.552
Cutting length in B direction= 1.540
Total wt. In 1 Footing= 27.487
If 8 No. Of Footing then Total wt of all footing is = 220
Total Amount = 11,000 Rs
🙏Thanks for this lacture Dir
Gajab, 👍, m not diploma holder, but earning bread for my family due to your videos. Salute
Hello Sandeep Dogra
Thank you so much for your good wishes. I greatly appreciate your love and support.
Keep Learning, and Keep Sharing.
Best teaching of Bbs in Utube.. Outstanding sir.. Please upload Beam,column, staircase, slab
What about chair
The video has been made in a very beautiful way
Best Teacher In The Family 💯
Thank you sir... 3-4 Lakh deke college/Institute me vi itna easy way me nhi sikhata hai... Love you sir
Hello Sir gd evening.. I hope you Will good .. Very knowledgeable video sir... Thanks for giving this information sir.. God bless u 🙂
Aap kamal hoo sir thank you so much .Kitna easily understand karwaya .
Bohot hi clear samjhaye ho sir. Dimag me chap gai calculation.
Very nice बहुत बहुत धन्यवाद भाई साहब हमेशा खुश रहो मुसकुराते रहो
Best teacher in on RUclips 🙏🙏🙏
Thanku so much for this video sir ,
Today I have learn how to find BBS Footing
Learn a lot from u Sir,hope I can learn much from ur videos
Thank you sir ji for helping me to clear the Concept ❤️😁
Now this is called a Quality Content ❤️👷
Thank you
ironman
Hame bohat khusi hai ki aapko hamari mehnat pasand aai , Civilguruji isi tarah civil engineers ko aage badane ke liye mehnat karte rahega aur aap bhi knowledge dusro ko share karte rahe.
KEEP LEARING, KEEP SHARING.
Sir your explanation is outstanding
Good job sir apki waja say bahoot information hasil hoi
From Pakistan 😍
Hello Hashim Abbas
Thank you so much for your good wishes. I greatly appreciate your love and support.
Keep Learning, Keep Sharing.
Thank you to Civil Guruji.🙏
Bahut badhiya batate hai aap thank u so much god bless you
Tq soo much sir... Realy clear coaching... 🙏🙏🙏
excellent calculation of number of one footing bars , cutting length & weight 👍👍#
Sir you are very good trainer .
Thank u very much .
Dowel bar in column to footing for more load transfer .,is it provide or not if provide
How to cutting and place
One video pls .thanks again
Best RUclips channel for civilians
Gd evening sir.. I am manish from bihar... I am diploma holder... I am big fan of u and for civil gurujii platform..
Footing f2 = 8 nos
To find :-
Cutting length :- A direction :- 1.55 meter.
B direction :- 1.52 meter.
Total weight :- 218.24 kg
Total amount if rate rs 50/kg :- 10912rs
Binding wire:- 2.18 kg..
You are awesome, mind-blowing, outstanding, miraculous, prodigious, wonderful, amezing love you sir❤️❤️
Thank you keep learning keep sharing
Thank u so bahut Achcha samajh Gaye
Congratulations super work continues to make videos good knowledge
Bar A = 1.55 MTR
Bar B = 1.52 MTR
TOT W = 224 KG
TOT AMT = 11200 RUPEES
BINDING WIRE = 2.24 KG
Tnk u so much sir 🙏🏻
sir great work i mean unmatchable sir they way you delivered the lecture dil se respect guruji
love from neighboring country
Qadir thank you 👍 keep learning keep sharing
👍
Bahot hi umda video sir jee maza aa gaya 👍👍👍👍
Number of bars along the B direction= 9 nos
Cutting length along A direction=1.65 meter
100mm bend
Cutting length along B direction=1.62 meter
88mm bend
Total Steel quantity=209kg.
Total amount of steel @50=Rs.10,450Rs
Binding wire =2.9Kg.
Binding wire is 2.24kg
Total wt of steel in footing is 224kg
Total cost of footing is 11200rs@ 50rs/kg
Cutting length A is 1.55m
..........................B is 1.54m
Total no.Of steel along A@B is 20nos.
