Sweep Frequency Response Analysis (SFRA or FRA) Test of Transformer || Analysis of SFRA Test results

Поделиться
HTML-код
  • Опубликовано: 4 ноя 2024

Комментарии • 8

  • @tjjanarthananx
    @tjjanarthananx 2 месяца назад

    Sir, could u please tell, open ckt-bushing.. Short ckt- winding(gen probe).. What is difference between bushing & winding connection..
    Both are same place in trsnsformer,?

  • @surendrakverma555
    @surendrakverma555 Год назад +1

    Very good. Thanks 🙏🙏🙏🙏

  • @chandanjana6964
    @chandanjana6964 10 месяцев назад +1

    Thnx sir.

  • @gopalpillai9190
    @gopalpillai9190 9 месяцев назад

    What about old transformer where there is no SFRA test performed , If the transformer is operational ,is it reccommended to reserve the test result. what should be the PM cycle for such test 5years , 10yrs or any schedule.

  • @md.farhadhossain2378
    @md.farhadhossain2378 Год назад +1

    if we compare the factory and site test reports and see magnitude are different. then what steps taken for good transformer condition?

    • @360Engineer01
      @360Engineer01  Год назад

      If factory and site test reports are different (more than tolerance), then problem of the transformer has to be identified with other tests like TTR, WR, Magnetic Balance etc.

  • @neerajlamba232
    @neerajlamba232 Год назад

    Line reactor or bus reactor per full details video bana plz