Period of Removing Formwork For Beams Bottom & Slab Bottom
HTML-код
- Опубликовано: 10 янв 2019
- Type of Formwork Minimum Period
Before Striking Formwork
Soffit formwork to slabs 3 days
(Props to be refixed
immediately after removal
of formwork)
Props to slabs:
1) Spanning up to 4.5 m 7 days
2) Spanning over 4.5 m 14 days
Soffit formwork to Beams: 7days
(Props to be refixed
immediately after removal
of formwork)
Props to Beams:
1) Spanning up to 6 m 14 days
2) Spanning over 6 m 21 days - Игры
Tnx for explaining
Thankyou ❤
thanku sir
Thanks sirji...
Welcome
Sir can i remove (complete formwork) both at a time, props and bottom plates of slab after 7 days spanning under 4.5 m at any floor?
Okay you can remove.
But having sure all span is not more than 4.5m
Sir . ..4.5 , 6 m wali length kaise measure krna hai ..thora acche se bataie nh...
Ek support se dusre support ke bich ki beam length
❤️🙏👍
What is props
Jacky
Jack support
Vertical members which give support to the centring material
Spaen not spaaan 😂
bhai spaen nhi span hai 😂
Aur tu homo sapien hai