Is right sir and thankyou very much civil guruji...
Than Q for ur information. At time 14.31, kindly ud u mention the internal distance of U bar. So that it will be more clear.
Thanks sir itna easily se apna question ko samjhya sir very good sir
Thank you
ASADULLAH
Hame bohat khusi hai ki aapko hamari mehnat pasand aai , Civilguruji isi tarah civil engineers ko aage badane ke liye mehnat karte rahega aur aap bhi knowledge dusro ko share karte rahe.
KEEP LEARING, KEEP SHARING.
You explain amazingly sir
Kindly make a video for high rise buildings and also about best practices to make a basement from excavation to waterproofing
Cutting along A direction 1.65
Cutting along B direction 1.62
No of bars along A direction 10
No of bars along B direction 10
Total weight 232.4 kg
Weight of binding wires 2.32 kg
Very easy to understand...hats off sir
Very Helpfull video
Thanks a lot sir❤❤
I think in this group you are the super duper sir nice your teaching style than others
We appreciate your recognition of our hard work, Civil Guruji Isi tarah Civil Engineers Ke liye Content laate rahega.
Keep Learning, Keep Supporting.
Sir im from nepal I really want to teach alot im in starting point but here isnt any those kind of insut sir
Super excellent 💥💥💥 got to learn which clg doesn't teach
Superbly explained....
F2 footing
Cutting length of A axis = 1.55 m
Cutting length of B axis = 1.52 m
Total weight = 224 kg
Total amount = 11200 rupees
Binding wire = 2.24 kg
Thank you so sir 💕
Total amount @ rate 50 = 11200 rupees
What wastage parcentage will be added
very very important video
thank u for making this video
sir
Pk motivation welcome for your valuable words... It motivates us keep learning keep sharing 😊
Thank you sir best teacher bhuta ache se samjha m aay sir mujhe drawing se quantity nikalna shikha na hai
yrr ap bht acha samjhty ho
Thank you
Nafees Kiyani
Hame bohat khusi hai ki aapko hamari mehnat pasand aai , Civilguruji isi tarah civil engineers ko aage badane ke liye mehnat karte rahega aur aap bhi knowledge dusro ko share karte rahe.
KEEP LEARING, KEEP SHARING.
thank u sir acche se samajh aa gya
Most welcome @CivilWalla-gc5rb
Agar koi sawal ya suggestion ho to jarur btaiye.
Thank you so much sir.... very very clear and exalant video sir... thank you very much sir
Sir practically karte hue acche se samajh mein aata
Fill this Form :-forms.gle/ZVSSrwRfrPzf2QyV8 or Give us a Call On 9111001234. Our Team Will help you.
sir intehayee behtareen video likin ap quantity course ka keh rahe hai o to sirf india mai hai ap please qs course videos mai upload karo taa k hm pakistan mai bhi fayeda othayen thankyou
Hello @JBAssociates93
QS ka course all over in word me available hai.
Aap hume 9111001234 par whatsapp message kijiye hamari team aapki help kar dengi.
Your explanation is outstanding sir
Please upload a video on BBS of Staircase
Angshuman sure my next video will be on Staircase... keep sharing for training call 9111001234
👍
F2 cutting length direction A along a bar=1.552 m
Cutting length direction B along a baar = 1.528m
Total weight of steel=219kg
Total amount rate according to 50/kg= 10950
Great
Good
Wrong ha tumhara tolal-224 kg h
Hi
Please explain me this
Bahut achha samjhate ho aap
To find
Answer.
1) Cutting length = 1.65m
2) Cutting length = 1.62m
3) Total weight = 232.56kg
4) Total amount = 11,628₹
5) Binding wire = 2.32kg
Cutting length of bar along A direction=1.55m
Cutting length of bar along B direction=1.52m
Total weight of steel=219Kg
Total amount if rate Rs 50/kg=Rs10950
Binding wire 1% of total weight of steel=2.19kg
Asif well done very good your answer is correct✅ keep learning keep sharing😊
@@user-me5iz8ge1c 24 kaise hoga
Cutting length of bar along A direction=1.552 m
Cutting length of bar along B direction=1.528m
Total weight of steet=219kg
cost of total steel @50rs/kg=10950 Rs
Binding wire=2.19 kg
Total wt. Of steel in 8 footing=197.14kg hoga
Total weight of steel = 224 kg
Bahot achchha jankari di sir aap ney Sukriya
Excellent work..
