  • @Mr.passuu
    @Mr.passuu 5 месяцев назад +2

    Mam glad to see ur photo on institute dashboard.😍

  • @beliver116
    @beliver116 14 дней назад +2

    Last Q 13 is wrongly solve

  • @niteshsurati1688
    @niteshsurati1688 5 месяцев назад +10

    Mam aapne galat bataya hai network diagram of questions 13 of points CFE intersection at point 4

  • @beliver116
    @beliver116 14 дней назад

    Total float bhi sahi karlo 12,0,12,0,0,0,0,0
    LFT bhi sahi karlo 15,11,16,15,16,16,29,40
    Critical path
    B-D-E-G-H 40 DAYS
    B-F-G-H 40 DAYS
    LAST F OR G POINT KI PERCENTAGE SAHI HAI