Are there any shortcut to copy and the paste existing activity codes ? I ve got 300 activity project all activity codes are same but i have to assign them one by one any shortcut ?
Select one then open assign code then press control and select the activities to assign similar code. then select the code and assign. if you need a video on it share your file on Softedemy@gmail.com thanks, an apology for the late reply.
My preference is to build a schedule utilizing a WBS, in a traditional manner, to lay out the projects deliverables and workflow. I would then use Activity Codes to supplement the ability to group, filter, and sort project data, therefore, enhancing performance analysis and reporting. I have also utilized project structures where the WBS was built out to a level 3 or 4 and then activity Codes were used for the remaining project levels. Project integration to Master Projects, owner requirements, and project management principles are other factors to consider when deciding how to structure projects.
The following are WBS attributes that cannot be performed and/or utilized by Activity Codes. WBS Summary Activities: A great way to highlight a Level 2 Schedule with a neat waterfall flow and to manage resources and costs at a rolled up level WBS elements can have Notebooks assigned WBS elements can have Work Products and Documents assigned Security can be assigned at the WBS level Thresholds, Risks, and Issues can be monitored and tracked at the WBS level Budgets, Spending Plans, and Budgets Logs can be managed and tracked at the WBS level Copying activities is a much easier task when grouped by WBS Earned Value attributes including WBS EV Milestones can be set at the WBS level The Tracking View is designed to use WBS elements Long range Resource Planning can be performed at the WBS level Projects can be summarized to specific WBS levels
WhatsApp:wa.me/+923155537580
Website : www.softedemy.com
For any query contact us on our email : info@softedemy.com
Thanks for this great lecture much useful to me.
You are welcome!
@@SoftEdemy do you have oil & gas construction project P6 file?? If it is pls share me to paramesh869@gmail.com
Are there any shortcut to copy and the paste existing activity codes ? I ve got 300 activity project all activity codes are same but i have to assign them one by one any shortcut ?
Select one then open assign code then press control and select the activities to assign similar code. then select the code and assign. if you need a video on it share your file on Softedemy@gmail.com
thanks, an apology for the late reply.
Thanks, great content by the way what is IPCs??
Interim payment certificates.
Thanks a lot, it's so good lesson
Glad you liked it!
nice video, you helped me finally figure out this assignment. Before this video, I was beginning to think maybe I was just retarded.
Thanks for your valuable comment.
thank you so much
Welcome
Thank you a lot,I love this
You're welcome 😊
SoftEdemy would you be able to post me the Villa Construction Project? Uzahradnik59@gmail.com
How Activity codes are different from WBS
My preference is to build a schedule utilizing a WBS, in a traditional manner, to lay out the projects deliverables and workflow. I would then use Activity Codes to supplement the ability to group, filter, and sort project data, therefore, enhancing performance analysis and reporting. I have also utilized project structures where the WBS was built out to a level 3 or 4 and then activity Codes were used for the remaining project levels. Project integration to Master Projects, owner requirements, and project management principles are other factors to consider when deciding how to structure projects.
The following are WBS attributes that cannot be performed and/or utilized by Activity Codes.
WBS Summary Activities: A great way to highlight a Level 2 Schedule with a neat waterfall flow and to manage resources and costs at a rolled up level
WBS elements can have Notebooks assigned
WBS elements can have Work Products and Documents assigned
Security can be assigned at the WBS level
Thresholds, Risks, and Issues can be monitored and tracked at the WBS level
Budgets, Spending Plans, and Budgets Logs can be managed and tracked at the WBS level
Copying activities is a much easier task when grouped by WBS
Earned Value attributes including WBS EV Milestones can be set at the WBS level
The Tracking View is designed to use WBS elements
Long range Resource Planning can be performed at the WBS level
Projects can be summarized to specific WBS levels
@@SoftEdemy Thanks for your reply your time efforts, I really appreciate and god bless you for your work.
@@Mahrash welcome. Thanks for commenting.