MS Project 2019 ● #6.3 Milestones Report ● Simple

Поделиться
HTML-код
  • Опубликовано: 27 окт 2024

Комментарии • 25

  • @karthikchordz
    @karthikchordz 2 года назад

    Hello. Many thanks for the video.
    I cant get the tick in the timeline when I mark the task as complete. Any suggestions how to enable this?

    • @vision6D
      @vision6D  2 года назад

      Hello,
      Thank you for your comment and question. Have you defined the task as a milestone or a task?
      Greetings from Geneva.

  • @infosportsmg
    @infosportsmg 5 лет назад

    Thanks for this video, How to create a weekly report with task evolution? thank you

    • @vision6D
      @vision6D  5 лет назад

      You are welcome. You have task reports in the report section or you can create your own report. Have a great day.

  • @heyfuckthepeople
    @heyfuckthepeople 4 года назад

    Hello. Thank you for the video!
    I have one question regarding the report - I have been working on another project template of yours and set the status date to 10th October. Before that date, there are two milestones (I marked complete 100%) and they appear in the milestone report in the third column. However, what about the third milestone (15th October)? It does not appear in the milestone report anywhere... I am a bit confused. I thought it would appear in the 'Milestones up next'...? I think I might have misunderstood it and would be grateful if you could clarify.
    Thank you,
    A.

    • @vision6D
      @vision6D  4 года назад +1

      It's an interesting point. I have recreated the situation and I arrive at the same situation as you do. I need to look at it closer and come back to you.

    • @heyfuckthepeople
      @heyfuckthepeople 4 года назад

      @@vision6D Thank you so much for your time and effort, I really appreciate it. I have only just started my adventure with MSP and I find your work extremely useful.

    • @vision6D
      @vision6D  4 года назад

      In which domain are you working?

    • @heyfuckthepeople
      @heyfuckthepeople 4 года назад

      @@vision6D Sorry, could you tell me what you mean by 'domain'?

    • @vision6D
      @vision6D  4 года назад +1

      Construction sector, IT, medical care, marketing, financial sector etc.

  • @uguruzun9202
    @uguruzun9202 4 года назад

    hey there, I do change the status date right before the milestone start date but I can't see the milestone as an upcoming milestone in the report.

    • @vision6D
      @vision6D  4 года назад

      Thank you for your question. The status date, is the project status date isn't it? What version do you have?

    • @uguruzun9202
      @uguruzun9202 4 года назад

      @@vision6D yes project status date. ms project 2013.

    • @vision6D
      @vision6D  4 года назад

      @@uguruzun9202 This was a long time ago for me. So I cannot reproduce the situation. Sorry for this.

  • @abraranis5096
    @abraranis5096 4 года назад

    not able to sign in, please guide

    • @vision6D
      @vision6D  4 года назад

      Thank you for your request. Where do you want to login?

    • @abraranis5096
      @abraranis5096 4 года назад

      @@vision6D from vision.com/download

    • @abraranis5096
      @abraranis5096 4 года назад

      @@vision6D guide me to download or visit you web site

  • @rookiemvp2008
    @rookiemvp2008 Год назад

    MS Project is so frustrating and it really does suck.

    • @vision6D
      @vision6D  Год назад

      May be with a better teaching you could go around your frustrations.
      Have a great day.