Thanks for you lessons🙏 please, how can one assign same resource twice to a particular activity? For example, during painting activity and I want to assign to painters to this activity while I already created one painter resource. How do I assign two painters in this picture?
Same ID resource to an activity cannot be assigned. 2 painter means 16 hours you will assign double units to the resource. It means the same or go to user preferences and change units to days and than in resources change budget units / time to 2 nos / day than change duration type to fixed duration and budgeted units/time
It's 3 year old video. May be at update datr at that time is 15 February . The update date is based on period of reporting like if weekly ends on Fridays than on Friday 4:00 PM and if months end then 30 pr 31st of month. I hope you understand. These reporting periods are predecided
sorry i couldn't understand your question. if your programme is not following the sequence while scheduling check below video link. ruclips.net/video/IMuEOk6Y3JU/видео.html Also for any help you can contact at our whatsapp number wa.me/+923155537580
@@SoftEdemy thanks for response so quickly. I made a progress update of activity started on 16 April. It has a FS relationship to next activity. When I click schedule next activity does not start at completion of 1st activity. Instead 2nd activity starts from data date.
@@stalluri11 If Successor activity have been assigned with FDS Relationship and on updating predecessor activity until 100 percent the successor activity will not start. May be possible your remaining duration is 0 . in case of 0 the successor activity will be schedule to start after data date. The other meaning i understood is that you are thinking that after completion of your first activity .The successor activity should be start updated. While updated manually you have to assign an actual start to each activity ,which have been started upto data date. If you did not started any activity whose predecessor is completed than it will be automatically start after data date earliest. if you want to automatically update the activity watch below linked video. it would help you to understand. How to Apply Actual Auto Compute Progress | Primavera P6 |19.12 | Advanced Tutorial ruclips.net/video/7O8ha7VnNW8/видео.html More Progress update relevant informative videos are below. How to Create Activity Steps to Update Physical Progress | Primavera P6 |19.12 | Advanced Tutorial ruclips.net/video/FHoN_3vwBGg/видео.html Update Progress using Activity Steps | Create Template | Performance Percent | Primavera P6 | Tips | ruclips.net/video/0keoRZiVV3k/видео.html How to use progress line to monitor activities performance in Primavera P6| Show delays graphically ruclips.net/video/e0vY5fr7lBY/видео.html How to update progress from excel to Primavera P6 | Beginners tutorial | update duration percent | ruclips.net/video/aZjcQN7Pr1M/видео.html
@SoftEdemy if activity started on 16 April with 5 days duration. It should finish on 21st. The next activity should start on 22nd as there is FS relationship. Doesn't make sense in schedule the 2nd activity starts on dat date which is 16 April.
@@stalluri11 yes you are right their may be something you are doing wrong. I have to look into the your schedule remotely. Contact at my whatsapp wa.me/+923155537580
Sure,I am busy with other stuff right now.Soon we will update our channel with latest and new videos. you can watch our pinned videos and earned value management videos that will cover all your queries.
@stalluri11 Good question, Your first activity is finishing on 24 April 2023 may be 2 o clock or may be in morning 9 o clock or else. That's why in precise same day one activity is finishing and next is starting. The reason is simple . P6 is precise to schedule upto one minute Check the time of activities also Go to user preferences and time see the time option and turn on 12 or 24 format. See the activities have middle day timing or else but in same day dates.
Planned dates are basically your baseline dates. Whenever you change your data date your current dates will movie accordingly if you haven't achieved your lookahead progress then there will be a negative float. Simply in your words, your current dates will vary from your planned dates. If your SPI is in the range of 1+or -0.25 and your schedule is realistic as per work then your revision of schedule is less otherwise you have to revise it every month. So the perfect answer to your question is that a perfect plan with targets achieve on time will not mismatch your planned dates with the current.
The easiest way to freeze your end dates is to apply the longest path filter and improve the Relationship and decrease the duration per activity until you achieve zero float. this practice can work only to decrease the 30 percent duration of your project. Further, you need extension time events and approval from clients with a new baseline schedule
Not matter but earned value is calculated on basis of performance percentage. And performance percentage or duration unit or physical percentage all of them
Thanks for you lessons🙏 please, how can one assign same resource twice to a particular activity? For example, during painting activity and I want to assign to painters to this activity while I already created one painter resource. How do I assign two painters in this picture?
Same ID resource to an activity cannot be assigned. 2 painter means 16 hours you will assign double units to the resource. It means the same or go to user preferences and change units to days and than in resources change budget units / time to 2 nos / day than change duration type to fixed duration and budgeted units/time
@@SoftEdemy oh, thanks so much, sir
The 16hrs/day is it only for that particular activity or overall activities on the program?
@@reginaldibenne6875 particular activity where you required. You can change for all
@@SoftEdemy That's so nice of you🙏
During schedule time why you select 15 February instead of the current date, could you please explain
It's 3 year old video. May be at update datr at that time is 15 February .
The update date is based on period of reporting like if weekly ends on Fridays than on Friday 4:00 PM and if months end then 30 pr 31st of month. I hope you understand.
These reporting periods are predecided
Moreover we have update progress tools check at www.softedemy.com/shop
@@SoftEdemy because when am update the schedule I used to put the current date but it’s changing the entire schedule date.so am confused .
