You can pass your PMP exam! These 10 scenario-based PMP Waterfall Questions and Answers will help you gain the knowledge and methodology you need.
Questions 61 to 70 out of the 100 Waterfall questions and answers.
You can do it!
Timestamps:
00:00 Intro
00:40 Question 61: Types of estimating
03:49 Question 62: Control charts
06:32 Question 63: Planning resource management
08:32 Question 64: Finding the biggest impacts
10:29 Question 65: Positional power
13:15 Question 66: Closing a project
15.51 Question 67: Change management
18:31 Question 68: Accuracy and precision
21:30 Question 69: Tuckman's model
23:12 Question 70: Executives are dissatisfied
#pmp #projectmanagement #pmbok
Thank you David for the amazing videos, today i was able to pass my PMP with flying colours going through the agile, waterfall questions. cannot thank enough for helping....woot woot....
Thank you David, Believe me you are doing fantastic.
that is greta david , your queustions are making may exam prep easy , for the comming week after your questions tends to 200 water falll questions , may be that time will be my pmp exam hhh .
Sheesh these were challenging. Thank you as always
Thank you David
Thank you.
David, I love the questions. These are great. Question: Why are your questions not multiple choice, select all like the test will be?
I agree.. there should be variety in the question types
For 68 - does "clear" result mean "desired" result usually? Also wouldn't a "wide" range have lower precision? Like if your target was 50 and your results were 0,100,95,5 vs. 31,32,31,33 wouldn't the second one be the high precision/low accuracy one with a smaller range?
Good question. The only place I can see it in PMBOK 6 is page 238, "Cost Management Plan". It gives a pretty good explanation, but a slightly different scenario. Accuracy being the acceptable range (i.e +/- 10%) and precision being how much we round up or down.
Awesome @David! Is it possible to make some tutorials on CPI, SPI and other Project Management key Metrics for PMP Exams? Thanks
I have videos for these on RUclips and in my Udemy course. The course ones are nicer, but the RUclips ones are here:
EVM: ruclips.net/video/U4fGdpX1oIs/видео.html
Variance: ruclips.net/video/935oMt-XLHE/видео.html
@@davidmclachlanproject Thanks a million. Is possible to create an Excel Modeling Tool for all of them (CPI, SPI, EVM, EVA, EMV, etc?)
For question 66 have a doubt, i think the answer should be (a) because the exit criteria is also the part of project charter (pg 81 of pmbok 6).
Thanks
Fair comment! I will reword this slightly for my course. The Project Charter on pg 81 contains exit criteria and success criteria - these things are more about when to cancel (or continue) a project (i.e. have we met the benefits? or is the cost to continue too great?), not necessarily the steps we need to take to finalise a project once we've delivered it. Those steps are in the Close Project or Phase process.