Very helpful video..
Keep going
Sir g main na footings part b ki quantity nekale hain app check kera ka ok hain yah nehi
MOST VALUABE INFORMATION ABOUT BBS
No one provide us such type of knowledge.
CIVIL GURUJI is the best platform to gain those skills.
THANKS YOU SO MUCH SIR AND YOUR TEAM.
LOVE YOU FROM ODISA SIR.❣
Dabol jali L lenth theory,
Thanku so mch sir....itne easily apne ache se smjha Dia..
Welcome
Kishan Thakur
Hame bohat khusi hai ki aapko hamari mehnat pasand aai , Civilguruji isi tarah civil engineers ko aage badane ke liye mehnat karte rahega aur aap bhi knowledge dusro ko share karte rahe.
KEEP LEARING, KEEP SHARING.
Interesting information sir. Luff it.
Plz make video about..BBS of different types of stirups in column
Bahut mast hai ❤❤❤ badhiya hai 👍👌👌👌👌❤❤❤
Thank you! 😊❤️ Itni acchi feedback milke sach mein khushi hui! Aise hi support karte raho, aur hum aur bhi zyada mast content lekar aayenge. Stay tuned! 🙌🎉
Sir mera ek question hay
What is the importance of Bill of steel and how much Percentage it should be of the total amount of building??
No of bars for A =10 for B =10
Cutting length for A=1.56, for B= 1.53
Total steel =(8×27.47)=219.76kg
Good explanation Sir.....thank you.
Thanks Sir god bless you from Nepal
Thank you so much for your good wishes. I greatly appreciate your love and support.
Achha bataya sir ji🎉
Really awesome lecture sir......
Phoen thank you so much😊
Cutting Length = 1.55 &1.52m
Total weight = 224 kg
Total amount = 11,200 Rs
Binding wire = 2.24 kg
☺Thank you Sir.।।।।
Sir column ke upar aisi hi interesting video leke aaiye 🙏please
Sure 😈 Demon
Humne apke request ko apne expert trainer ke sath share karenge aur bahut jald iss topic par hum video lnayenge.
Nos of bar in both direction =10, 10
C. L of RA=1.55
C. L of RB=1.52
Wt of steel in A direction=13.77
Wt of steel in B direction=13.51
Total Wt of one Footing=28 Kg
Total Wt of F2 Footing=28*8=224 Kg
Unit rate of steel=60 Rs/kg
Total amount of steel=13440
Contingency of binding wire=2.24kg
Please check and mention correct Or not
Same bro
Same
You are absolutely correct 👍
Or sab aapne bhut ache se samjaaya thanks
God bless you sir 🙏🙏🙏
Thank you very much for your Love and Support . I appreciate your expression of support and goodwill. Let us continue to learn and share knowledge together.
Sirji bahot badiya video
Thank you
Nitin Gaikwad
Hame bohat khusi hai ki aapko hamari mehnat pasand aai , Civilguruji isi tarah civil engineers ko aage badane ke liye mehnat karte rahega aur aap bhi knowledge dusro ko share karte rahe.
KEEP LEARING, KEEP SHARING.
Very nice knowledge sir.
Estimation and valuation ke free lecture leke aao Bo bhi practical data ke ...
You are best techar
Thank you very much for your Love and Support . I appreciate your expression of support and goodwill. Let us continue to learn and share knowledge together.
Acche se samaj aaya
👍
Extra ordinary video hai sir...
Thank you so much sir vry nice teaching
Thanks sir helpfully video
बहुत बढ़िया
Dear Sakshi construction
Thank you for your kind wishes. Your support is greatly appreciated. We will continue to strive for excellence and share our knowledge with others. Thank you again for your encouragement. Keep Learning, Keep Sharing.
Footing 2
10 No. Of bars on both directions
Cutting length on the main bar is 1.55m
Cutting length on the distribution bar is 1.53m