@@MrJithingopal143 it will change your entire schedule dates . If you haven't performed the during update period
@@SoftEdemy yes that’s what my question is, how we know the update period.
WhatsApp:wa.me/+923155537580
Website : www.softedemy.com
For any query contact us on our email : info@softedemy.com
Very simple to understand..keep it up
Keep watching
very informative
When I update progress and then click schedule program is not using completed dates with next activity although it has a FS relationship
sorry i couldn't understand your question. if your programme is not following the sequence while scheduling check below video link.
ruclips.net/video/IMuEOk6Y3JU/видео.html
Also for any help you can contact at our whatsapp number
wa.me/+923155537580
@@SoftEdemy thanks for response so quickly. I made a progress update of activity started on 16 April. It has a FS relationship to next activity. When I click schedule next activity does not start at completion of 1st activity. Instead 2nd activity starts from data date.
@@stalluri11 If Successor activity have been assigned with FDS Relationship and on updating predecessor activity until 100 percent the successor activity will not start. May be possible your remaining duration is 0 . in case of 0 the successor activity will be schedule to start after data date.
The other meaning i understood is that you are thinking that after completion of your first activity .The successor activity should be start updated. While updated manually you have to assign an actual start to each activity ,which have been started upto data date. If you did not started any activity whose predecessor is completed than it will be automatically start after data date earliest.
if you want to automatically update the activity watch below linked video. it would help you to understand.
How to Apply Actual Auto Compute Progress | Primavera P6 |19.12 | Advanced Tutorial
ruclips.net/video/7O8ha7VnNW8/видео.html
More Progress update relevant informative videos are below.
How to Create Activity Steps to Update Physical Progress | Primavera P6 |19.12 | Advanced Tutorial
ruclips.net/video/FHoN_3vwBGg/видео.html
Update Progress using Activity Steps | Create Template | Performance Percent | Primavera P6 | Tips |
ruclips.net/video/0keoRZiVV3k/видео.html
How to use progress line to monitor activities performance in Primavera P6| Show delays graphically
ruclips.net/video/e0vY5fr7lBY/видео.html
How to update progress from excel to Primavera P6 | Beginners tutorial | update duration percent |
ruclips.net/video/aZjcQN7Pr1M/видео.html
@SoftEdemy if activity started on 16 April with 5 days duration. It should finish on 21st. The next activity should start on 22nd as there is FS relationship. Doesn't make sense in schedule the 2nd activity starts on dat date which is 16 April.
@@stalluri11 yes you are right their may be something you are doing wrong. I have to look into the your schedule remotely. Contact at my whatsapp wa.me/+923155537580
Hi, Pls put video for how to update Actual cost and find EV, cash flow generation and etc...
Sure,I am busy with other stuff right now.Soon we will update our channel with latest and new videos. you can watch our pinned videos and earned value management videos that will cover all your queries.
@@SoftEdemy Thank you...
@@ravindrankrishnan2964 welcome,if you are in specific urgent problem than i can help you personally.
@@SoftEdemy Thanks. Not urgent., Pls put video as your wish...
@@ravindrankrishnan2964 Thanks we will but more precise and informative stuff soon.
Also, see How to update progress from excel to Primavera P6 | Beginners tutorial | update duration percent |
ruclips.net/video/aZjcQN7Pr1M/видео.html
Update Progress using Activity Steps | Create Template | Performance Percent | Primavera P6 | Tips |
ruclips.net/video/0keoRZiVV3k/видео.html
I am having a problem when I use FS relationship the next activity is starting same date as finish date of 1st activity
@stalluri11 yes FS means finish to start.
Finish or first activity than start of next activity.
@SoftEdemy finish date of 1st activity 24april. Start date of next activity is same 24 April. It should be 25 April right?
@stalluri11 you can understand complete about relationships by watching this link
ruclips.net/video/_ZBzpEM78Jg/видео.html
Relationships
@stalluri11 Good question,
Your first activity is finishing on 24 April 2023 may be 2 o clock or may be in morning 9 o clock or else.
That's why in precise same day one activity is finishing and next is starting.
The reason is simple .
P6 is precise to schedule upto one minute
Check the time of activities also
Go to user preferences and time see the time option and turn on 12 or 24 format. See the activities have middle day timing or else but in same day dates.
very helpful
Thanks for Commenting .Stay tunned with channel.
How to put new data date without changing planned dates??
Planned dates are basically your baseline dates. Whenever you change your data date your current dates will movie accordingly if you haven't achieved your lookahead progress then there will be a negative float. Simply in your words, your current dates will vary from your planned dates. If your SPI is in the range of 1+or -0.25 and your schedule is realistic as per work then your revision of schedule is less otherwise you have to revise it every month. So the perfect answer to your question is that a perfect plan with targets achieve on time will not mismatch your planned dates with the current.
For any further confusion, you can share your contact. I will guide you in case of any issues.
The easiest way to freeze your end dates is to apply the longest path filter and improve the Relationship and decrease the duration per activity until you achieve zero float. this practice can work only to decrease the 30 percent duration of your project. Further, you need extension time events and approval from clients with a new baseline schedule
SIR can u share this project to me.?
For any query contact on Softedemy@gmail.com
what if we do it by selecting
physical % progress instead of Duration %?
Not matter but earned value is calculated on basis of performance percentage. And performance percentage or duration unit or physical percentage all of them