Period of Removing Formwork For Beams Bottom & Slab Bottom

Поделиться
HTML-код
  • Опубликовано: 10 янв 2019
  • Type of Formwork Minimum Period
    Before Striking Formwork
    Soffit formwork to slabs 3 days
    (Props to be refixed
    immediately after removal
    of formwork)
    Props to slabs:
    1) Spanning up to 4.5 m 7 days
    2) Spanning over 4.5 m 14 days
    Soffit formwork to Beams: 7days
    (Props to be refixed
    immediately after removal
    of formwork)
    Props to Beams:
    1) Spanning up to 6 m 14 days
    2) Spanning over 6 m 21 days